JOB SAFETY ANALYSIS WORK SHEET

PLANT/EQUIPMENT : Deathaizer Department: Mechanical /YGP Date: 05/08/2008


Area Division/Unit: deathanizer area & layedown yard JSA Number:
DESCRIPTION OF ACTIVITY: JSA for hydro test Activates for All New Piping and other areas where required at DE-Ethanizer area & laydown
yaard

Prepared by: Reviewed by: Approved by: Proponent Signature:


Khaled Ismail (Enppi Site HSE Mgr)
Sayed Abdeen (Enppi Q.C Mgr)
Abd Aaal Al Sayed (PTJ Hydro Test Eng.) Date: Date: Date:
Aymen Abdo (PTJ HSE Mgr)
Date: 05/08/2008
References: Saudi Aramco Construction Safety Manual, Project LPP, HIP , etc.

Safety Equipment: Full PPE , Fire extinguishers and Fire water hose and safety Harness

Serial SEQUENCE OF BASIC TASK POTENTIAL HAZARDS HAZARD CONTROLS


# STEPS
1.0 Scaffold Erection ( Falling • Falling Of Scaffold Crew Lead To 1.All scaffold structures shall be erected with metal
Protection ) Serious /Fatal Injuries component and approved by saudi aramco

• Structure Collapse 2. Scaffold erection plans (drawings) shall be


submitted to loss prevention department for review
• Equipment / Property Damage
prior to men being allowed to work on the scaffold.
• Improper Fall Protection
3. All fittings (couplers, clamps, etc.) shall be of a
• Improper Spacing metal type approved to ansi or equivalent
requirements. they shall be examined regularly and
• Inadequate Foundations care must be taken to ensure that moving parts are
sound and well lubricated and that threads are not
• Uncertified & /Or Inadequate Number
Of Scaffold Supervisors / Inspectors
stripped.
4. Planks shall not be painted or treated in any way
• Unqualified Scaffold Erection Crews that would conceal defects.

• Scaffold Drawings Not Submitted For


JSA for hydro test Activates for All New Piping and other areas where required at DE-Ethanizer area & laydown yard
1
Special Scaffolds 5. Planks shall be stacked on a suitable foundation.
where the height of a stack exceeds 20 planks,
• Scaffolds Not Properly Tagged Before
measures shall be taken to tie or bond succeeding
Use
layers.
• Unauthorized Alternation Of Scaffold 6. Planks shall be inspected for defects, including
Tags decay, prior to each use.

7. The design working load of each platform unit


(i.e., plank) shall be capable of supporting without
failure one or more 91 kg (200 lb) person with 22.7
kg (50 lb.) of equipment.

8. Each platform, where applicable, shall be


designed and constructed to carry a uniformly
distributed load. uniformly distributed loads and
person loading are not cumulative and the most
restrictive loading shall be used for platform design.

9. The ground or floor on which a scaffold is going


to stand must be carefully examined .

10. Concreteblocks, barrels, and other loose or


unsuitable material shall not be used for the
construction or support of scaffolding.

11. The base plate shall be of a type approved for


supporting scaffolding posts. (see manufacturer's
specifications.)

12. Scaffold erection crew shall be qualified.

13. Apply scaff tag system.

14. Scaffold crew shall equipped with ppe specially


fall protection equipment during erection and
dismantling.
15. Improve house keeping at scaffold plat form.

JSA for hydro test Activates for All New Piping and other areas where required at DE-Ethanizer area & laydown yard
2
16. Scaffoldsupervisors and inspectors shall be saudi
aramco certified .
2.0 Pressure Testing • Serious/Fatal Injuries From Pipe 1. Written procedures approved prior to testing shall be
Rupture &/ Or High Pressure followed
Water Blast 2. Piping, vessels, supports and foundations designed
for gas service shall not be overloaded by the extra
• Hazardous Waste Testing Fluids weight of the test liquid. Temporary supports and
braces may be required.
• No Distance Barricades 3. All Gasket shall be specifed according to standard
and to be premnatly used
• No Warning Signs 4. Hazardous gases or vapors must be vented clear of
any area where personnel are working or where there is
• No Preliminary Walkthrough any possible source of ignition.

5. Valves must isolate any ancillary equipment not


• Improper Disposal Of Test under test.
Fluids
6. Only calibrated test gauges shall be used and they
• No Traffic Control shall be mounted in the upright position. Pump
discharge gauges must be visible to the pump operator
for the duration of the test.

7. The equipment / vessel shall have adequate


vacuum relief capacity to avoid damage or collapse,
when draining the test liquid.

8. Tested line shall be supported and secured .

9. Lines shall be drained and dried mechanically when


the test liquid is corrosive or otherwise hazardous.

10. A system under test shall be depressurized (with the


exception of pressure due to a liquid head) before any
work is done to stop leaks or repair weakness, including
the tightening of bolts.

11. A block valve is required on the line from the test


JSA for hydro test Activates for All New Piping and other areas where required at DE-Ethanizer area & laydown yard
3
pump to the equipment under test.

12. Air shall not be used to displace test fluid from


underwater equipment unless it has been determined
that the equipment will not float.

13. Warning signs and preliminary walkthrough shall be


involved at site area.

14. Distance barricades must be at work area.

15. The traffic shall be controlled through prepared the


traffic plan.

16. Check and verify the system for corrosion or


other aspects that can affect the piping system integrity
while hydro testing.

17. An accessible bleed valve shall be provided for


the protection of the piping system in case an immediate
depressurizing is needed.

18. Water is the hydrotest media.

19. Air shall be vented from the system before


hydrotesting start.

20. Pressure shall be increased gradually with 10


minutes hold at each step, no rapid change in pressure.

21. Relief valve setting to be verified by plant


process and/or instrument engineer to ensure its
adequacy.

22. Minimum of two pressure gauges with block


and bleed valves shall be provided on the system.

23. Release permit shall be issued along with other


permits required for this activity.