Professional Documents
Culture Documents
Chapter 1: Overview of Reliability: 1.1 Definitions and Concepts 1.1.1 Power Systems and Elements
Chapter 1: Overview of Reliability: 1.1 Definitions and Concepts 1.1.1 Power Systems and Elements
Power system is recovery system and the elements of the power system
after being taken down will be restored back to work, so the status of breakdowns
also been recovered after a certain time.
Most elements of the power system are also periodic maintenance to restore
the ability to work after working time.
-1-
depend on the internal structure of the element.Because the element can have a
complex structure, it is a system. For example, the generator is a complex system
given separately, but in the problem of the reliability of the electric system it is only
one element with parameters such as the intensity of breakdowns, constant recovery
time.
For the recovery system (or recovery element) such as electric system, its
elements…, the concept of interval does not mean mandatory, because the system
worked continuously. Therefore, reliability is measured by an appropriate quantity,
such as availability.
-2-
For power systems, availability (also referred to as reliability) or not
availability is not enough to assess the reliability of the specific problem, so we use
other indicators also probability.
∑ ni
i =1
SAIFI =
NT (times/load. year) (1.2)
- Customer average interruption duration index – CAIDI provides average
duration needed to recover electrical supplied ability in one time black out.
CAIDI=
∑ ri N i
∑ Ni (hour/outage times) (1.3)
Therein : ri is time of each outage ;Niis number of
customers in maintenance outage.
- Customer average interruption frequency index – CAIFI provides average
number of power outages of one customer (in one area) in one year.
-3-
CAIFI = Σni/CN (outage times/customer.year) (1.4)
With: CN is the number of outage customers
- Average service availability index – ASAI provides average duration of one
customer supplied electricity in a year (%). It is defined as ratio of total hour
supplied and total hour requirring by one customer ( usually, total hour
requirring is 24*365=8760 hours)
N T . 8760−∑ r i N i
ASAI = (%)
N i . 8760 (NTis total of customer) (1.5)
- Customer total average interruption duration index – CTAIDI provides total
average duration of electrical outage. This criterion is calculated as CAIDI,
except, customer experiencing multiple interruptions is only counted one
time.
CTAIDI =
∑ ri N i
CN (1.6)
With: CN is the number of outage customers
- Customers experiencung multiple interruptions – CEMIs provides the
number of customers’s power outage. This index has purpose of showing
troublesoem to customer that average value does not refer to.
CN ( k >n )
CEMIn=
NT (1.7)
- Average system interruption duration idex: ASIDI about load side is defined
as ratio between total unsupplied power (by interrupting incidents) and total
supplied power (kVA).
ASIDI =
∑ r i Li
LT (1.8)
Therein : Li : isthe load capacity of outage ; LT : is the load capacity
total.
- Average system interruption frequency index – ASIFI is defined as ratio of total
interrupting power (kVA) and total supplied power (kVA).
ASIFI =
∑ Li
LT (1.9)
-4-
- Customers experience multiple sustained interruptions and momentary
interruptions events – CEMSMIn lists number of momentary and permanent
interrupting events of one customer.
CNT (k >n )
CEMSMIn=
NT (1.10)
Therein : CNT(k>n) :Customers have outage times larger than
n.
- Momentary average interruption frequency index – MAIFI provides the
number of electrical momentary interrupting of one customer in an area per
year.
MAIFI=
∑ IM i N mi
NT (1.11)
Therein : Imi is transient outage times ; Nmi is transient outage
customer.
- The average power consumption is not provided: AENS =power total is not
provided on customers total.
AENs = ΣLa(i)/Ni (kWh/customer) (1.12)
Therein : La(i)is the power loss of load i
- The annual average blackouts indicator: ACCI
ACCI = = ΣLa(i)/ΣNi (1.13)
- Momentary average interruption event frquency index – MAIFIE provides
average number of momentary interrupting event of one customer in an area
per year.
- Average service unavailability index – ASUI.
- Energy not supplied index – ENS.
-5-
large area of the country or territory. When the damaged elements of system
can lead to stop supplying electricity to customers for each region or the
whole system. There are many outage causes, people divided into four main
causes as follows:
- Due to the weather: flood, rain storms, tornadoes, lightning, tsunami ...
- Due to corrupting the electrical components of the system as:
Corrupt transformers
Corrupt swithgear
+ Protection and control such as: damaged relays, broken signal line,
damaged control circuit.
Low/high voltage
Low/high frequency
Unbalanced load
-6-
Because of dispatching staff of power system
- Other Causes:
+ Excavation.
+ Fire or explosives.
+ Sabotage, terrorism.
For above type, load should supply power with highest reliability. Under
type is economic-technical problem basing on considerations between capital
investment in power system and economic losses due to power outages:
Economic losses are seen in view of the power system.This loss is calculated
from the real loss in load and in accordance with opinion of the power system.It is
to serve design, planning of electric systems that satisfy the reliability requirements
of the load, while ensuring economic efficiency of power system.
This loss is calculated for net distribution line, transmission line and power
source separately.It was also calculated for each type of loadfor outage times, for 1
kW or 1kWh and calculated for the duration of outages time.
-8-
- In Australia using price table of outages ($/kWh) as follows (in Australian
currency):
+ Civil load: 0.5 for planned outages - 1.5 for incident outage.
+ Normal business load: 2.5 for planned outages - 7.5 for incident
outage.
+Sensitivebusinesses load: 5 for planned outages- 15 for incident
outage.
- At EDF usingprice as follows:in 1988 cost at distribution network is: 14.5
F/kWh general, not by type of load; specialized loadnetwork has two price, if
the capacity is less than 8%, the price is 7.25 F/kWh, higher than 8%, the
price is 14.5 F/kWh.
In the target function of the problem defined as source and grid structure;
there are also losses components due to reliability calculated by economic losses
-9-
mentioned above.However, such calculation also encountered many
difficulties.Thus we can calculate the reliability factor as the boundary
conditions of the problem, ie using indirect indicators of reliability such as:
The price of reliability is used to review and assess its growth rate.Economic
analysis of reliability can be a very useful tool in planning decisions to spend
money to improve reliability by providing more capital for the system.
The reliability study showed that reliability is desired to avoid the breakdown
of equipment or combination of equipment which leads to power supply stop.The
degree of reliability is considered reasonably to damage due to outages increased to
avoid the consequences of exceeding outage of customer. According reasonable
degree of confidence from the consumer perspective can be defined as the
confidence level when investmenttotal and damage is minimized. Note that the
improvement of system reliability and investment is not linear relationship and
-10-
reasonable reliability of the system for fitting optimaly... the smallest cost total. The
problem is the initial capital investment increasing how reliability is. Where does
subsequent capital investment put to achieve the highest reliability?
-11-
conditions. For those loads are not allowed outage, the investment with the best
possibilities.For other loads should be based on a comparison between the losses
due to outages and investment costs.In fact, distribution network also uses a lot of
old equipment, outdated technology, low reliability gradually replaced by modern
equipment having high reliability, thus the reliability of the grid are becoming
markedly improved.
The second measure is the use of automated devices on the network and
remote control device.The automatic equipment is used: automatic close, automatic
backup power close, supervisory control systems and remote data acquisition
(SCADA). According to statistics for overhead transmission line, transient problems
can be accounted for 70-80 % of the total number of line faults.It is caused because
a lightning strike on the line, tree falls on line, strange objects fall into line...The
incident is usually eliminated after one or two electrical discharges.Therefore, if
using automatic close, the closed rate is very high since time of automaitic close is
very short(2-5s), so load should not suffer blackouts. There are twopower
supplieswhile having a redundant power supply, the automatically closed device of
redundant power is very efficiently. When there is a breakdown power supply, the
other source will immediately be put to work without causing outages for
load.Nowadays, with the development of information technology, monitor control
systems and remote data collection is widely used in the industry.This system
allows data collection, analysis and control of remote objects. Using SCADA
systems in the distribution network will quickly separated incident grid segments
and restored the power supply for the no-incident segment.For many distribution
network and complex wiring such as gird in the city, the use of SCADA system is
very efficient and reasonable, however for distribution network in rural areas... has
large cost affecting economic criteria of the facility.
Diagram is segments grid. Radial-segments grids are the most used today
because it costs even low, simpler scheme can be applied widely. Disadvantages are
not highly reliable. Segments Equipment may be the circuit breaker, disconnector.
In this scheme, if incident is only a segment,backward segment will be outage;
preceded segments (toward the source) only are temporary outage during operation
time. In this type of diagram, the number and placement of segment equipment also
affect the outage time of load. So we choose specificlyfor each specific grid.
Experience shows that minimizing power loss due to routine maintenance and
breakdowns, we need more segment equipment on the line. Placement of segment
equipment divided same line length. However, installing much segment equipment
will increase investment, malfunction elements of grid for 10kV grid; people often
choose the length of the segment line from 2-3 km. Use this scheme effectively
need to combine with automatic closing devices, remote control ... can dramatically
improve the reliability of the distribution grid.The use of these devices can
eliminate the influence of transient malfunction and shorten the operation time on
the grid, thereby improving the reliability of power supply. Because of large capital
-13-
investment, we need to compare between losses due to outages and investment
costs.
The fourth measureis finding and fixing fast problems. This is an important
solution to improve the reliability of power supply. Search and quickly isolate
incident, shorten outage time of load.This includes the contents: organized enough
people, tools, supplies, backup equipment and media being ready for every incident
situation. Collect information, analyze and isolate incident quickly. Repair quickly
incident in distribution network will reduce outage time of load, power loss due to
incident, and improve reliability of distribution grid.
The reliable problem of the power system is divided into four categories:
-14-
d) The reliable problem of the load.
The synthetic problem for sourceand grid still uses indirect methods of
synthesis, which is based on different plans calculatingreliable criterion by
analytical methods to compare and select optimal solution.
Reliable analysis studies the effects of internal and external factors to the
reliability of the electric system.Factors affecting the reliability of the power system
are:
- Reliability of elements:
-15-
+ The intensity of incident, recovery time.
+ Periodic repairs.
+ Outage to work.
- The structure of the system:
- The coupling among the elements in the station diagram, grid shape.
- Ability manipulates and changes the connection diagram (automatically or
manually).
- Organization System of management and operation:
- Organize and arrange the mobile units to intervene when having incidents.
+ Organize network to recover incident and periodic repairs.
+ Reserve equipment and repair.
+ Reserve capacity in the system.
+ The structure and operation of the control and operation system.
+ Strategy preserves periodic equipment.
- The impact of environment:
+ Electrical load.
+ Climatic factors, temperature and pollution.
- Human factors: the level of operational staff, technical factors, automated
operation.
In analysis, these factors are inputs while the output is the reliable target
of power systems.
However, the overall result would still be used in the planning and
operation of power systems.
-16-
The reliable problem in planning servicein order to determines the
addition of new equipment, structural changes in the electrical system in next
year.The reliable problem in operational service in order to tests and
selectsoperational strategies for available electrical systems.
Two problems are same and this is general model of the power system.
In power system, distribution network is the final stage of the power supply
to the load.Distribution gridaffects to economic and technical indicators of power
systems as:
The task of the distribution grid is to supply to load with standard quality and
reliability in permissible limits.However, for reasons of economic and technical
-17-
conditions, the high or low reliability of the current system depends on the load
requirements and the quality of the distribution network.
This scheme has higher reliability than the previous diagram.In principle,
network operates closedbut protective and control devices require good and
expensive equipment and is. Operating openingmesh issimple and much cheaper.
When the load curve changes by computer system, the wiring diagram is
redistributed to minimize power losses in the system.
Power supply system has high reliability and economic indicators, the stage
of measurement and automation can control highly. It helps power system always
operation optimally.
-18-
1.4 METHODS AND TOOLS FOR EVALUATING DISTRIBUTION
RELIABILITY
L
λSC =λ0
100 (1.14)
-19-
λCT – Working outage intensity.
Capacity and time using the largest capacity of the entire distribution
network is:
T max =
∑ P max i . T max i
∑ Pmax i (1.20)
-20-
In the case of segments with disconnector, if the incident occurs in a certain
segment, circuit breaker will jump temporarily and cut the entire distribution grid.
Disconnector segmented and isolated malfunction element to the source. Then
sourceis closed to supply power for segment being in front of malfunction segment
toward the source.
When the incident occurs in a certain segment, that segment’s load and
segments(powered through breakdown segment) meets power outage during
repairing time. Load of the previous segment (before breakdown segment) only
meetspower outageduring operation time to isolate incident elements.
-21-
- The impact of the incident on the following grid, here's segment II, this effect
depends fractional device.
λII>I = 0; TII>I = 0.
Total number of power outages and outage time of grid segment I is:
Total number of power outages and outage time of grid segment II is:
Example:
Given:
-22-
Malfunctioning intensity cố λosc = 4 (l/100km.year); Tsc = 12h, Tttsc = 2h.
Segment 1:
= 6.2 + 6.0,5 = 15 h
Segment 2:
-23-
= 6.2 + 6.2 = 24 h
-24-