Professional Documents
Culture Documents
43.8D - 20456 - Cyl Bottom - Thread Perpendicular Issue
43.8D - 20456 - Cyl Bottom - Thread Perpendicular Issue
Status Report No 21
8D REPORT Com.Date 12.9.20
Closed VQPR #
Report date
D0 - Symptom of failure (As seen/reported by the customer)
Prepared by Karthikeyan
G3/8 thread is not in line with sealing surface on the cyl bottom .
D3 - Containment actions
Check List Quantity Containment actions planned Resp Action status
3.1 Stocks at Customer 150 Segregation done 1 no found rejection - Complete
3.2 Stocks in transit 0 -
3.3 Finished Goods stock 0 -
3.4 Waiting for FI&T 22 All the available parts inspection done Vijayakumar Complete
3.5 WIP - Inhouse 0 -
3.6 Stocks at Stores 0 -
3.7 WIP - SCs and Vendors NA -
3.8 At other locations if any NA -
3.9 At newtech Stock 0 -
*Abbreviations: RPN-Risk priority number, FI&T - Final inspection and checklist, WIP - Work in progress, SC - Sub contractor
email communication hence unsigned
Page: 2/2
Predrill hole was not center for tapping Verify VMC operation Found ok
Insufficient part clamping surface and pressure Verify Clamping method & Fixture Significant
Inadaquate operator training for burr clean before every part clamping Cross verify Found ok
Tap worn out Verify Tool condition & Tool life monitoring check sheet Found ok
Sealing surface and threading operation not doing same setup Verify Program Found ok
OP#60-
OP#20- OP#30- OP#40- OP#50-
OP #10 - Number
Band Saw CNC CNC VMC
Incoming punching and
Cutting Turning 1 Turning 2
Inspection engraving
OP#80
OP#-90 Cleaning OP #70 Final
Despatch to oiling and Inspection
Customer packing
Root Cause : Part slightly tilted while Threading operation Running due to insufficient part clamping .
Corrective Action: We have implement our part clamping method .We have make part profile fixture instead of clamping pad for VMC operation .
Root Cause : Perpendicularity check point not cover inprocess and final inspection report .
Corrective Action : We have provide training about thread perpendicularity issue and Impact.We will add thread perpendicularity check point in process and final
inspection Report.
Inprocess and Final We have plan to add thread perpendicularity checkpoint in our inprocess and final
inspection Not add thread perpendicularity value in our inspection reports inspection report.
Clamping pad we has used for part holding purpose in VMC operation location bore done on 4th axis table to avoid burr holding and
Improve the part clamping pressure To avoid part tilting issue
while Threading operation .
Subhash &
Vijayakumar
/Compleed
We have add thread perpendicularity value in our inprocess and final inspection
No Check point for thread perpendicularity verification report
ACTION PLAN
We have make new fixture for vmc operation
We have add thread perpendicularity value in our inprocess and final inspection report.
We have provide training about thread perpendicular and its impact. Responsibility &Target
date
Display one point lession all the respective areas .
Problem Identified CAPA agreed CAPA Implemented, Under monitoring Issue closed & signed off
email communication hence unsigned
Page: 3/3
THEME PROBLEM:Thread Not inline with sealing surface DATE OF PREPARE 31.05.2021
Here after
dont use
Clamping
Thread
pad for VMC
perpendicular
operation
Value add in
.We need to
Inspection
use only
Reports
Fixture for
VMC
operation
TRAINING RECORD
NAME SIGNATURE DATE TRAINER NAME PREPARED BY
Vasanth Production Engineer Karthikeyan
Manikandan Operator
Kajendran Operator
Sudhen Quality engineer 31.06.2021 Vijayakumar & Subhash
APPROVED BY
selvi Final Inspector
Vijayakumar
Vijayalakshmi Final Inspector
Buvaneshwari Packing