RESUME PERHITUNGAN VOLUME

PEKERJAAN GALIAN DAN TIMBUNAN PANEL


DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (12 AGUSTUS 2021 - 29 AGUSTUS 2021)

HASIL OPNAME PEKERJAAN GALIAN DAN TIMBUNAN

NO. ITEM PEKERJAAN KUMULATIF PERIODE KE-15 OPNAME PERIODE KE-16 KUMULATIF PERIODE KE-16
S/D 11 AGUSTUS 2021 29 AGUSTUS 2021 S/D 29 AGUSTUS 2021 KETERANGAN
M3 M3 M3

1 Galian Tanah 288,986.648 17,862.505 306,849.153


2 Timbunan Panel 15,734.683 3,859.698 19,594.380

CATATAN :

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (12 AGUSTUS 2021 - 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 0 + 000 s/d 0 + 450


GALIAN
LUAS (M2)
JARAK VOLUME
NO. STA LUAS LUAS
PENAMPANG (M2) RATA-RATA (M2) (M) (M3)

1 0 + 000 -
- 0 -
2 0 + 025 -
58.559 5 292.793
3 0 + 050 117.117
93.941 25 2,348.513
4 0 + 075 70.764
77.531 25 1,938.275
5 0 + 100 84.298
84.292 25 2,107.300
6 0 + 125 84.286
83.022 25 2,075.550
7 0 + 150 81.758
81.467 25 2,036.675
8 0 + 175 81.176
87.200 25 2,179.988
9 0 + 200 93.223
85.423 25 2,135.563
10 0 + 225 77.622
77.034 25 1,925.838
11 0 + 250 76.445
78.182 25 1,954.538
12 0 + 275 79.918
77.303 25 1,932.575
13 0 + 300 74.688
72.130 25 1,803.250
14 0 + 325 69.572
66.460 25 1,661.500
15 0 + 350 63.348
53.767 25 1,344.163
16 0 + 375 44.185
22.093 25 552.313
17 0 + 400 -
75.929 25 1,898.225
18 0 + 425 151.858
157.886 25 3,947.150
19 0 + 450 163.914

Sub Total 32,134.205

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (12 AGUSTUS 2021 - 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 0 + 450 s/d 0 + 900


GALIAN
LUAS (M2)
JARAK VOLUME
NO. STA LUAS LUAS
PENAMPANG (M2) RATA-RATA (M2) (M) (M3)

Sub Total STA 0+000 SD STA 0+450 32,134.205

19 0 + 450 163.914
161.223 25 4,030.563
20 0 + 475 158.531
164.133 25 4,103.313
21 0 + 500 169.734
153.618 25 3,840.450
22 0 + 525 137.502
136.288 25 3,407.188
23 0 + 550 135.073
169.219 25 4,230.475
24 0 + 575 203.365
221.373 25 5,534.325
25 0 + 600 239.381
191.674 25 4,791.850
26 0 + 625 143.967
156.177 25 3,904.425
27 0 + 650 168.387
169.422 25 4,235.550
28 0 + 675 170.457
151.283 25 3,782.075
29 0 + 700 132.109
121.363 25 3,034.063
30 0 + 725 110.616
109.205 25 2,730.125
31 0 + 750 107.794
105.331 25 2,633.263
32 0 + 775 102.867
126.541 25 3,163.513
33 0 + 800 150.214
218.072 25 5,451.788
34 0 + 825 285.929
177.194 25 4,429.838
35 0 + 850 68.458
270.907 25 6,772.663
36 0 + 875 473.355
447.469 25 11,186.725
37 0 + 900 421.583

Sub Total 113,396.393

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (12 AGUSTUS 2021 - 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 0 + 900 s/d 1 + 350


GALIAN
LUAS (M2)
JARAK VOLUME
NO. STA LUAS LUAS
PENAMPANG (M2) RATA-RATA (M2) (M) (M3)

Sub Total STA 0+000 SD STA 0+900 113,396.393

37 0 + 900 421.583
373.211 25 9,330.263
38 0 + 925 324.838
319.103 25 7,977.575
39 0 + 950 313.368
304.780 25 7,619.488
40 0 + 975 296.191
281.035 25 7,025.863
41 1 + 000 265.878
260.412 25 6,510.300
42 1 + 025 254.946
252.432 25 6,310.800
43 1 + 050 249.918
239.150 25 5,978.738
44 1 + 075 228.381
220.597 25 5,514.925
45 1 + 100 212.813
213.001 25 5,325.013
46 1 + 125 213.188
203.712 25 5,092.788
47 1 + 150 194.235
182.292 25 4,557.288
48 1 + 175 170.348
164.128 25 4,103.188
49 1 + 200 157.907
149.793 25 3,744.813
50 1 + 225 141.678
137.208 25 3,430.200
51 1 + 250 132.738
127.031 25 3,175.775
52 1 + 275 121.324
113.478 25 2,836.938
53 1 + 300 105.631
101.474 25 2,536.838
54 1 + 325 97.316
94.426 25 2,360.650
55 1 + 350 91.536

Jumlah Total 206,827.830

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (12 AGUSTUS 2021 - 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 1 + 350 s/d 1 + 800


GALIAN
LUAS (M2)
JARAK VOLUME
NO. STA LUAS LUAS
PENAMPANG (M2) RATA-RATA (M2) (M) (M3)

Sub Total STA 0+000 SD STA 1+350 206,827.830

55 1 + 350 91.536
89.409 25 2,235.213
56 1 + 375 87.281
88.759 25 2,218.963
57 1 + 400 90.236
87.146 25 2,178.638
58 1 + 425 84.055
78.212 25 1,955.288
59 1 + 450 72.368
67.396 25 1,684.888
60 1 + 475 62.423
70.025 25 1,750.625
61 1 + 500 77.627
80.958 25 2,023.938
62 1 + 525 84.288
86.800 25 2,169.988
63 1 + 550 89.311
89.111 25 2,227.775
64 1 + 575 88.911
87.539 25 2,188.463
65 1 + 600 86.166
84.534 25 2,113.338
66 1 + 625 82.901
80.600 25 2,014.988
67 1 + 650 78.298
77.000 25 1,924.988
68 1 + 675 75.701
77.403 25 1,935.075
69 1 + 700 79.105
77.946 25 1,948.650
70 1 + 725 76.787
72.885 25 1,822.113
71 1 + 750 68.982
72.963 25 1,824.063
72 1 + 775 76.943
80.407 25 2,010.175
73 1 + 800 83.871

Jumlah Total 243,054.993

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (12 AGUSTUS 2021 - 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 1 + 800 s/d 2 + 250


GALIAN
LUAS (M2)
JARAK VOLUME
NO. STA LUAS LUAS
PENAMPANG (M2) RATA-RATA (M2) (M) (M3)

Sub Total STA 0+000 SD STA 1+800 243,054.993

73 1 + 800 83.871
83.676 25 2,091.900
74 1 + 825 83.481
79.817 25 1,995.425
75 1 + 850 76.153
80.343 25 2,008.563
76 1 + 875 84.532
82.192 25 2,054.800
77 1 + 900 79.852
88.093 25 2,202.325
78 1 + 925 96.334
107.324 25 2,683.088
79 1 + 950 118.313
119.084 25 2,977.100
80 1 + 975 119.855
119.622 25 2,990.538
81 2 + 000 119.388
115.924 25 2,898.088
82 2 + 025 112.459
97.785 25 2,444.625
83 2 + 050 83.111
70.965 25 1,774.125
84 2 + 075 58.819
63.359 25 1,583.963
85 2 + 100 67.898
62.811 25 1,570.278
86 2 + 125 57.724
62.141 25 1,553.513
87 2 + 150 66.557
62.102 25 1,552.551
88 2 + 175 57.647
80.863 25 2,021.570
89 2 + 200 104.078
143.083 25 3,577.064
90 2 + 225 182.087
144.287 25 3,607.176
91 2 + 250 106.487

Jumlah Total 284,641.681

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (12 AGUSTUS 2021 - 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 2 + 250 s/d 2 + 475


GALIAN
LUAS (M2)
JARAK VOLUME
NO. STA LUAS LUAS
PENAMPANG (M2) RATA-RATA (M2) (M) (M3)

Sub Total STA 0+000 SD STA 2+250 284,641.681

91 2 + 250 106.487
106.648 25 2,666.190
92 2 + 275 106.808
103.349 25 2,583.715
93 2 + 300 99.889
105.220 25 2,630.491
94 2 + 325 110.550
99.052 25 2,476.300
95 2 + 350 87.554
123.930 25 3,098.250
96 2 + 375 160.306
203.597 25 5,089.913
97 2 + 400 246.887
141.595 25 3,539.863
98 2 + 425 36.302
18.151 25 453.775
99 2 + 450 -
- 25 -
100 2 + 475 -

Jumlah Total 307,180.178

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (S/D TANGGAL 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 0 + 000 s/d 0 + 450

GALIAN

NO. STA KUMULATIF PERIODE KE-15 OPNAME PERIODE KE-16 KUMULATIF PERIODE KE-16
S/D 11 AGUSTUS 2021 29 AGUSTUS 2021 S/D 29 AGUSTUS 2021 KETERANGAN
M3 M3 M3

1 0 + 000
- - -
2 0 + 025
284.723 8.070 292.793
3 0 + 050
2,287.925 60.588 2,348.513
4 0 + 075
1,937.413 0.863 1,938.275
5 0 + 100
2,143.538 - 36.237 2,107.300
6 0 + 125
1,935.013 140.538 2,075.550
7 0 + 150
1,771.363 265.313 2,036.675
8 0 + 175
1,713.313 466.675 2,179.988
9 0 + 200
1,647.638 487.925 2,135.563
10 0 + 225
1,613.788 312.050 1,925.838
11 0 + 250
1,436.813 517.725 1,954.538
12 0 + 275
1,092.500 840.075 1,932.575
13 0 + 300
854.500 948.750 1,803.250
14 0 + 325
852.888 808.613 1,661.500
15 0 + 350
1,102.625 241.538 1,344.163
16 0 + 375
675.875 - 675.875
17 0 + 400
2,019.675 - 121.450 1,898.225
18 0 + 425
4,099.275 - 152.125 3,947.150
19 0 + 450

Sub Total 27,468.860 4,788.908 32,257.768

Jumlah Total 32,257.768

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (S/D TANGGAL 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 0 + 450 s/d 0 + 900

GALIAN

NO. STA KUMULATIF PERIODE KE-15 OPNAME PERIODE KE-16 KUMULATIF PERIODE KE-16
S/D 11 AGUSTUS 2021 29 AGUSTUS 2021 S/D 29 AGUSTUS 2021 KETERANGAN
M3 M3 M3

Sub Total STA 0+000 SD STA 0+450 27,468.860 4,788.908 32,257.768

19 0 + 450
3,952.875 77.688 4,030.563
20 0 + 475
3,315.513 787.800 4,103.313
21 0 + 500
2,849.650 990.800 3,840.450
22 0 + 525
2,859.200 547.988 3,407.188
23 0 + 550
3,125.663 1,104.813 4,230.475
24 0 + 575
3,494.425 2,039.900 5,534.325
25 0 + 600
3,667.838 1,124.013 4,791.850
26 0 + 625
3,290.375 614.050 3,904.425
27 0 + 650
3,015.913 1,219.638 4,235.550
28 0 + 675
3,314.425 467.650 3,782.075
29 0 + 700
3,700.750 - 666.688 3,034.063
30 0 + 725
3,582.250 - 852.125 2,730.125
31 0 + 750
3,608.975 - 975.713 2,633.263
32 0 + 775
3,920.600 - 757.088 3,163.513
33 0 + 800
5,366.013 85.775 5,451.788
34 0 + 825
4,287.013 142.825 4,429.838
35 0 + 850
6,769.175 2.675 6,771.850
36 0 + 875
11,183.238 3.488 11,186.725
37 0 + 900

Sub Total 102,772.748 10,746.395 113,519.143

Jumlah Total 113,519.143

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (S/D TANGGAL 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 0 + 900 s/d 1 + 350

GALIAN

NO. STA KUMULATIF PERIODE KE-15 OPNAME PERIODE KE-16 KUMULATIF PERIODE KE-16
S/D 11 AGUSTUS 2021 29 AGUSTUS 2021 S/D 29 AGUSTUS 2021 KETERANGAN
M3 M3 M3

Sub Total STA 0+000 SD STA 0+900 102,772.748 10,746.395 113,519.143

37 0 + 900
9,330.263 - 9,330.263
38 0 + 925
7,977.575 - 7,977.575
39 0 + 950
7,619.488 - 7,619.488
40 0 + 975
7,025.863 - 7,025.863
41 1 + 000
6,510.300 - 6,510.300
42 1 + 025
6,310.800 - 6,310.800
43 1 + 050
5,978.738 - 5,978.738
44 1 + 075
5,514.925 - 5,514.925
45 1 + 100
5,325.013 - 5,325.013
46 1 + 125
5,092.788 - 5,092.788
47 1 + 150
4,557.288 - 4,557.288
48 1 + 175
4,103.188 - 4,103.188
49 1 + 200
3,744.813 - 3,744.813
50 1 + 225
3,430.200 - 3,430.200
51 1 + 250
3,175.775 - 3,175.775
52 1 + 275
2,836.938 - 2,836.938
53 1 + 300
2,536.838 - 2,536.838
54 1 + 325
2,360.650 - 2,360.650
55 1 + 350

Sub Total 196,204.185 10,746.395 206,950.580

Jumlah Total 206,950.580

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (S/D TANGGAL 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 1 + 350 s/d 1 + 800

GALIAN

NO. STA KUMULATIF PERIODE KE-15 OPNAME PERIODE KE-16 KUMULATIF PERIODE KE-16
S/D 11 AGUSTUS 2021 29 AGUSTUS 2021 S/D 29 AGUSTUS 2021 KETERANGAN
M3 M3 M3

Sub Total STA 0+000 SD STA 1+350 196,204.185 10,746.395 206,950.580

55 1 + 350
2,235.213 - 2,235.213
56 1 + 375
2,218.963 - 2,218.963
57 1 + 400
2,178.638 - 2,178.638
58 1 + 425
1,955.288 - 1,955.288
59 1 + 450
1,684.888 - 1,684.888
60 1 + 475
1,750.625 - 1,750.625
61 1 + 500
2,023.938 - 2,023.938
62 1 + 525
2,169.988 - 2,169.988
63 1 + 550
2,227.775 - 2,227.775
64 1 + 575
2,188.463 - 2,188.463
65 1 + 600
2,113.338 - 2,113.338
66 1 + 625
2,014.988 - 2,014.988
67 1 + 650
1,924.988 - 1,924.988
68 1 + 675
1,935.075 - 1,935.075
69 1 + 700
1,948.650 - 1,948.650
70 1 + 725
1,822.113 - 1,822.113
71 1 + 750
1,824.063 - 1,824.063
72 1 + 775
2,010.175 - 2,010.175
73 1 + 800

Sub Total 232,431.348 10,746.395 243,177.743

Jumlah Total 243,177.743

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (S/D TANGGAL 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 1 + 800 s/d 2 + 250

GALIAN

NO. STA KUMULATIF PERIODE KE-15 OPNAME PERIODE KE-16 KUMULATIF PERIODE KE-16
S/D 11 AGUSTUS 2021 29 AGUSTUS 2021 S/D 29 AGUSTUS 2021 KETERANGAN
M3 M3 M3

Sub Total STA 0+000 SD STA 1+800 232,431.348 10,746.395 243,177.743

73 1 + 800
2,091.900 - 2,091.900
74 1 + 825
1,995.425 - 1,995.425
75 1 + 850
2,008.563 - 2,008.563
76 1 + 875
2,054.800 - 2,054.800
77 1 + 900
2,202.325 - 2,202.325
78 1 + 925
2,683.088 - 2,683.088
79 1 + 950
2,977.100 - 2,977.100
80 1 + 975
2,990.538 - 2,990.538
81 2 + 000
2,898.088 - 2,898.088
82 2 + 025
2,444.625 - 2,444.625
83 2 + 050
1,774.125 - 1,774.125
84 2 + 075
1,583.963 - 1,583.963
85 2 + 100
1,570.278 - 1,570.278
86 2 + 125
1,553.513 - 1,553.513
87 2 + 150
1,552.551 - 1,552.551
88 2 + 175
2,021.570 - 2,021.570
89 2 + 200
3,577.064 - 3,577.064
90 2 + 225
3,607.176 - 3,607.176
91 2 + 250

Sub Total 274,018.036 10,746.395 284,764.431

Jumlah Total 284,764.431

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
REKAPITULASI PERHITUNGAN VOLUME
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE KE 16 (S/D TANGGAL 29 AGUSTUS 2021)

REKAPITULASI PERHITUNGAN VOLUME GALIAN DI STA 2 + 250 s/d 2 + 475

GALIAN

NO. STA KUMULATIF PERIODE KE-15 OPNAME PERIODE KE-16 KUMULATIF PERIODE KE-16
S/D 11 AGUSTUS 2021 29 AGUSTUS 2021 S/D 29 AGUSTUS 2021 KETERANGAN
M3 M3 M3

Sub Total STA 0+000 SD STA 2+250 274,018.036 10,746.395 284,764.431

91 2 + 250
2,666.190 - 2,666.190
92 2 + 275
2,583.715 - 2,583.715
93 2 + 300
2,252.815 377.676 2,630.491
94 2 + 325
1,135.658 1,340.643 2,476.300
95 2 + 350
1,085.746 2,012.504 3,098.250
96 2 + 375
3,099.388 1,990.525 5,089.913
97 2 + 400
2,145.100 1,394.763 3,539.863
98 2 + 425
- - -
99 2 + 450
- - -
100 2 + 475

Sub Total 288,986.648 17,862.505 306,849.153

Jumlah Total 306,849.153

Klungkung, 01 September 2021

Dibuat Oleh,
PT. Gunung Emas Putih

Muhammad Maulana Ardi Denianto


Surveyor Project Manager

Diperiksa Oleh,
NINDYA – BNL, KSO

Muhammad Ihsan I Wayan Darmada


Site Engineer Manager Site Operation Manager

Disetujui Oleh,
NINDYA – BNL, KSO

I Made Sujana
Project Manager
RINCIAN REKAPITULASI PROGRES 3
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE 01 MARET 2021 - 31 MARET 2021

HASIL OPNAME
NO. ITEM PEKERJAAN SATUAN OPNAME 8 OPNAME 9 OPNAME 10 JUMLAH
10-Mar-2021 17-Mar-2021 25-Apr-2021

1 Pekerjaan Galian Tanah M3 10,242.93 11,434.40 26,003.52 47,680.84


REKAPITULASI PROGRES 3
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH
PERIODE 01 MARET 2021 - 31 MARET 2021

VOLUME
NO. ITEM PEKERJAAN VOLUME KONTRAK SATUAN SISA KONTRAK
s/d Periode Lalu Saat ini s/d Saat Ini

1 Pekerjaan Galian Tanah - M3 8,657.483 10,242.925 18,900.408 -


REKAPITULASI PERHITUNGAN VOLUME PROGRES
PEKERJAAN GALIAN DI AREA PENGENDALIAN BANJIR TUKAD UNDA, BALI
PT. GUNUNG EMAS PUTIH

HASIL OPNAME
OPNAME 1 OPNAME 2 OPNAME 3 OPNAME 4 OPNAME 5 OPNAME 6 OPNAME 7 OPNAME 8 OPNAME 9 OPNAME 10 OPNAME 11 OPNAME 12
20-Jan-2021 30-Jan-2021 7-Feb-2021 13-Feb-2021 17-Feb-2021 24-Feb-2021 3-Mar-2021 10-Mar-2021 24-Mar-2021 24-Mar-2021 31-Mar-2021 7-Apr-2021
44,039.800 2,446.496 17,475.001 16,849.155 5,442.505 25,093.695 8,657.482 10,242.925 12,772.420

S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D
20-Jan-2021 30-Jan-2021 7-Feb-2021 13-Feb-2021 17-Feb-2021 24-Feb-2021 3-Mar-2021 10-Mar-2021 24-Mar-2021 24-Mar-2021 31-Mar-2021 7-Apr-2021
44,039.800 46,486.296 63,961.297 80,810.452 86,252.958 111,346.653 120,004.135 130,247.060 143,019.480

Target Target Target Target Target Target Target Target Target Target Target Target
20-Jan-2021 30-Jan-2021 7-Feb-2021 13-Feb-2021 17-Feb-2021 24-Feb-2021 3-Mar-2021 10-Mar-2021 24-Mar-2021 24-Mar-2021 31-Mar-2021 7-Apr-2021
33,747.000 67,494.000 101,241.000 269,976.000

Deviasi Deviasi Deviasi Deviasi Deviasi Deviasi Deviasi Deviasi Deviasi Deviasi Deviasi Deviasi
20-Jan-2021 30-Jan-2021 7-Feb-2021 13-Feb-2021 17-Feb-2021 24-Feb-2021 3-Mar-2021 10-Mar-2021 24-Mar-2021 24-Mar-2021 31-Mar-2021 7-Apr-2021
- 8,653.30 - 33,742.82 - 82,340.59 - 246,960.66

JUMLAH HARI TIAP PERIODE OPNAME


OPNAME 1 OPNAME 2 OPNAME 3 OPNAME 4 OPNAME 5 OPNAME 6 OPNAME 7 OPNAME 8 OPNAME 9 OPNAME 10 OPNAME 11 OPNAME 12
23 10 8 6 4 7 7 7 14 0 7 7

PRODUKSI TIAP HARI PER PERIODE OPNAME


OPNAME 1 OPNAME 2 OPNAME 3 OPNAME 4 OPNAME 5 OPNAME 6 OPNAME 7 OPNAME 8 OPNAME 9 OPNAME 10 OPNAME 11 OPNAME 12
1,914.774 244.650 2,184.375 2,808.193 1,360.626 3,584.814 1,236.783 1,463.275 912.316

STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA STA sd STA
0+775 0+775 0+775 0+875 0+875 1+100 0+900 0+900
sd sd sd sd sd sd sd sd
0+1650 1+800 1+925 1+225 1+725 2+225 1+675 1+850

0+850 NK 1+375
sd
1+650

1+950
sd
2+350

LEMBAR 1 / 1

PROGRES PRODUKSI MINGGUAN


PT GUNUNG EMAS PUTIH
PEKERJAAN GALIAN DI AREA PENGENDALAIAN BANJIR TUKAD UNDA, BALI
50,000.000

45,000.000

40,000.000
VOLUME PROGRES MINGGUAN (M3)

35,000.000

30,000.000

25,000.000

20,000.000

15,000.000

10,000.000

5,000.000

0.000
2 0 -J an - 2 0 2 1 3 0 -J an - 2 0 2 1 7 - F eb - 2 0 2 1 1 3 - F eb - 2 0 2 1 1 7 -F eb -2 0 2 1 2 4 -F eb -2 0 2 1 3 -Mar -2 0 2 1 1 0 - Mar - 2 0 2 1 2 4 - Mar - 2 0 2 1 2 4 - Mar - 2 0 2 1 3 1 -Mar - 2 0 2 1 7 - A p r -2 0 2 1

TANGGAL OPNAME