Falck Onsite: Lifting Plan (As Required by Reg 8 LOLER)

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Falck Onsite

Lifting Plan (As required by Reg 8 LOLER)


Location: Falck Onsite Date:

Description of Load: Weight of load:

Task:

1. Weight of load unknown 8. Load has sharp edges 15. Hazards to personnel
2. High centre of gravity 9. Extremely heavy load 16. Communications
3. Unstable load 10. No lift point above load 17. Tag lines required
4. Awkward size/shape 11. Restricted headroom 18. Poor light conditions
5. Fragile load 12. Confined work area 19. Test lift
6. No dedicated lift points 13. Conflicting operations 20. PTW restrictions
7. No dedicated rigging 14. Lift equipment condition 21. Other (Specify)
Step by step lifting plan (including any key personnel and their responsibilities):

1. Banksman to check rigging loft for availability, suitability and serviceability of all equipment
2. Banksman to conduct toolbox talk prior to task, including a walk around the area and setting up barriers
3. Select suitable equipment, load to be slung under supervision of the Banksman, move crane into position (do
not lower hook)
4. Banksman to check slinging of load. If Banksman is happy, lower crane hook towards the load, slingers to
attach load to crane hook
5. Ensure slingers are in a safe position, Banksman to check crane alignment, conduct test lift and ensure load
stability
6. Test lift conducted, move load in a safe and controlled manner, sling angle to remain at 90° or less, slingers to
control movement by means of taglines
7. Once load arrives at landing area, lower slowly check positioning of slingers, conduct test drop
8. Once test drop has been confirmed, lower load completely and slingers to de-rig when safe to do so
9. Check all equipment for damage and return to rigging loft (report any damaged equipment immediately)
10. Conduct detailed de-brief

(Continue over to provide additional information & sketches)


Personnel Required: Crane Banksman 2x Slingers
(e.g. Crane Op, Banksman) Op
Communications Method: (Tick) Hand signals: X Verbal: Radio:

Required materials list:

Risk Assessment performed? Yes: X Ref No. (if applicable): RA-FO 002 (attach copy to plan)

Final checklist – if you answer ‘yes’ to all the ‘applicable’ questions below then the lift may proceed
1 Have all identified hazards been risk assessed? Have suitable controls been put in place? Yes X N/A
2 Is lifting equipment correctly rated and certified with all slings and lift points visually checked? Yes X N/A
3 Has the lift path been selected and cleared of obstructions and/or conflicting operations? Yes X N/A
4 Is the laydown area(s) adequate in both size and load bearing capacity? Yes X N/A
5 Are suitable materials available for protection of the load/slings while landing the load (eg timber)? Yes X N/A
6 Have barriers been positioned and/or suitable warnings issued to prevent unauthorised access? Yes X N/A
7 Have you confirmed the laydown area is within the operating range of the crane? Yes X N/A
8 Have weather conditions and their effect on the safety of the lift been taken into consideration? Yes X N/A
9 Has a meeting been held to discuss, plan and do all personnel involved fully understand the plan and Yes X N/A
has all relevant information been passed on to all parties?

Lift planned by: Anthony Swales Signature:

Position: L.A.P

You might also like