PEKERJAAN RENOVASI GEDUNG 17

PT. SATU DUA TIGA

PRECENDECE DIAGRAM METHOD (PDM)

11 2 13
I
12 1 14

-1 10 2 12
H
-2 7 4 11 12 2 14 16 1 17
E L
8 1 12 16 0 17
14 2 16
K
0 2 2 14 0 16
A 17 0 17
0 0 2 FINISH
0 0 0 2 3 5 -1 4 5 9 1 10 4 14 17 0 17
START C D G
0 0 0 2 0 5 4 0 9 10 0 14
0 1 1
B -1 8 3 11
1 1 2 F
14 6 17

9 2 11
J
15 6 17

NAMA KEGIATAN KODE DURASI/MINGGU AKTIVITAS SEBELUM HUBUNGAN LOGIS


PEKERJAAN PENDAHULUAN A 2 - A-C (FS = 0)
PEKERJAAN BONGKARAN B 1 - B-C (FS = 0)
PEKERJAAN PONDASI DAN URUGAN C 3 A,B C-D (FS = -1)
PEKERJAAN BETON D 5 C D-E (FS = -2)
D-F (FS = -1)
D-G (FS = 1)
D-J (FS = -1)
PEKERJAAN PASANGAN E 4 D E-H (FS = -1)
E-I (FS = -1)
E-K (FS = 0)
PEKERJAAN LANTAI F 3 D 0
PEKERJAAN ATAP/PLAFOND G 4 D G-K (FS = 0)
PEKERJAAN KUSEN, PINTU DAN JENDELA H 2 E H-K (FS = 0)
PEKERJAAN INSTALASI LISTRIK I 2 E I-K (FS = 0)
I-L (FS = 0)
PEKERJAAN SANITASI J 2 D 0
PEKERJAAN PENGECATAN K 2 E,G,H,I K-L (FS = 0)
PEKERJAAN LAIN-LAIN L 1 I,K 0