Annexure Specification Dsil Requirement Quad Body 1200M2: Page 1 of 3
Annexure Specification Dsil Requirement Quad Body 1200M2: Page 1 of 3
Page 1 of 3
Cover - 25 mm thik
BRG - Double thrust bearing
Rubber -- EPDM Quality suitable for 160 degree c
Guide -- Heavy duty
Testing pressure --- 100 psig
PERFORMANCE PARAMETERS
1] Evaporation rate should be not less than 4.5 lb/sq.ft/hr.
2] Zero entrainment
3 ]1200 m2 body should be capable to handle a crush rate of 6500 TCD at clear juice% cane +110.
TERMINAL POINTS
1] Steam entry of exhaust valve /inlet of calendria.
2] juice - Inlet / outlet valve of body
3] Vapour- Outlet of catchall
4] Water- Entry of body and colendria valves .
5] Condensate - Delivery valves of pumps.
6} Caustic soda- inlet valve of body
PURCHASER SCOPE
1] structure and stagging Work
2} Civil Work
3} All electrical Work
4} SS Tube
DRAWINGS :
The following drawing to be submitted with in two/ three days for approval with load data after finalisa-
Page 2 of 3
tion of order .
1.Load details for designing structures & stagings
2 GA drawings
3. Drawings of Tube plate , Rubber Items etc.
The equipment and materials supplied against the order shall confirm to technical details, design
data as per drawing duly approved by us and ensure the confirmity of DP test.
Page 3 of 3