Revision Questions

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Revision Questions • The Contractor explain the matter to the S.O.

1. Identify the party in each of the following roles that: • The S.O. inform the higher committee such as general secretary of the ministry.
i. Award the contracts to the Contractors under the P.W.D. Form of Contract. • The matter will be discussed in the meeting to decide whether to approve or reject.
Government • The decision made will be conveyed to the Contractor by the S.O.
ii. Ensure the Employer’s position in the contract is protected. • The S.O. shall communicate the Government’s decisions or instruction to the
Contract administrator / Architect / Superintendent officer Contractor as per Clause 5.0.
iii. Performs specialized construction works and in many situations his certifications • Government to Contractor: The SO will issue drawings, details and written
required before the CCC can be issued. instruction to the Contractor (Clause 5.1).
Nominated sub-Contractor • Contractor to Government: The Contractor give written notice to the SO, SO will
iv. Also carry out valuation of works other than the Quantity Surveyor. prepare the report to notify the Government.
Architect / Consultant
4. Under P.W.D. 203A Form of Contract and PAM Contract 2018, both provided several
2. The Superintendent Officer (S.O.) of a project shall, as soon as possible, price each conditions which allow the Employer to determine the contract of the employment of
variation using certain order of precedence. the Contractor.
Briefly explain the order of precedence for the variation price. Briefly describe six (6) conditions to determine the employment of the Contractor.
• Clause 25.1(a): for the valuation of work of similar character and executed under Clause 51.1(a) of P.W.D. 203A
similar conditions, the rates in BQ after adjustment shall be used. i. Fails to commence works at the site within 2 weeks after the Date for Possession
• Clause 25.1(b): for the works is not of similar character or executed under similar ii. Suspends or abandons the carrying out of the works or any part thereof for a
conditions, a fair valuation with reasonable basis rate made by the S.O. shall be continuous period
applied. iii. Fails to execute the works in accordance with the contract
• Clause 25.1(c): the rate in the BQ shall determine the valuation of the omitted items iv. Persistently neglects to carry out his obligations under the contract.
and if the omission substantially vary the conditions of the remaining works, the v. Refuses or persistently neglects to comply with a written notice from the S.O. in
rates of the remaining works shall be valued under rule (b). relation to any defective work
• Clause 25.2: where the works cannot property be measured or valued, the S.O may vi. Fails to comply with provisions of Clause 47 (Sub-contract or Assignment)
allow daywork price as specified in the Appendix plus 15% provided the Contractor Clause 25.1 PAM Contract 2018
produces the vouchers, receipts and wage books specifying the time for labour and i. If without reasonable cause, the Contractor fails to commence the works in
plant employed and material used with 7 days after the works is done. accordance with the contract
• Clause 25.3: the certified amount of the variations shall be added to or deducted ii. If without reasonable cause, the Contractor wholly or substantially suspends the
from the contract sum. carrying out of the works before completion
iii. If the Contractor fails to proceed regularly and/or diligently with the works
3. The P.W.D. 203A Form of Contract obliges the Employer to appoint the S.O. who is iv. If the Contractor persistently refuses or neglects to comply with an AI
responsible for the administration of the contract. The contract is made between the v. If the Contractor fails to comply with the provisions in Clause 17.0 (Assignment and
Government and the Contractor. Sub-contracting)
Since the Government and the Contractor are not allowed to make direct vi. If the Contractor abandoned the works
communication with each other, briefly explain the method of communication
between the Government and the Contractor. 5. Identify the contractual terms in each of the following situations:
• The direct communication between the Government and Contractor might cause i. The developer’s requirement is to start the operation of the ground floor retail
the transparency problem arise. stalls and car parks without the construction of apartment above fully completed.
• Hence, S.O. acts as the medium of communication. What can the QS suggest during the contract formation stage?
1
• Clause 21.2: Sectional Commencement Dates and Clause 21.3: Sectional be protected against loss, damage or deterioration and be in accordance with the
Completion Dates Contractor.
• The QS shall suggest the developer to have a sectional commencement and • Besides, Clause 30.2 also states that the certificate shall only include the value of
completion date for the ground floor retails stalls, car parks and apartment. materials and goods which are reasonably, properly and not prematurely brought to
• The sectional commencement and completion date shall be inserted in the the site.
Appendix.
ii. The payment can only be imposed by the Employer to the Contractor upon the 9. The interim certificate and payment have a set-off amount without the Contractor’s
receipt of a CNC. prior knowledge. This resulted in the Contractor not able to pay his suppliers who
• Clause 22.1: Liquidated Damages and Certificate of Non-Completion stopped supplying materials which caused delay to the progress of works. Appraise
• When CNC is issued by the Architect, the Contractor shall pay the Employer a the following situations based on the PAM Form of Contract.
sum calculated at the rate stated in the Appendix for the period from the The Contractor insisted the set-off amount is against the contract but the Employer
Completion Date to the date of Practical Completion. argued the Contractor has overrun the contract period and a CNC has been issued and
iii. This price is inserted by the QS in the tender/contract documents meant for the the set-off for LD.
supply of materials by a Nominated Supplier. i. Adjudicate this dispute
• Clause 28.1: P.C. Sums and Provisional Sums – Nominated Suppliers. • According to Clause 30.4(b), the Employer is entitled to set-off all cost incurred
• The P.C. Sums are included in the contract bills to nominate the nominated and loss and expense provided the Employer or the Architect on his behalf has
suppliers to supply any materials and goods to be fixed by the Contractor. given the Contractor a written notice delivered by hand or registered post,
specifying his intention to set-off the amount and the grounds on which such set-
7. Based on the PAM Form of Contract 2018, the Contractor has abandoned the works off is made not later than 28 days before any set-off is deducted from any
due to the irreconcilable problems among the partners in the company. payment by the Employer.
Advise on the actions that the Employer needs to take so that the project can continue. • In this case, the Employer set-off the amount from the interim certificate and
• The Employer may determine the Contractor’s employment under Clause 25.1(f). payment without the Contractor’s prior knowledge. Hence, the Employer is not
• The Employer shall follow the procedure for determination as stipulated in Clause entitled to set-off any amount.
25.2. • Besides, Clause 22.1 stated that the imposition of liquidated damages by the
• When the Contractor’s employment is determined, the rights and duties of the Employer shall not be taken into account by the Architect in the issuance of
Employer and the Contractor are shown in Clause 25.4. payment and final certificate and is not subject to the set-off procedures under
Clause 30.4 and adjudication.
8. The Contractor has abandoned the project due to insolvency of his company. The • Hence, the deduction of the liquidated damages shall not reflect on the interim
Architect found out that the interim certificate was over paid the Contractor. certificate. The Employer can recover the sum as a debt or may deduct from any
Materials off site also certified by the QS. monies due or to become due to the Contractor or recover from the performance
Advice the Employer this situation with reference to PAM Form of Contract 2018. bond.
• The Employer may determine the Contractor’s Employer under Clause 25.3. ii. The Contractor’s claim for EOT is rejected by the Architect.
• Upon the determination, the Final Account shall be prepared based on Clause 25.6. • As stated in Clause 23.4, the Architect shall base on Clause 23.5, 23.6 and 23.8 to
• The outstanding amount due to the Employer shall be paid by the Contractor as a consider the Contractor’s submission and shall either reject the Contractor’s
debt payable to the Employer. application with reasons or issue a Certificate of Extension of Time with the
• The material off site certified by the QS is a breach of his duties. details within 6 weeks from the receipt of the sufficient particulars.
• Clause 30.2 stated that the materials and goods must be for the incorporation into • In this case, the cause of delay of the Contractor is not in the list of the relevant
the permanent works and have been delivered to and properly stored at the site and events for the Architect to grant extension of time under Clause 23.8.
• Hence, the Architect can reject the Contractor’s application with reasons.
2
10. During a contract, using P.W.D. Form of Contract, the Contractor is unable to procure 13. Based on P.W.D. 203A Form of Contract, explain the process of valuation, Final
Performance bond by the Date for Possession. Accounts and Final Certificate that a Project Superintending Officer should follow.
Elaborate and cite the clauses on how his contract is impacted. Quote and explain the relevant clauses.
• Clause 13.1(b) shows that if the Contractor fails to submit the Performance Bond on Valuation
the date of possession of site, then the Contractor shall be deemed to have opted • Clause 28.3: The S.O. shall issue an interim certificate within 14 days from the date
for Performance Bond in the form of Performance Guarantee Sum. of any valuation being made stating the amount due to the Contractor from the
• Clause 13.2 stated that the deductions of 10% shall be made from the first interim Government.
payment and subsequent interim payment until the total amount deducted to a sum Final Accounts
equivalent to 5% of the contract sum. • Clause 31.1: Not later than 3 months after the issuance of the CPC, the Contractor
• The amount retained by the Government shall be up to 12 months after the expiry shall submit full particulars to the S.O. for the preparation of Final Account.
of the Defect Liability Period or the issuance of the Certificate of Making Good • Clause 31.2: If the Contractor fails to submit full particulars of all claims within the
Defects, whichever is the later. stipulated period, the S.O. shall make the assessment based on the available
information submitted by the Contractor for the purpose of the Final Account.
11. A Contractor was held liable to make a contribution to the cost of remedial works Final Certificate
resulting from the demolition of load bearing walls. The walls were shown on the • Clause 31.3: Within 3 months after the expiry of the Defects Liability Period or within
Architect’s drawing as non-load bearing. 3 months after the issuance of the CMGD, whichever is the later, the S.O. shall issue
Explain the position of the Contractor in this situation. the Final Certificate.
• Clause 1.1 stated that the Contractor shall carry out and complete the works in
accordance with the contract documents and provide the materials, goods and 14. A Sales Gallery located at Selayang was awarded to ABC Builder Sdn Bhd under PAM
standards of workmanship of the quality and standard described in the contract Form of Contract 2018 (With Quantities).
documents and/or required by the Architect. The Employer instructed the commencement of construction works despite without
• In this case, the Contractor fails to construct the walls according to the Architect’s obtaining building plan approval from Majilis Perbandaran Selayang (MPS). Stop work
drawings. order was issued by the MPS.
• Clause 6.5(c) stated that if the Architect finds any work, materials, goods or Advice the Architect on the entitlement of the Contractor under this circumstance.
workmanship which is not in accordance with the contract, the Architect shall Quote and explain the relevant clauses.
instruct the Contractor in writing to rectify such work with no adjustment to the • In this issue, the Employer fails to obtain the building plan approval from the local
Contract Sum. authority and the stop work order is issued which caused the suspension of the
• Clause 6.6 also stated that the compliance by the Contractor with a written works.
instruction issued under Clause 6.5 shall not entitle the Contractor to an extension • The Contractor is entitled to claim for Extension of Time under Clause 23.9(x) where
of time nor compensation for any loss and/or expense that may be incurred. the suspension of the whole or part of the works by order of an Appropriate
• Hence, the Contractor is liable to make contribution to the cost of remedial works Authority is not due to any negligence, omission, default or breach of contract by
with no extension of time or compensation granted to him. the Contractors and/or Nominated Sub-Contractors and follow all the procedures
for the application of Extension of Time under Clause 23.1(a) and 23.1(b).
12. Some standard forms of contract have been defined practical completion as taking • The Contractor is also entitled to claim for loss and/or expense under Clause 24.3(o)
place when the development is completed for all practical purposes. due to the suspension of the whole or part of the works by order of an Appropriate
Explain the meaning of the development is completed for all practical purposes. Authority due to the negligence or omission on the part of the Employer, Architect
**Answer from both forms is acceptable. or Consultant and he needs to follow all the procedures for the application for loss
• PAM 2018: Clause 15.1 and/or expense under Clause 24.1(a) and 24.1(b).
• PWD 203A: Clause 39.5
3
15. Marvel Development Sdn Bhd awarded 10 units bungalows to Titan Construction Sdn Advice the Architect what rights does the NSC have under PAM 2018.
Bhd on 8 January 2018 with the construction period of 15 months. The contract • Clause 27.6 stated that if the Contractor fails to pay the NSC, the Employer may, but
awarded based on PAM Form of Contract 2018 (Without Quantities). not obliged to, pay the amounts directly to the NSC and deduct the same from any
On 10 February 2019, the Employer intended to construct 25 units bungalows at sums due or to become due to the Contractor.
adjacent low. The Employer wants the Architect, Archi Sdn Bhd to issue the additional • The Employer is not obliged to do so because there is not a privity of contract
scope works as Variation Order to Tian Construction Sdn Bhd. between the Employer and the NSC as stated in Clause 27.10.
Advice the Employer and the Architect on the above.
• As stated in Clause 11.1, the variation means the alteration or modification of the 18. Yakin Construction Sdn Bhd is the main Contractor for a housing project in Nilai. The
design, quality or quantity or works. However, the additional scope of works does developer is Nilai development Sdn Bhd.
not comply with the terms of variation. The Architect certified RM500,000 as the amount due to Yakin Construction Sdn Bhd
• The definition of works as stated in Article 7 (be) shall means the works described in in interim certificate No. 4 dated on 1 March 2019. The period of honouring is 30 days
the Articles of Agreement and referred to in the Contract Documents and includes upon Architect’s Certificate as stated in Appendix in PAM 2018. However, Nilai
any changes made to these works in accordance to with the Contract. Development Sdn Bhd only honouring RM150,000 to Yakin Construction Sdn Bhd on
• Besides, the additional scope of works might cause the Performance Bond, 30 March 2019. The balance remains outstanding on 1 August 2019.
Retention Sum and Liquidated Damages and also affect the nature and the scope of What is Yakin Construction Sdn Bhd entitlement under this situation?
works. • Since the Employer only owe the Contractor a portion of the payment, the
• Hence, the additional works highly affect the original contract period and contract Contractor is entitled to charge interest from the Employer based on Clause 30.17.
sum. • Clause 30.17 stated that if the Employer fails to pay the Contractor the amount due
• To protect the Employer’s interest, a new contract for the additional scope of works on any certificate after the Period of Honouring Certificate, a simple interest based
shall be entered between the Employer and the Contractor. on Maybank Base Lending Rate plus 1% shall be payable by the defaulting party on
such outstanding amount until the date payment is made.
16. A site agent signed a daywork sheet on the work cannot be properly measured and
valued. 19. The Contractor for a hospital project has notified the SO in writing that the said parcel
However, the QS consider the signed daywork sheet are unreasonable excessive, he has reached practical completion.
intended to reduce the hours signed. Advice the S.O. on the 5 criteria prior the issuance of CPC under P.W.D. Form 203A.
What is the QS’s position under the above situation? Explain and quote the relevant • Clause 39.5(a) to (e)
clause based on PAM Form of Contract 2018 (With Quantities).
• According to Clause 11.6(d), the vouchers specifying the time spent daily upon the 20. The Government awarded a public housing project to A&B Construction Sdn Bhd
work shall be signed by the Site Agent and verified by the Site Staff and shall be based on P.W.D. 203A in October 2018. Due to the recent financial crisis, A&B
delivered to the Architect and Quantity Surveyor at weekly intervals with the final Construction Sdn Bhd not able to repay his debt and declared bankruptcy by the court
records delivered not later than 14 days after the work has been completed. order.
• As the Quantity Surveyor does not involve in the supervision works on site, he might Discuss the above situation and quote the relevant clause.
not understand the nature of works. • The Government may terminate the contract under Clause 51.2(a)(i) by giving a
• Besides, the vouchers verified by the Site Staff is deemed to be final. The duty of the notice to the Contractor.
QS is to value it and he has no right to challenge the Site Staff. • The consequence of termination as stated in Clause 51.2(b).

17. The Contractor issues a cheque for payment to the aluminium works NSC.
Subsequently, the Contractor decides to stop the cheque due to his company’s
financial difficulties.
4
21. The contactor gave a written notice to the project Architect to notify him that the • Clause 27.3 stated that subject to Clause 27.4, the Contractor shall not be required
works are practically completed on 15 April 2019. The project Architect has carrying to enter into a sub-contract with any NSC with a reasonable objection based on
out joint CPC inspection with the Contractor on 22 April 2019. After the joint available known facts and documented evidence that the financial standing or
inspection, the project Architect found out that there are no minor defects. solvency or technical competence of the NSC.
The project Architect seeks your opinion on the date and the issuance of the CPC.
Quote the relevant clause under PAM 2018. Tutorial 12
• Clause 15.2(b)(i) and 15.2(b)(ii) 1. The Contract Administrator plays an important role in a building contract. Please
• The date of the issuance of CPC shall be on 15 April 2019 because there are no minor explain the 5 Contract Administrator’s roles under this context.
defects. • Act as agent / contract administrator for the Employer
• Carry out his functions and duties under the contract with care and duties
22. Both PAM 2006 and PAM 2018 have the provision for retention fund. Discuss the • Delegate his authority
following: • Issue instruction to the Contractor as per Clause 2.0
a. The difference for the said provision. • Advise the Employer
• PAM 2006: The percentage of retained shall be 10% of the certified work done • Inspect and monitor the contract works
until 5% of the contract sum. • As an independent professional for the issuance of certificate
• PAM 2018: The percentage of retained shall be 5% of the certified work done. • Protect the Employer’s position in the contract
b. The similarity for the said provision.
• The time for release the first moiety and second moiety of the retention fund. 2. Mr A is the Architect for a factory awarded under PAM Contract 2018, the Contractor
did not follow the materials, goods and workmanship specification as stated in the
23. An Indian Convention Centre located at Batu Caves awarded to Ubud Construction Contract. Explain which clause of the provision allow Mr A to issue the instructions?
Sdn Bhd. The building contract used is PAM 2018. Under this circumstance, what is the Contractor’s entitlement?
The Employer, Batu Caves Management Sdn Bhd, has engaged 100 craftsmen from • Clause 6.5 stated that if the Architect finds any work, materials, goods or
India to perform the craving works not forming part of the contract. The craftsmen workmanship which is not in accordance with the Contractor, the Architect shall
delayed their works. As a result, Ubud Construction Sdn Bhd’s completion also instruct the Contractor in writing to……
delayed beyond the completion date. • In this case, the Contractor shall not entitle to an extension of time or compensation
Discuss the Contractor’s entitlement under this context. for any loss and/or expense that may be incurred under Clause 6.6.
• The Contractor is entitled to claim for EOT under Clause 23.8(k) and loss and/or
expense under Clause 24.3(e) on the delay on the part of the craftsmen employed 3. You are the Consultant Quantity Surveyor for a housing development in Kuala Langat
or engaged by the Employer in executing the work not forming part of the Contract contracted based on PAM Contract 2018. A dispute happened between the Employer
or the failure to execute such works. and the Contractor. As an expert in contract administration, the Employer seek your
• Clause 24.4 stated that the Architect or QS shall ascertain the loss and/or expense. advice on the method to resolve the dispute between the contracting parties. Please
advise the Employer 4 effective way to resolve the dispute.
25. For a mixed development project in KL, the Contractor has not agreed to the • Discussion and negotiation, Mediation. Arbitration and Litigation
nomination of a NSC under PAM 2018.
Explain to the Contractor his position under this situation. 4. In a building tender stated that the tender validity and open for acceptance for 3
• Clause 27.2 stated that the Architect shall not nominate any person as NSC against months from the date tender closing, but the Contractor withdraw it after 3 weeks,
whom the Contractor makes reasonable objection in accordance with Clause 27.3. explaining that a suddenly increased workload. Is the Contractor liable to the
• The Contractor shall make the reasonable objection in writing not later than 14 days Employer for the additional costs of a replacement Contractor?
from the receipt of the nomination instruction from the Architect. • The Contractor is not liable to the Employer for the additional costs.
5
• This is because the Contractor has no privity of contract with the Employer. 3. If the Contractor fails to complete the Works by the Date of Completion or within any
extended time under PWD 203A.
5. Clause 3.6 PAM Contract 2018 stated: “The Works Programme shall not constitute I. What certificate shall the S.O. issue in the above situation?
part of the Contract, whether physically incorporated or not into the Contract • Clause 40.1: The S.O. shall issue a Certificate of Non-Completion.
Documents:” II. What is the Government’s entitlement?
Explain your understanding on the above provision. • Clause 40.2: The Government shall be entitled the Liquidated and Ascertained
• The work programme is a tool used to monitor the progress of work and for the Damages calculated at the rate stated in the Appendix 1 from the period of the
assessment of extension of time and the effect of the delay and/or the disturbance issuance of CNC to the date of issuance CPC or the date of termination of the
to the work progress. Contract.
• It is also used to determine whether the Contractor is progressing regular and/or
diligently. 4. For project awarded based on PWD 203A, if in the opinion of the Contractor, the works
• Clause 3.6: The work programme shall part of the contract. has achieved practical completion, what is action need to be taken by:
• It is to allow the Architect to issue Variation Orders or to grant Extension of Time to I. The Contractor.
the Contractor if any changes happen. • Clause 39.2: If the Contractor considers that the works have achieved practical
• The Architect can give advice to the Contractor to revise the work programme. completion, the Contractor shall notify the S.O. in writing.
• If the work programme forms part of the contract, it is not practical and flexible II. The Superintending Officer.
because no extension of time can be granted to the Contractor. • Clause 39.3: Within 14 days of the receipt of such notice, the S.O. shall carry out
• Besides, if the Contractor fails to follow the work programme, it becomes a testing / inspection of the works. The S.O. shall either issue the CPC to the
Contractor’s default. Contractor if in his opinion the whole works have reached Practical Completion
• At the same time, the Contract Administrator is in breach because he fails to and have satisfactorily passed any inspection or test carried out by the S.O. or
supervise and monitor the works and result in defaults of the Employer. give instruction to the Contractor specifying all defective works which are
required to be completed by the Contractor before the issuance of the CPC.
6. Briefly explain the procedure to claim for extension of time under PAM Contract 2018.
• Clause 23.1(a) and 23.1(b). Tutorial 14
1. Multi Million Sdn Bhd is the main contractor for a public project which awarded under
Tutorial 13 P.W.D 203A 2010. Unfortunately, the Contractor not able to proceed with the works
1. Liquidated damages stated in Appendix PAM Contract 2018 is a genuine pre-estimate diligently and regularly due to the company financial problems.
of the loss and/or damage which the Employer will suffer. Explain to the Employer, Advice the Superintending Offer, on the rights of the Government.
what are those 4 factors can be take into consideration of the computation of the • The Government may terminate the contract 51.1(a)(iii) by give the written notice
liquidated damages. to the Contractor specifying the default and requiring the Contractor to remedy the
• Direct costs incurred under the contract. E.g. extend the appointment of the default within 14 days from the receipt of the default notice.
consultant • If the Contractor fails to remedy the breach within the stipulated period, the
• Loss of revenue and profit. E.g. rental and business Government shall have the right to terminate the Contract by giving a written notice
• Additional project administration costs. E.g. legal fees to the Contractor as stated in Clause 51.1(b).
• Interests and finance cost. E.g. increase of loan interest paid • The consequences of the termination of the Government and the Contractor are
shown in Clause 51.1(c).
2. An affordable housing awarded under PWD 203A in delay. As the Contractor for the
said project, explain the process to claim extension of time under the provision.
• Clause 43.1
6
Final • In PWD Clause 47.3, the S.O. shall instruct the Contractor to terminate the sub-
1. Explain the type of instruction that can be issued to a Contractor. contract.
• Clause 1.4: Discrepancy or divergence between documents • If the Contractor fails to do so, the Government may terminate the contract based
• Clause 6.3: Inspection and testing on Clause 51.1(a)(vii).
• Clause 6.5: Work not in accordance with the contract
• Clause 11.3: Issue of variation after practical completion 5. There should not be new VO or AI issued after CPC, only for minor works. What should
• Clause 11.4: AI on P.C. Sums and Provisional Sums be done to avoid this situation?
• The Architect should inspect the completed work jointly with the Contractor,
2. The reasons of EOT. Employer’s representative, NSC and the other Consultant before CPC is issued.
• The EOT provision is for all intended purposes to preserve the Employer’s rights to • It is the Architect’s duties to ensure all the construction meets the approved
Liquidated Damages. drawings and specification.
• If the EOT provision is deleted in the building contract, the Architect has no ground • If anything was found not constructed according to the drawings or specification and
to grant EOT which cause the contract period “at large”. not listed as a punch list item, he shall request the Contractor to make good on the
• Time at large means that the Contractor is not bound to complete the works on or items.
before the completion date, but at his own reasonable time.
• However, the Contractor is still liable to pay for the general damages under the 6. Based on the sectional completion, explain how the facilities or building can be used
common law. before the project completed? Section / Partial
• Sectional: Clause 21.2 and 21.2 (PAM) v Clause 41.1 and 41.2 (PWD)
3. How to mitigate the peculiar condition to ensure the Contractor preserve his right to • Partial: Clause 16.1 and 16.2 (PAM) v Clause 42.1 (PWD)
claim EOT?
• Before signing the contract, the Contractor shall have the knowledge on the Contract. 7. What happen if the Contractor failed to comply AI?
• If he found the peculiar condition, he can discuss with the contract administration. • Clause 2.4: The Employer may employ and pay the other persons to complete the
• Amendments can be made in the standard form of contract provided the agreement works and the cost of employing the other persons and the additional cost shall be
between both parties are achieved. set-off.
• In the event of delay, the Contractor shall follow the proper procedures for the • Clause 25.1(d): The Employer may determine the Contractor’s employment if he
application of EOT. persistently refuses or neglects to comply with an AI.

4. Explain the clause of Contractor shall not wholly or substantially sub-contract the 8. What is as-built drawings?
works under PAM and PWD. • Actual drawings to shows the works constructed on site.
• See Clause 17.0 (PAM) and Clause 47.0 (PWD). • For the purpose of reporting the work progress.
• Clause 17.2 prohibited the Contractor to assign his rights or benefits under the • See Clause 3.10: As-built drawings and operation and maintenance manuals.
Contract to any other parties without the written notice of the Employer.
• Clause 17.3 prohibited the Contractor to wholly or substantially sub-contract the 9. Steps from CPC until the Contractor move out.
works. PAM 2018
• No prohibition for the Contractor to sub-contract the specialist trades to the special • Release of first moiety of retention fund
sub-contractor i.e. plumbing sub-contractor. • Release of Performance Bond
• In PAM Clause 25.1(e), the Employer may determine the Contractor’s employment. • Defects Liability Period
• Issuance of Certificate of Making Good Defects
• Release of second moiety of retention fund
7
• Final Account and Final Certificate • Discuss with Architect / S.O.
PWD 203A • Follow all the procedures for the application of EOT.
• Defects Liability Period • See Clause 23. (PAM) and Clause 43.0 (PWD).
• Issuance of Certificate of Making Good Defects
• Release of Performance Bond / Performance Guarantee Sum 15. NSC notices the discrepancies between main and subcontract.
• Final Account and Final Certificate • NSC can ignore it because he has no obligation to rectify or inform anyone.
• NSC is not the party in the main contract, he has no contractual relationship.
10. What is SO’s duties if the Contractor cannot finish on time? • NSC only has the contractual relationship with the main Contractor.
• Issue a letter of enquiry to the Contractor. • Thus, NSC only needs to fulfil his obligation under the sub-contract.
• Issue Certificate of Non-Completion if the works delay beyond the completion date • However, if the discrepancy involves critical aspects or related to the health and
as per Clause 40.1. safety, he should inform the Architect.
• Under this circumstance, the Government is entitled to impose Liquidated and • This is to prevent his liabilities in litigation.
Ascertained Damages with the issuance of CNC. • If discrepancies in terms of materials and goods, follow NSC Contract.
• Without the issuance of CNC, the time will be at large and cause the Government • If discrepancies in terms of contract condition, follow Main Contract.
cannot claim for LAD.
• The LAD can be deducted from the any money due or to become due to the Additional
Contractor or Performance Bond or debt due from the Contractor. Expressed Terms
• The Government may employ and pay the others to complete the outstanding works. • Conditions as stated in the standard form of contract
• E.g. performance bond and retention sum.
11. How can the Contractor avoid LD?
• Before the issuance of CNC, he should ask the Employer/Government’s permission Implied Terms
to employ others to ensure the works are not delayed provided he follows Clause • The Contractor shall carry out works with all proper skill and care
17.2(PAM) / Clause 47.1(PWD). • Materials should be in reasonably fit for purposes and reasonably quality
• If the CNC is issued, he still can lock for others to complete the works to reduce the • Fit for purposes – for design and build contract
amount of LD by paying the costs and expenses incurred to employing others. • A duty to operate, e.g. obtain the building plan approval
• Alternatively, if there is no CNC / CPC issued, the Employer cannot impose LD. • An obligation not to hinder or prevent the Contractor from carrying out his works
• An obligation to exercise his discretion honesty and in good faith
12. Discrepancies/problems, what type of AI should be issued?
• Clause 6.5 and 11.1 3 Ways Variations Might Occur
• The Employer may change their minds
13. Delay due to VO, what should the Contractor do? • Discrepancy between tender, contract and the construction drawings
• Advise the Architect to issue EOT. • Changes in legislation and other external factors
• The relevant event is Clause 23.8(h): compliance with AI issued by the Architect.
• The Contractor shall apply the EOT by following Clause 23.1(a) and 23.1(b). Different contract deal with the contract price in different ways
• Contract with BQs – paid upon the works described and quantified
14. Delay happen, what should the Contractor do before delay happened? • Lump Sum Contracts – paid upon the schedule of works
• The Contractor has used his best endeavour to prevent delay. • Remeasurement Contracts – paid in full based on the works completed and quantities
• Relevant event stated in the contract happens. actually carried out

8
Types of payment in construction • Must be date – the certificate is issued to record an event or contractual status at a
• Advance payment specific point of time.
• Payment based on work executed • Must refer to the Contract or works to which the Architect to issue a certificate.
• Stage payment • Must be directed or addressed and issued towards the relevant party.
• Bullet payment • Must be sent, served or delivered in accordance with Clause 34.0
• Must refer to a specific issue for which the Architect is empowered to issue the
Why the original interim certificate issue to the Employer in lieu to the Contractor? certificate. E.g. extension of time, interim payment.
• The Employer is the pay master. • Must have a specific declaration by the Architect.
• The interim certificate must be addressed to him to enable him to draw the loan from • Must be signed by the Architect as named in the Article 3 of the Article of Agreement.
the bank by using the interim certificate.
Good Practice Before Issuing CPC
What would the situation if the Contractor not submit their progress claim in the interim • Receipt of the written confirmation from all consultants that the works under their
claim interval? respective scope have been completed to their satisfaction.
• If the Contractor does not submit the progress claim which mean the work done for the • A physical inspection of the works
month is zero.
• The QS still need to issue the valuation certificate to the Architect and the amount Effects of the Issuance of CPC
stated in the interim certificate for the month will be in zero. • Completion of the works by the Contractor.
• The Employer can take the possession of the completed works.
What would the situation if the Architect took more than 21 days to issue the interim • The commencement dates of the Defects Liability Period and the period to complete
certificate? the Final Account.
• He can additional time will be counted into the period of honouring certificate which • The Contractor is entitled to receive half of the retention fund.
lead to a shorter period of honouring certificate. • The Contractor’s liability to liquidated damages and insure the works ends

If the Employer fails to honour the certificate, the Contractor may: Importance of Certificate of Non-Completion
• Suspend the work under Clause 30.7 (Full amount) • The LD which the Employer is entitled to claim shall be calculated at the rate set out in
• Charge interest under Clause 30.17 (Part of the amount) the Appendix for the period between the date of CNC and the date of the CPC.
• Determine his own employment under Clause 26.1(a) • The failure to issue the CNC on time may render the time to be set at large for the
• Refer to adjudication under Clause 34.1 contract and the Employer may lose his right claim LD for non-completion.
- To remind the Contractor that the time is the essence.
Purpose of Retention Fund - To request the Contractor to prepare a accelerate programme for the speedy
• If the Contractor fails to perform his obligation such as failure to rectify the defects, the completion of all remaining works along with an estimated date as to when the Practical
Employer may utilize the fund to pay the third party to carry out the defective works. Completion can be achieved.
• Recover the Employer’s cost and loss - To remind the Contractor to extend all insurance policies related to Clause 19 and 20.
• Safety provision against re-possession of materials and goods by the Contractor’s - To remind the Contractor to extend the Performance Bond, if required.
supplier, if the retention of title is still not transferred to the Contractor. - To notify all NSC of the issuance of the CNC.

Essential Features of an Architect Certificate Determination for Breach


• Must be tangible, in writing and in the form of a physical document. • Under common law.
• The party may make clear that it has no intention of performing further.
9
• The party may be guilty of such a serious breach of contract that will be treated as - Proper planning, scheduling and monitoring of works to ensure adequate resources,
having no intention of performing. time, worker allocated for each activity in the work programme.
• Bring the contract to an end • Proactive actions
- Proactive measures including quick responses to non-compliance from the Employer,
Determination of the Contractor’s Employment confirm verbal instruction, request additional information through Request for
• The contract still exists even though the contractor’s employment is determined. Information (RFI) and apply for Extension of Time in the evets of delay.
• The conditions laid down the procedures for determination.
• Not all of these circumstances amount to breach of contract to justify determination. Liquidated Damages
• Appointment of new contractors for the continuation of works. • A pre-determined sum which becomes payable by a party to a contract if certain
specified breaches occur.
Contractual Relationship • Replace the right to claim damages measured by the amount of loss actually suffered.
• The Employer appoints the relevant consultants, Architect, QS and Engineer. • The parties to know from the start as much as possible about the risks they bear.
• The Employer enters into a main contract with the main contractor. • They also save time and money on arbitration and litigation.
• The main contractor entered into a sub-contract with the nominated sub-contractor • The parties are fully aware of the monetary rights and liabilities and the amount that
appointed by the Employer on Architect’s Instruction. the Contractor could price for the risk.
• The main contractor under Clause 17.3 shall not wholly or substantially sub-contract the • If the LD amount is too high, whereby the Employer is benefit from the default, the
contract works to other domestic contractors. Contractor may contest with proof.
• The NSC contract is signed between the main contractor and NSC. • A claim for unliquidated damages under common law is available if ‘NIL’ is inserted in
• In the event of any discrepancy between the main contract and NSC contract. The NSC the Appendix of the conditions which treats the LD as inoperative and the LD clause was
contract shall prevail. strike off in the contract.
• Any assignment of the NSC shall obtain the consent from both the Employer and the
main contractor. Certificate of Completion and Compliance
• Any contention in relation to pre-tender process upon signing of the sub-contract will The Principal Submitting Person (PSP) must sign a CCC to confirm that the project:
not be entertained. • For which the PSP had obtained building plans approval from a local authority.
• Is completed.
Effective Method to Prevent Construction Claim • Has met all statutory requirements with regards to health and safety aspects.
• Proper documentation • Is ready to be occupied with all essential utilities services connected.
- Properly record, keep and document the factual evidence like daily progress reports,
progress photographs, minutes of meeting, request for information and AI. Presentation of Claim
• Knowledge on the contract • Introduction: names of parties, original contract sum, commencement and completion
- The Contractor should read the contract / tender document thoroughly, understand date, details of condition of contact, details of EOT claimed and certified amount.
their role, obligations and responsibilities. • Facts relating to the claim:
• Preservation of rights • Contractual basis of the claim: claim for L/E or additional expenses within the conditions
- Served written notice of potential claims, follow the procedures and time frame as or claim for common law damages due to breach of expressed or implied terms.
stipulated in the contract. • Details of the claim: any instructions or delays which have occurred, reasons and effects
• Qualify the changes of delay and supporting documents.
- The Contractor should qualify any valuation involves additional cost prior the execution, • Evaluation of the claim: site overhead or preliminary costs, head office overheads,
negotiation or signing off. depreciation on plants, increased insurance costs, interest and finance charges, cost
• Planning, scheduling and monitoring claims from sub-contractors, adjustment of levies, cost escalation and loss of profit.
10

You might also like