Professional Documents
Culture Documents
Extensive Survey Project
Extensive Survey Project
Extensive Survey Project
BELAGAVI-590018
2015-2016
We express our deep sense of gratitude and thanks to Head of Civil Engineering
Department, Dr.NIRANJAN P.S, for providing necessary facilities and encouraging us
to make this project grand success.
We fell with a great pleasure to express our deep of gratitude and profound thanks
to staff members of the Department of Civil Engineering Their valuable guidance in
both field and office work helped us to complete the project within the prescribed time.
Finally we express our sincere thanks to lab instructors who helped us in the camp
to complete the camp successful and all our friends for their kind co-operation and help
for the successful completion of the project.
Examiners:
1. …………………… 2. ……………………
INDEX
1.0 INTRODUCTION .............................................................1-3
1.1 FOLLOWING ARE THE TECHNICAL AIMS AND ABILITIES
2.5 SPILLWAY
2.6 IRRIGATION
2.6.3 RELATION BETWEEN DUTY OF WATER (D), DELTA (Δ), BASE PERIOD (B)
3.4.3DESIGN OF PUMP
3.5.4 DISINFECTION
HIGHWAY PROJECT……………………………..................44-57
4.0 TRANSPORTATION:
4.8 CURVES
FIELD DATA…………………………………………………63-86
BIBLIOGRAPHY………………………...…………….………..87
EXTENSIVE SURVEY PROJECT B- 5
2015-16
1.0 INTRODUCTION:
OBJECTIVES:
This extensive survey project is conducted to acquire a practical knowledge and
applications of theory and overcome the difficulties that could arise in field during
surveying. We also learn the use of different survey instrument and to develop the team
spirit at work. It also helps to develop the confidence in handling of survey project. An
extensive survey project camp is usually arranged for civil engineering students.
We conducted survey for a new tank project, water supply scheme, highway project and
old tank project.
With this motive survey camp was arranged with the help of our lecturers at Ghati
village, Doddaballapura Taluk, Bangalore Rural District which is 60km away from
Bangalore
We were able to finish the survey works under guidance of our faculties and the
knowledge gained by us in our course of study.
The second stage work of investigation includes the survey work at the site in order to
collect the data necessary for the design of project elements, preparation of drawings,
estimates etc. the office work is confined to the designs, drawings and estimates of the
project.
placed in the rear in the sanctum sanctorum. Good transportation facilities from all
round the corners of the state. The famous cattle fair is also held here in December, it is
very famous.
Reconnaissance survey:
It means the process of visiting the site and surrounding area for knowing nature of the
soils, rock and ground water table which are likely to be encountered during
construction. The information obtained during site reconnaissance may sometimes it is
sufficient for judging the general suitability of site or for making of helps in deciding
about the exploration techniques which may be necessary for further investigation.
Reconnaissance survey should include an inspection of the following things: local
topography, excavation, quarries, evidence of landslides, behavior of existing structures
at or near the site, water levels in the streams, flood marks, nature of vegetation etc.,
Study of toposheet:
This sheet gives the topographical features of the locality like alignment of a railway
line, roadway, streams and its distributaries and permanent structures located in that
locality. This map helps in selecting the site for a new tank and also gives clear picture
of transportation to the proposed area in proposed site for the transportation of men and
material for their construction. From this we can know the approximate catchment area
of site. This map has to be study before reconnaissance survey.
Fly Leveling:
The main objective of the fly leveling is to establish a temporary bench mark (TBM)
near the site which is accurate, from MSL (mean sea level). In Ghati Subramanya, we
are conducted fly leveling from Makalidurga railway station; it is 3km away from the
Ghati Subramanya and The MSL of 846.645m (RL OF GL on railway sleeper) to our
project site by using Auto level with tripod and leveling staff.
Average annual rainfall for doddaballapura area from Meteorological department data is
80cms.
Bad year rainfall is 2/3 of 80cm = 53cm
Runoff coefficient is usually assumed as 15% to 20%
Assuming as 20%.
Annual yield = 20/100 × 53 = 10.60cm
Yield from catchment = (4.96×106) × 10.60 = 0.52576×106cum/year.
NEW TANK
PROJECT
INTRODUCTION
The flow rate of a river or a natural stream may vary considerably during different
periods of a year. It may carry little or no water during some periods of a year and may
carry huge amount of water after heavy rains thus become a raging torrent and a hazard
all along its banks. During extremely low flows it may not be possible to meet the
demands of the consumers if water is drawn directly from a river. As such it is essential
to create a reservoir or an artificial lake by constructing a dam across the river which can
retain the excess water from periods of high flows for use during the periods of low
flows or droughts. In addition to conserving water for later use, the storage of floodwater
may also reduce flood damage on the downstream of the reservoir.
Engineering surveys
The area of the dam site, reservoir and other associated works is surveyed and a
contoured plan of the entire area is prepared. From the contoured plan the storage
capacity and the water spread area of the reservoir at various elevations are determined
as indicated below. From the contoured plan of the reservoir site the water spread area of
the reservoir at any elevation is directly determined by measuring the area enclosed by
the contour corresponding to that elevation. The water spread areas at different
elevations are thus determined and the same are plotted against elevation to obtain an
elevation-area curve.
The storage capacity of the reservoir may be determined by taking contour areas at equal
interval and summing up by trapezoidal formula or prismoidal formula. Thus if V is the
storage volume and A1, A2, A3, An… are the areas enclosed by the successive contours
at an interval h, then the various formulae are as follow.
Trapezoidal Formula
h
A1 A2
V=∑ 2 (1.1a)
A1 An
2 A2 A3 A4 An 1
V=h (1.1b)
Prismoidal Formula
h
A1 4 A2 A3
V=∑ 3 (1.2a)
h
( A1 An) 4( A2 A4 .....) 2( A3 A5 .....)
V= 3 (1.2b)
The storage volumes up to various elevations are determined by using any of the above
noted formulae and the same are plotted against elevation to obtain elevation-capacity
curve.
The contoured map of the reservoir area also indicates the land and property which
would be submerged in the reservoir when filled up to certain elevation and thus enables
the estimation of compensation to be paid to the owners and the time schedule according
to which they must be moved, as the reservoir is gradually filled during the construction
of the dam.
Useful Storage.
The volume of water stored between the normal pool level and the minimum pool level
of a reservoir is called the useful storage. In a multipurpose reservoir the useful storage
may be subdivided into conservation storage and flood control storage in accordance
with the adopted plan of operation of the reservoir. The useful storage is also known as
live storage as it can be used for various purposes required to be served by the reservoir.
Dead Storage.
The volume of water held below the minimum pool level of a reservoir is known as dead
storage. It cannot be used for any purpose under ordinary operating conditions.
Surcharge Storage.
The volume of water stored between the normal pool level and the maximum pool level
of a reservoir is called surcharge storage. The surcharge storage is an uncontrolled
storage as it exists only while a flood is occurring and cannot be retained for later use.
Bank Storage.
The bank storage is the volume of water that is temporarily stored in the permeable
banks of a reservoir when the reservoir fills and drains out as the water level in the
reservoir is lowered. The bank storage effectively increases the capacity of the reservoir
above that indicated by elevation-capacity curve. The amount of bank storage depends
on geologic conditions and may amount to several percent of the reservoir volume.
Valley Storage.
The volume of water held by a natural stream channel is known as the valley storage.
Even before a reservoir is constructed certain amount of water is stored in the natural
stream channel as a valley storage which may however vary. After the construction of a
reservoir the storage capacity increases but the net increase in the storage capacity is
equal to the total storage capacity of the reservoir minus the natural valley storage. This
distinction of the total and net storage capacities is of no importance for storage or
conservation reservoirs, but from the point of view of flood control the effective storage
capacity in the reservoir is equal to the useful plus the surcharge storage minus the
natural valley storage corresponding to the rate of inflow to the reservoir.
RESERVOIR YEILD:
This is the amount of water that can be drawn from reservoir in a specified time interval.
General considerations
The successful design, construction, and operation of a reservoir project over the full
range of loading require a comprehensive site characterization, a detailed design of each
feature, construction supervision, measurement and monitoring of the performance, and
the continuous evaluation of the project features during operation. The design and
construction of earth and rock-fill dams is complex because of the nature of the varying
foundation conditions and range of properties of the materials available for use in the
embankment. The first step is to conduct detailed geological and subsurface
explorations, which characterize the foundation, abutments, and potential borrow areas.
The next step is to conduct a study of the type and physical properties of materials to be
placed in the embankment. This study should include a determination of quantities and
the sequence in which they will become available. The design should include all of the
studies, testing, analyses, and evaluations to ensure that the embankment meets all
technical criteria and the requirements of a dam.
Rock.
Sands and Gravels and
Clayey material.
This is however a broad classification because within each category the properties of
materials may vary widely and also the materials of more than one category may be
found interspersed in the foundation under the proposed dam. Therefore the design of
anyone dam may involve a variety of foundation problems. The main problems of each
of the above noted three types of foundations are as indicated below.
Rock
Rock foundations in general do not present any problem. The shear stresses induced in
these foundations by earth dams will usually be well within their capacity and they
would allow only small seepage to take place under the dam. However, in some cases
they may require grouting if there are through joints, fissures, crevices, fault planes or
permeable strata present in the foundation rock, which if not grouted would result in
erosive leakage and excessive loss of water.
Clayey material
Clay foundations require greatest attention since they are more susceptible to shear
failures. Clays being highly impervious do not permit the excess water present in their
voids to be drained out easily under the load of the dam and hence their consolidation
takes a long time which may even extend to number of years in many cases. As such
when a dam is constructed on clay foundations due to lower rate of consolidation the
shear strength of the soil increases at a slow rate. Hence the shear stresses induced in the
soil by the load of the dam may exceed the shear strength of the soil which may result in
the failure of the dam. For clay foundations therefore, it is necessary to ensure that the
foundation shear stresses are less than the shear strength of the soil. For this it may
sometimes be necessary to flatten the slopes of the dam to spread its load on a larger
area though steeper slopes could have been otherwise provided so far as the stability of
the dam alone is concerned.
In this section the various considerations to made for determining the cross-section of an
earth dam are discussed.
For determining the cross-section of an earth dam there are no mathematical analyses or
formulae as in the case of rigid dams. The cross-section of an earth dam however
depends on the following factors.
Foundation conditions;
Availability of the materials of construction within reasonable range;
Physical properties of the materials available for construction;
Methods of construction to· be adopted and the degree of construction control that is
anticipated;
Types of earth moving machinery;
Diversion considerations and construction schedule;
Climatic conditions in relation to placement moisture content control; subsequent
moisture content changes, etc.
Safety with respect to stability and seepage.
On the basis of these factors the cross-section of an earth dam may be determined which
involves the consideration of the following parameters.
Top width
Side slopes
Free board
Top Width.
The crest width of the earth dam depends upon the following considerations :
1. Nature of the embankment materials and minimum allowable percolation distance through
The embankment at the normal reservoir level.
2. Height of the structure.
3. Importance of the structure.
4. Width of the highway on the top of the dam
5. Practicability of construction.
6. Protection against earth quake forces.
Following are some of the Empherical expressions for the top width b of the earth dam, in
terms of the height Z of the dam:
1. b = 0.2×Z+3 for very low dams <15m
2. b = 0.55Z1/2+0.2Z for height less than 30m
3. b=1.65×(Z+1.5)1/3 for height greater than 30m
Where,
Z=Avg. height of the dam in m =12.1m
Top width = (0.2×12.1+3) =5.42
Side slopes.
No specific rules can be given for determining the side slopes of an earth dam. The
general procedure is that on the basis of experience with similar dams side slopes are
considered and the same are modified if necessary after the stability analysis is carried
out. It is obvious that the most economical dam is obtained when its volume is Minimum
and therefore when the side slopes have maximum steepness consistent with stability.
However, in general the side slopes of a dam depend on the physical properties of the
material of construction, the strength of the foundation and the type of the dam i.e.,
homogeneous, zoned or diaphragm. The stability of side slopes depends mainly on the
physical properties of the materials for construction of the dam. Further if the foundation
is weak flatter side slopes will be required but if the foundation is strong steeper side
slopes may be provided. Similarly a zoned dam permits the use of steeper side slopes
because in this case the stronger materials are placed where they are most effective in
resisting shear stresses and the drainage systems control and reduce pore water
pressures. In usually the slope may vary for low height dam of homogeneous silt clay
soil up to <15m, the slope will be 1.5H: 1V on upstream side or reservoir side and 2H:
1V on downstream side is commonly adopted.
Freeboard.
Freeboard is the difference in the elevation of the crest of the dam and the still level in
the reservoir. Sufficient freeboard must be provided so that there is no possibility
whatsoever of the dam being overtopped. The freeboard may be classified as normal
freeboard and minimum freeboard. The freeboard above the full reservoir level (FRL) is
known as normal freeboard, and the freeboard above the maximum water level (MWL)
is known as minimum freeboard.
This condition is not exactly fulfilled by any practical earth dam section. However, A.
Casagrande has demonstrated that in general for earth dam sections the seepage line for
most of its length coincides with Kozeny's theoretical parabola called the base parabola,
but it deviates from the base parabola for a short distance at the upstream or the entrance
face of the dam in all the cases and at the downstream or the exit face of the dam in
some cases. The amount and character of the deviations depend on local conditions at
these portions of the dam. Thus for the different types of earth dams the seepage line
may be determined as indicated below.
Homogeneous earth dam with a horizontal drainage blanket.
Homogeneous earth dam without any arrangement for horizontal drainage
Blanket.
Homogeneous earth dam with rock toe.
Zoned earth dams with a central core – Earth dam of composite cross-section.
A Purely homogeneous section poses the problems of seepage, and huge sections are
required to make it safe against piping, stability, etc. Due to this, a homogeneous
section is generally added with an internal drainage system; such as a horizontal
drainage filter as shown in fig, rock toe, etc. The internal drainage system keeps the
phreatic line (i.e. top seepage line) well within the body of the dam, and steeper slopes
and thus, smaller sections, can be used. The internal drainage is, therefore, always
provided in almost all types of embankments.
We shall discuss the graphical method of the determination of phreatic line by
casagrande method. casagrande assumed the phreatic line to be a base parabola with its
focus at F, the starting point point of filter FE. The following is the procedure for
locating the phreatic line graphically.
AB is the upstream face. Let its horizontal projection be L. on the water surface,
measure the distance BC=0.3L. then the point C is the starting point of the the base
parabola.
To locate the position of the directrix of the parabola, we utilize the principle that any
point on the parabola is equidistant from the focus as well as directrix. Hence with the
point C as the centre, and CF as the radius, draw an arc to cut the horizontal line through
CB in D. Draw a vertical tangent to the curve FD at D. CD=CF Hence the vertical line
DH is the directrix.
The last point G on the parabola will evidently midway between F&H.
In order to locate the intermediate points on the parabola we use the principle that its
distances from focus and directrix must be equal. EX. To locate any point P, draw
vertical line QP at any distance x from F. measure the distance QH. With F as center and
QH as the radius, draw an arc to cut the vertical line through Q in point P.
Join all these points to get the base parabola. However, correction is to be made at the
entry point. The line must start from B, & not from C. Also the phreatic line is a flow
line, must start perpendicularly to the U/S face AB which is a 100% equipotential line.
‘ ’ is obtained as
= b
Since the pressure all along the seepage line is atmospheric, the only change in head
along this line is that due to drop in the elevation. Hence the successive equipotential
lines will meet the seepage line at equal vertical intervals.
The seepage line drops vertically into a horizontal filter drain or a rock toe filter.
For an earth dam composed of homogeneous material without filter at downstream toe
the seepage line will meet the downstream face at a point above the base of the dam. The
location of the seepage line for a homogeneous section and the point where the seepage
line meets the downstream face depend only on the geometry of the cross-section of the
dam. The positions of the seepage line as well as that of the point where it meets the
downstream face are not influenced by the permeability of the material composing the
dam so long as the material is homogeneous.
For most of the length the seepage line coincides with the base parabola. The focus of
the base parabola lies at the break out point of the bottom flow line where the flow
emerges out from relatively impervious medium to a highly pervious medium.
The presence of pervious stratum in the foundation below the dam does not influence the
position the seepage line.
For a zoned earth dam with an impervious core in the centre the effect of the outer shells
can be neglected altogether. Thus in this case the seepage line may be drawn only for the
core. The focus of the base parabola is located at the downstream toe of the core. The
seepage line is assumed to be practically horizontal through the upstream shell, the
downstream shell acts as a drain and is saturated to a depth just enough to carry the
seepage flow passing through the core.
b n d
5.42 1.75 5
HEIGHT OF
EMBANKMENT AREA IN Sq. VOLUME OF EMBANKMENT IN
CHAINAGE R.L (h) in m M CUB. M
0 811.935 0 0
5 810.925 0.45 2.793375
10 809.745 1.75 14.844375
15 808.275 3.1 33.6195
20 807.075 4.4 57.728
25 806.025 5.3 77.8835
30 805.115 6.2 100.874 113049.4988
35 804.175 7.2 129.744
40 803.225 8.1 158.7195
45 802.565 8.8 183.216
50 802.595 8.8 183.216
55 802.995 8.4 169.008
60 803.005 8.3 165.5435
It is essential to provide a spillway of sufficient capacity (or outflow rate through the
spillway) so that surplus flood water is discharged keeping the water level in the
reservoir below some predetermined maximum level and no damage is caused to the
dam. A spillway of insufficient capacity may however lead over-topping of the dam
resulting in serious damage to the dam or in the failure of the dam. On the other hand an
over-estimation of the spillway capacity would result in an uneconomical design.
Discharge Channel
The flow released through the control structure is usually conveyed to die stream bed
below the dam in a discharge channel or waterway. The main function of this is to
convey water safely from the reservoir downward to the river. The conveyance structure
may be the do~ face of the spillway, an open channel excavated along the ground
surface, a closed conduit placed through or under a dam, or a tunnel excavated through
an abutment.
The length of the waterway weir i.e., L is calculated from Lacey’s regime formula
L 4.83 Q
Where, Q=Discharge in cumec
L=Length of the water way in meters
Q = 10×52/3=29.24cumec
Design of weir wall: The weir wall is usually trapezoidal in cross-section with either
both upstream & downstream faces inclined; or upstream face vertical & downstream
face inclined. The design of the weir wall involves the determination of its top & bottom
widths such that the section will be stable under the condition of maximum stress. In
general the condition of maximum pressure on a hydraulic structure is that in which the
head water is at the level of the crest of the weir or at the top of the crest shutters (if any)
& no water is flowing over the weir so that there is no water on the downstream side.
Type of weir wall: The weir is consists of horizontal floor and masonry crest with
concrete bed.
Dimension of the weir wall :
Crest width of weir wall should be greater than 0.6 m, so the crest width is taken as
1.0m. Upstream side batter may be kept as 0.4H: 1V and the downstream side batter
should not be flatter than 1:1.The bottom width (B) of the weir wall should not be less
than
Where, d = head of water over the weir wall at the time of max., flood. I.e. 0.5m
H= height of weir.
G = Specific gravity of floor material. (For concrete 2.4)
Height of weir above foundation (H) = FTL –General GL
The general ground level or hard rock level is assumed to be 807.08m.
H =809m-807.08m== 1.92m
2.6 IRRIGATION:
Irrigation may be defined as the process of supplying water to land by artificial means
for the purpose of cultivation. Ordinarily water is supplied to land by nature through rain
but generally it is not enough in the proper growth of plants. As such the basic objective
of irrigation is to supplement the natural supply of water to land so as to obtain an
optimum yield from the crop grown on the land.
Delta is defined as the total depth of water over the irrigated land required by a crop
grown on the entire base period of the crop. It is denoted by a symbol Δ Greek delta .
The delta for any may be determined by dividing the total quantity of water in hectare-
meters required by the crop for its growth by the area of the land in hectares over which
the crop is growing. Delta may be defined as the total water required by a crop for its
growth in hectare-meter per hectare.
or a field of area hectares corresponding to the depth of water Δ meters the quantity
of water supplied for growing a crop on the field.
= × Δ hectare-meter
= × Δ×104 m3 __ __ __ __ __ __ __ __ 1
Further for the same field of area D hectares for growing a crop on it if water is supplied
at the rate of 1 cumec for the entire base period of B days, then the total quantity of
water supplied to the field.
=1×B×24×60×60 m3
=8.64×104×B m3 __ __ __ __ __ __ __ __ (2)
Equating (1) & (2). We get
× Δ×104 = 8.64×104×B
__ __ __ __ __ __ __ __ (3)
The above equation gives a relation between duty of water, delta and base period of a
crop.
The required quantity of water, manure, fertilizers etc… may not be available to
cultivate the culturable commanded area.
If the lands fallow i.e.… without cultivation for one or more crop seasons the fertility of
the soil increases.
A portion of the land is required to be left uncultivated to serve as a pasture for the
cattle. The area under cultivation at any instant of time needs to be restricted to protect
the land water logging especially in areas where water table is high.
Thus during any crop season only a part of culturable commanded area is put under and
hence the culturable commanded area may be sub divided into two categories.
Culturable cultivated area:
It is that portion of the culturable commanded area which is actually cultivated during a
crop season.
Culturable uncultivated area:
It is that portion of the culturable commanded area which is not cultivated during a crop
season.
Intensity of irrigation:
The intensity of irrigation is defined as the percentage of the culturable commanded area
proposed to be annually. Usually the area irrigated during each crop season is expressed
as a percentage of the culturable commanded area which represents the intensity of
irrigation for the crop the season. By adding the intensities of irrigation for all the crop
season the yearly intensity of irrigation may be obtained.
CUMEC DAY: The total quantity of water flowing for one day at the rate of 1 cumec is
known as cumec day. One cumec day is equal to 8.64 hectare-meters.
CROP RATIO: It is defined as a ratio of the areas of the land irrigated (or anticipated
to be irrigated) during the two main crop seasons viz., rabi and kharif. Thus it is also
sometimes called Rabi-Kharif ratio.
CAPACITY FACTOR: Canal is designed for certain maximum discharge capacity, but
it need not carry the same discharge at all the times. As such the ratio of the mean
supply discharge of a canal for certain duration to its maximum discharge capacity is
defined as capacity factor.
2. CONTOUR CANAL: The canal in which is aligned nearly the parallel to the
contours of the country. It can irrigate area only one side. As the ground level on the
other side is higher so it is not necessary to construct the bank on that side. Such a canal
with only one bank is known as single bank canal. However when both the banks are
provided it is known as double bank canal. A contour canal has to cross drainage and
hence for this canal cross drainage work is required to be provided.
3. SIDE SLOPE CANAL: A canal in which is aligned at right angles to the contours of
the country. Thus it is neither on the watershed nor in valley but it is somewhere in
between the two slope along the valley. As this canal is nearly parallel to the natural
drainage of the country it does not intercept drainage and hence cross-drainage works
are not required.
The main canal takes of some from the river some points from where it must be taken to
mount the watershed or ridge in the area. The portion of the canal between the points
where it takes off from the river to the point where it mounts the watershed usually in
heavy cutting and also in this portion the number of cross drainage works will be
required to be constructed which will make this portion of the canal is very expensive.
This necessitates some cross drainage works. Also in this reach the canal will be able to
irrigate areas only on the side of the canal. The watershed may also have to be
abandoned in order to bypass towns or villages located on the watershed.
In hilly areas it may not be possible to align the canal along the watershed or ridge. This
is so because in the hills the river flows in the valley below, while the watershed or the
ridge may be hundreds of liters above it. it would not be economically feasible to take
the canal on top of such a ridge. The canal will thus be aligned as a contour canal.
As far as possible to avoided the curves in the alignment of canals because of the curves
to lead to disturbance of flow and a tendency to silt on the inside and scour on the
outside of the curves.
The alignment of the canal should be such that idle length of the canal is Minimum.
The canal alignment should be as far as possible a balanced depth of cutting and filling
is achieved.
The alignment should be made in a rocky, brackish or cracked stratum.
The alignment should be such that the canal crosses the natural stream where the stream
is straight with minimum waterway.
IRRIGATION INTENSITIES
CROP INTENSITIES AREA in hectares
Paddy 50% 937.5
Jowar 10% 187.5
Wheat 25% 468.75
Vegetable 15% 281.25
CALUCULATION OF DUTY:
For design of irrigation canal in non alluvial soil formation the Economical depth will be
utilized in which the area of cross section in filling will be equal to area of cross section
in cutting.
A trapezoidal section is taken to design the canal and the side slopes of the canals are
assumed as, 2H: 1V in cutting and in filling 1.5H: 1V.
The Longitudinal or bed slope of the canal will be obtained after draw the longitudinal
section along the centre line.
PORTION 1: After study the longitudinal or profile of the canal is necessary to design
as fully filling from sluice tank to 165m distance.
Let, the longitudinal slope be 1inS i.e. 1in1000 from the Longitudinal profile of ground.
For trapezoidal cross section:
rea = B my ×y
Where, m=2 for filling
As per IS, the rigid concrete lined channels the Manning’s coefficient n = 0.014 and
Assume allowable velocity varies 1.0m/sec to 2.0m/sec for rigid concrete lined channels.
Therefore V= 1.0m/sec.
y
R=
= 0.6435 ≈0.65m
B = 0.80m
= 0.6435 ≈0.65m
Dept. of civil engineering.
NHCE, Bangalore 28 | P a g e
`
EXTENSIVE SURVEY PROJECT B- 5
2015-16
PORTION 2: After 165m distance from the sluice tank canal drop necessary, due to
chainage of elevation. After 165m Distance the level of the ground is Economical depth
will be utilized in which the area of cross section in filling will be equal to area of cross
section in cutting.
For most economical trapezoidal channel section
Where, m=1.5
y
= 0.7413≈0.75m
However the sluice opening is designed to draw the normal water requirement with a
driving head of 0.50m
Area of vent way...
=Cd
0.4352=
= m
The opening is designed as circular type.
d
=
d
0.2031=
d=0.50m
Provide Barrel of minimum size of 0.60m×0.75m. with 0.5m dia. Of circular opening at
the entrance of the barrel well or tower head.
RCC slab is designed for carry soil and self weight of slab. Side walls are acting on
abutments and resist the lateral earth pressure and weight of earth.
The minimum size is required for inspection and repairs so opening is controlled by gate
or mechanical regulator.
DESIGN OF TOWER HEAD: The regulating arrangement for gate is provided in well
or tower head is kept 0.3m above MWL i.e.810+0.3=810.3m.
The tower head is rest on the cement concrete bed internal diameter is assumed 1.20m
and the thickness of the top width of tower head sidewall is 0.45m and the thickness is
increases 0.6m towards bottom, stone pitching with water cushion and earth slope
around the tower head.
A fall may be provided at a location where the FSL of the channel outstrips the ground
level but before the bed of the channel comes into filling.
A falls should be so located that as far as possible there is no loss of the commanded
area of the channel.
The location of a fall may also be affected by the possibility of combining it with a
regulator or a bridge or some other structures. Such combinations often results in
economy.
Design of notch:
Minimum # of 2 notches should be provided. Notches are provided on the basis of full
discharge.
Providing 2 notches for 1.344 cumec
q100 = Q100/2=1.344/2=0.672m3/sec
q50 = Q50/2=0.672/2=0.336m3/sec
PROTECTION WORKS:
DESIGN OF SOLID APRON:
Depth of water cushion
x y’ = 0.91 y √h
Where, y’ = depth of water on /
x = 0.5m
Thickness of solid apron T = ½ √ y h = ½ ×√ 2+1.82) =0.97m
RL of bottom of apron = 804.5 - 0.50 – 0.97 =803.03m
Where, H = 1.97m
=2.25 B = 2.64m
REVETMENT:
Length of U/S revetment =3 ×y = 6m
Length of D/S revetment = 4×(y + H) = 15.88m
PROTECTION WALLS:
ABUTMENTS:
Length of abutment may be kept same as the width of drop wall at foundation level i.e.
2.64m
Top width of abutment = 0.30m
Top level of abutment = 805.25m
Bottom of the abutment is kept on hard soil = 804.50m
The wall will have batter of 1in8.
WING WALLS:
U/S wing wall is kept at level 805.25m
Top width of wing wall is 0.3m and it is splayed at 1: 1
Bottom of the U/S wing wall is kept at hard soil level 804.50m
D/S wing wall is kept at level 805.25m.
Top width of wing wall is 0.3m and it is splayed at 1: 3.
b n d
1 2 30
CHAINAGE HEIGHT
AREA IN sq.m. VOLUME OF CUTTING IN cub.m.
0 1.5 6
30 1.55 6.355
60 1.6 6.72
90 1.6 6.72
120 1.7 7.48
150 1.75 7.875
180 1.75 7.875
210 1.75 7.875
3593.1
240 1.8 8.28
270 1.85 8.695
300 1.9 9.12
330 1.8 8.28
360 1.85 8.695
390 1.9 9.12
420 1.9 9.12
450 1.9 9.12
WATER
SUPPLY
AND
SANITARY
PROJECT
to compute the existing population. The topographical map was also used to plan the
layout of water supply pipe distribution system for the village.
Ghati village is an old village developed in an unorganized manner so the dead end
system pattern of water supply distribution has been considered for layout planning. The
water supply pipe has been laid in this pattern for the village. The details of pipe
distribution is marked and indicated on the topographical map assuming that the water in
the pipe lines will flow under gravity at the specified head needed for locations having
one to two storied dwelling units as specified in manual of water supply engineering.
The population of S.S. Ghati can be taken as 2050 in the year 2046.
Total 400
24
Therefore maximum daily demand 0.0068 0.0204 m3 / s
8
3.4.3DESIGN OF PUMP
4 0.0067 60 1.162
Hf
2 9.81 0.150
H f 0.735 m
V2
Velocity head, Vh
2g
1.16 2
Vh
2 9.81
Vh 0.068 m
Total Head loss, H 6 (0.735 0.068) 6.803 m
4 fLV 2
Hf
2 gD
4 0.0067 1840 1.162
Hf
2 9.81 0.150
H f 22.54 m
Velocity head,
V2
Vh
2g
1.16 2
Vh
2 9.81
Vh 0.068 m
0.206
0.103 m 2
Area of each screen, 2
Diameter of each circular screen
(0.103 4) / 0.362 m
3.5.2 Design of sump
The sump can act as pre-sedimentation tank to remove 0.1mm and above particle size.
The side slope of sump is 10% towards the center so as to facilitate cleaning manually.
Assume Water depth as 2.5m and 0.5m as free board.
Total Depth of sump = 3m
capacity of sump (m3)
Surface area Depth(m)
595.35
2.5
238.14m 2
L×B = surface area
L: B=3:1
L = 3×B
3B×B = 238.14
B = 8.91 m
⇒L = 26.73 m
Q
Actual over flow rate
L B
895.35
Actual over flow rate 3.76m 3 / m 2 / day
8.91 26.73
3.5.3 Design of sedimentation tank:
Max. Water to be treated in 24 hours = 895.35x103 lit/d
Quantity of water to be treated during the detention period of 4 hours
895.35 103
4 149.225 103 litre 149.225m3
24
Velocity of floe to be maintained through the tank = 0.2 m/minute
Where, Q is in m3/hr
48 2.1 2
8.23hr
Actual detention time 24.48
Q
Actual velocity L H
24.48
0.255m / min
Actual velocity 48 2
3.5.4 Disinfection:
Bleaching powder is used as a disinfectant.
Dosage of chlorine is 0.3 mg/liter
Amount of chlorine required
0.3 595.35 1000
0.178kg / day
106
The Chlorine content in bleaching powder = 30 %
Amount of bleaching powder required
0.178 100
0.593 kg / day
30
Amount consumption of bleaching powder
0.593 365 216.445
Hence annual bleaching powder consumption is 217 kg/year.
The bleaching powder is mixed with water and the solution is fed into disinfection unit
for mixing with raw water to achieve disinfection and to maintain residual chlorine of
0.1mg/liter.
TABLE:
HIGWAY
PROJECT
4.0 TRANSPORTATION:
INTRODUCTION
Transportation contributes to the economic, industrial, social and cultural development
of any country. Transportation is very vital for economic development of any region
since every commodity produced needs transportation at all stages from production to
distribution.
Inadequate transportation at regions retards the process of socio-economic development
of the country. The adequacy of transportation systems of a country indicates the degree
of development of the country. In developing country like INDIA where 75% of the
population resides in villages and hence the development of the urban alone does not
indicate the overall development of the country.
Sight distance:
The sight distance consideration deals with the calculation of the super elevation
required, radius of the curve to be provided etc for the given design speed.
The portion or all the layout of the centerline of the highway on the ground is called the
alignment. The horizontal alignment includes the straight path, the horizontal deviation
and curves changes in gradient and vertical curves are covered under vertical alignment
of roads.
The main aim of alignment is to connect two important stations through an obligatory
station by constructing new road. Sometimes it is necessary to realign the existing road
to standards as specified by IRC, so as to cater to the traffic demands. The basic
requirement of an ideal alignment between two terminal stations is that it should be
short, safe, easy and economical. The alignment should be such that it would offer
minimum population and products.
for deciding the number of traffic lanes and roadway width, pavement design and
economic analysis of highway project.
Reconnaissance survey:
This carried out to examine the general character of the area for deciding the most
feasible routes for detailed study. Reconnaissance starts with the field inspection by
along the proposed routed or area where the road is proposed. All information, which
affects the geometric design, is noted down. Gradients, drainage requirements etc,
This survey helps to identify two or three alternatives connecting the two station points
through an obligatory point with this key plan or index map is prepared indicating all
features collected.
Preliminary survey:
This is carried out to collect all the physical information, which is necessary in
connections with highway alignment. The main objective is to estimate the quality of
earthwork materials and other construction aspects and to work out the cost of
alternative proposals. This is generally carried out to know the alignment detains by
traverse rising plane table and compass.
Final survey:
This is conducted to work out the details of longitudinal and cross sectional profile. This
also helps to fix up the centerline of the selected alignment and to collect the additional
data for the preparation of drawings.
DESIGN TABLES
Table 4.a Terrain Classification
SL No. Terrain Cross Slope
1. Plain 0 - 10%
2. Rolling 10 - 25%
3. Mountainous 25 - 60%
4. Steep > 60%
Roadway width 10 m
NOTE:
For speed 60 kmph longitudinal Coefficient of friction (f) is 0. 15.
Super elevation e = 0.070 (maximum).
Camber 1 in 40 (2.5 %) depends on rainfall.
Safe stopping sight distance for design speed of 60 kmph is 80m.
Minimum overtaking sight distance is 45m is necessary.
For a design speed of 60kmph and 2.5% camber (1in40).
(Or)
V
e f
Where,
V = Vehicle speed in m/s v = vehicle speed in km/h
G = Acceleration due to gravity in m/s2
e = Ratio of super elevation
f = Co-efficient of side friction between vehicle tyres and pavement. (Taken as 0.15)
Radii for horizontal curves corresponding to ruling minimum and absolute minimum
design speeds are shown in the Table:
Where,
M= the minimum set-back distance from the centre line of the road to sight obstruction
in meters at the middle of the road
R= centre line of the road in meters.
D= distance between the centre line of the road and the inside lane in meters.
S= sight distance in meters.
For applying the above relationship, sight distance is measured along the middle of inner
lane. However on single-lane roads, sight distance is measured along centre line of the
carriageway and ‘ ’ is taken as zero.
TABLE 4.h
Radius of Set back distances in metres
circle curves S+20 m S+20 m S+20 m S+20 m S+20 m
(m) (v+20km/h) (v+25km/h) (v+30km/h) (v+40km/h) (v+50km/h)
14 3.4 - - - -
15 3.2 - - - -
20 2.4 3.8 - - -
23 2.1 3.3 - - -
30 1.5 2.6 3.7 - -
33 1.0 2.31 3.4 - -
50 - 1.6 2.2 5.0 -
60 - 1.3 1.9 4.2 -
80 - 1.0 1.4 3.1 5.6
100 - 0.8 1.1 2.5 4.5
120 - 0.7 0.9 2.1 3.7
150 - 0.5 0.8 1.7 2.3
TRANSITION CURVES:
Spiral curve should be used for transitions. These are necessary for smooth entry of
vehicles from a straight section into a circular curve. The transition curves also improve
aesthetic appearance of the road, besides permitting gradual application of the super
elevation and extra widening at curves. Minimum length of transition curves for various
radii is given in the table.
100 45 20 15 15
125 35 15 15 NA
150 30 15 15 15
170 25 15 NA
200 20 15
300 15 NA
400 15
500 NA
The above table indicates the horizontal curves without transition curves.
In such cases, the super-elevation is provided as follows.
First, calculate the length of transition curve though it is not provided.
Let L= length of transition curve
We = Wm + Wps
We = nl2/2R + V/[9.5R0.5]
Referring all the tables and formulas from the preceding sheets & the drawings from the
survey conducted the following values recommended in the table.
L < SSD
(1.5 0.035 S )
L 2S
N
Summit curves
For safe stopping sight distance condition
L > SSD
N S2
L
4.4
Where, S = SSD in m
L < SSD
4.4
L 2 S
N
For safe over taking sight distance condition
NS 2
L
L > OSD 8 H
Where, S = OSD in m
L < OSD
8 H
L 2 S
N
Design traffic
The design traffic is considered in terms of the cumulative number of standard axles in
the lane carrying maximum traffic during the design life of the road. This can be
computed using the following equation:
(3)
where is the cumulative number of standard axles to be catered for the design in
terms of million standards axle (msa), is the initial traffic in the year of completion
of construction in terms of the number of commercial vehicles per day, is the lane
distribution factors, is the vehicle damage factor, is the design life in years,
and is the annual growth rate of commercial vehicles ( =-0.075 if growth rate is 7.5
percent per annum). The traffic in the year of completion is estimated using the
following formula:
(4)
where P is the number of commercial vehicles as per last count, and x is the number of
ears between the last count and the year of completion between the last count and the
year of completion of the project
N=(365 x 450 x ((1+.005)15-1) x 1.5 x 0.5 ) / 0.05 = 2.65 x 106 std axle
= 2.65 MSA
C B R value = 6%
As per IRC 37-2012, page no. 25
For granular base & granular sub base, thickness of pavement Is
Base = 225 mm
B M = 20 mm
CBR VALUE 6%
THICKNESS OF SUB BASE COARSE 175 mm
THICKNESS OF BASE COARSE 225 mm
THICKNESS OF SURFACE COARSE
DBM 50 mm
BM 20 mm
TOTAL THOCKNESSS 470 MM
315 0 C 0 0
330 0 C 0 0
345 0 C 0 0
360 0.85 C 9.945 127.5
375 1.95 C 27.105 292.5
390 2.4 C 35.52 360
405 2.85 C 44.745 427.5
420 3.15 C 51.345 472.5
435 3.15 C 51.345 472.5
450 3.25 C 53.625 487.5
465 2.1 C 29.82 315
480 1.5 C 19.5 225
495 0.9 C 10.62 135
510 0.45 C 4.905 67.5
525 0.2 C 2.08 30
540 0.1 C 1.02 15
555 0.1 C 1.02 15
570 0.05 C 0.505 7.5
585 0 C 0 0
600 0.3 F 3.18
615 0.2 C 2.08 30
630 0.45 C 4.905 67.5
645 0.5 C 5.5 75
660 0.5 C 5.5 75
675 0.5 C 5.5 75
690 0.55 C 6.105 82.5
705 0.7 C 7.98 105
720 0.85 C 9.945 127.5
735 0.95 C 11.305 142.5
750 1.15 C 14.145 172.5
OLD TANK
PROJECT
5.1 INTRODUCTION:
Tank Restoration project as the name itself indicates is to restore the existing tank to its
original capacity or to augment further increase in the storage capacity of the tank. It
may also be to improve the conditions of the bund to standard dimensions from existing
dimension.
When a tank is large in comparison with the annual runoff from the catchments area all
the silt carried by the runoff water will be deposited on the bed of the tank. The fine silt
which takes long time to settle will be spread more uniformly over the tank bed and
frequently the thickest deposit of such silt will be below the deepest standing water that
is in the vicinity of the bund. The water drawn off through outfall sluices may remove a
small amount of silt deposited in the tank but such action is very local. Restoration can
be adopted. The capacity can also be improved by raising the height of the bund and the
sill of the waste weir.
Prismoidal Formula
h
A1 4 A2 A3
V=∑ 3
h
( A1 An) 4( A2 A4 .....) 2( A3 A5 .....)
V= 3
Volume = L/3 B √ ×B
The storage volumes up to various elevations are determined by using any of the
above noted formulae and the same are plotted against elevation to obtain elevation-
capacity curve. From contoured plan of the reservoir site the water spread area of the
reservoir at various elevations is indicated below.
The storage capacity of the reservoir determined using the above formulae by taking
contour areas at equal intervals is as follows.
The contoured map of the reservoir area also indicates the land and property which
would be submerged in the reservoir when filled up to certain elevation and thus enables
the estimation of compensation to be paid to the owners and the time schedule according
to which they must be moved, as the reservoir is gradually filled during the construction
of the dam.
FIELD
DATA
55 1.66 803
60 1.65 803.01
2.5 1.58 803.08
5 1.5 803.16
7.5 1.4 803.26
2.5 1.65 803.01
5 1.64 803.02
7.5 1.7 802.96
65 1.78 802.88
70 1.93 802.73
2.5 1.9 802.76
5 1.8 802.86
7.5 1.68 802.98
2.5 2.11 802.55
5 2.42 802.24
7.5 2.3 802.36
75 2.1 802.56
80 2.24 2.06 804.84 802.6
2.5 2.13 802.71
5 2.13 802.71
7.5 2.06 802.78
2.5 2.38 802.46
5 2.3 802.54
7.5 2.2 802.64
85 1.51 803.33
90 2.66 802.18
2.5 2.74 802.1
5 2.66 802.18
7.5 2.41 802.43
2.5 1.51 2.59 803.76 802.25
5 1.33 802.43
7.5 1.55 802.21
95 2.52 801.24
100 2.69 801.07
2.5 2.85 800.91
5 2.7 801.06
7.5 2.65 801.11
2.5 2.66 801.1
5 2.3 801.46
7.5 2.15 801.61
105 2.08 801.68
110 1.68 802.08
2.5 1.7 802.06
5 2.1 801.66
7.5 2.76 801
2.5 1.6 802.16
5 1.98 801.78
7.5 2.25 801.51
115 1.73 802.03
120 2.94 800.82
2.5 2.85 800.91
5 2.91 800.85
7.5 2.9 800.86
2.5 2.85 800.91
5 2.5 801.26
7.5 2.45 801.31
125 2.35 3.81 802.3 799.95
130 2.12 800.18
2.5 2.25 800.05
5 1.8 800.5
7.5 1.25 801.05
2.5 2.9 799.4
5 2.8 799.5
7.5 2.75 799.55
135 2.52 799.78
140 2.01 800.29
2.5 1.66 800.64
5 1.07 801.23
7.5 0.99 801.31
2.5 2.52 799.78
5 2.3 800
7.5 2.25 800.05
145 1.77 800.53
150 2.14 800.16
2.5 2.11 800.19
5 2.92 799.38
7.5 3.48 798.82
2.5 3.18 799.12
5 3.14 799.16
7.5 3.02 799.28
155 3.69 800.06 798.61
160 3.33 797.74 796.73
2.5 1.28 796.46
5 1.5 796.24
7.5 1.87 795.87
2.5 1.05 796.69
5 1.45 796.29
7.5 1.3 796.44
165 3.27 794.67 796.95
170 2.45 792.67 792.22
2.5 1.3 791.37
5 1.2 791.47
5 0.95 798.59
7.5 0.97 798.57
3.92 0.235 803.21 799.3
285 2.98 800.24
290 1.08 802.14
2.5 0.97 802.25
5 0.95 802.26
7.5 0.77 802.45
2.5 1.23 801.98
5 0.96 802.25
7.5 0.84 802.38
3.55 0.85 805.91 802.36
295 3.25 802.66
300 1.67 804.25
2.5 1.47 804.45
5 1.29 804.62
7.5 1.31 804.6
2.5 1.24 804.67
5 1.29 804.62
7.5 1.24 804.68
3.93 0.535 809.3 805.38
305 3.5 805.8
310 1.45 807.86
2.5 1.72 807.59
5 2.05 807.25
7.5 2.15 807.15
2.5 0.97 808.33
5 0.98 808.32
7.5 0.75 808.56
315 0.55 808.76
3.13 0.14 812.29 809.16
320 1.49 810.8
2.5 1.82 810.47
5 2.24 810.05
7.5 2.46 809.83
2.5 1.19 811.1
5 0.57 811.72
7.5 0.18 812.11
325 0.16 812.13
CANAL ALIGNMENT
STATION DISTANCE BS IS FS HI RL REMARK
L C R
BM 0 2.98 807.98 805
2.5 3.1 804.88
5 3.115 804.87
7.5 3.06 804.92
2.5 3.12 804.86
5 3.1 804.88
7.5 3.175 804.81
30 3.01 804.97
2.5 3.18 804.8
5 3.26 804.72
7.5 3.43 804.55
2.5 2.82 805.16
5 2.58 805.4
7.5 2.1 805.88
60 3.04 804.94
2.5 3.455 804.53
5 3.82 804.16
7.5 4 803.98
2.5 2.545 805.44
5 2.475 805.51
7.5 2.42 805.56
90 3.07 804.91
2.5 3.08 804.9
5 2.98 805
7.5 2.855 805.13
2.5 2.94 805.04
5 2.835 805.15
7.5 3.07 804.91
120 1.5 3.1 806.38 804.88
2.5 1.18 805.2
5 1.23 805.15
7.5 1.29 805.09
2.5 1.27 805.11
5 1.385 805
7.5 1.305 805.08
150 1.53 804.85
2.5 3.205 803.18
5 3.215 803.17
WATER SUPPLY
STATION BS IS FS HI RL DISTANCE REMARK
S1 4.55 825.16 820.61 0 BM
2.27 822.89 10
1.18 823.98 40
0.7 824.46 70
1.38 823.78 100
2.4 822.76 130
S2 0.005 3.57 821.6 821.6 160
1.26 820.34 190
1.94 820.46 220
2.27 819.33 240
S3 3.86 3.815 821.65 817.78 270
3.385 818.25 300
1.59 820.06 330
S4 3.7 0.68 824.67 820.97 340
S5 3.9 0.56 828.01 824.11 360
0.64 827.37 390
0.35 827.66 400
S6 3.4 0.25 831.16 8247.8 404.5
2.875 828.28 414.5
2.395 828.76 424.5
1.86 829.3 434.5
1.385 829.77 444.5
0.875 830.28 454.5
S7 3.885 0.29 834.75 830.87 464.5
2.575 832.18 484.5
1.7 833.05 504.5
1.18 833.57 514.5
0.61 834.14 524.5
0.01 834.74 530.5
S8 3.36 0 838.11 834.75 537
2.675 835.44 547
1.85 836.26 557
1.54 836.57 567
1.05 837.06 577
0.49 837.62 587
S9 3.455 0.12 841.45 837.99 594
2.91 838.55 604
1.92 839.54 614
HIGHWAY PROJECT
STATION DISTANCE BS IS FS HI RL REMARK
L C R
BM 0 1.235 812.66 811.425
15 1.305 811.355
30 1.465 811.195
2.5 1.46 811.2
5 1.49 811.17
7.5 1.41 811.25
2.5 1.788 810.872
5 1.85 810.81
7.5 1.705 810.955
45 1.625 811.035
60 1.68 810.98
2.5 1.64 811.02
5 1.04 811.62
2.5 1.65 811.01
5 1.49 811.17
75 2.49 1.68 813.47 810.98 CP1
90 2.39 811.08
2.5 2.32 811.15
5 2.3 811.17
2.5 2.38 811.09
5 2.95 810.52
105 1.84 811.63
120 1.34 812.13
2.5 1.265 812.205
5 1.23 812.24
2.5 1.41 812.06
5 1.39 8123.08
135 1.39 8132.08
130 1.32 812.15
2.5 1.335 812.115
5 1.085 812.385
2.5 1.32 812.15
5 1.3 812.17
165 0.995 813.05
180 3.45 0.42 816.65 813.2 CP2
2.5 3.45 813.46
5 3.19 812.98
2.5 3.67 814.395
5 3.6 813.05
195 2.225 815.94
210 3.625 0.71 819.57 815.94 CP3
2.5 0.62 818.943
5 0.43 819.135
2.5 0.85 818.745
5 1.25 818.315
225 2.21 817.355
240 1.08 818485
2.5 1.05 818.515
5 1.335 818.23
2.5 1.235 818.33
5 1.815 817.75
255 1.06 0.11 820.52 819.455 CP4
270 0.96 820.515
2.5 0.9 819.615
5 0.805 819.71
2.5 1.01 819.505
5 1.375 819.14
285 1.165 819.35
300 1.9 818.615
2.5 1.99 818.525
5 2.23 818.35
2.5 2.04 818.475
5 2.1 818.415
315 2.45 818.155
330 2.36 818.09
2.5 2.1 818.495
5 1.98 818.538
2.5 2.425 818.415
5 2.31 818.205
345 2.02 818.495
360 3.45 0.97 823 819.545 CP5
2.5 3.58 819.415
5 3.3 819.695
2.5 3.445 819.55
5 3.23 819.765
375 2.34 820.655
390 1.62 821.375
2.5 1.61 821.385
5 1.53 821.465
2.5 1.8 821.195
5 1.68 821.315
405 2.56 0.84 824.72 822.155 CP6
420 1.88 822.835
2.5 1.94 822.775
5 1.83 822.885
2.5 2.03 822.685
5 2.01 822.705
435 1.42 823.295
450 1.295 823.42
2.5 1.53 823.185
5 1.45 823.265
2.5 1.53 823.185
5 1.4 823.315
465 1.63 823.085
480 2.07 822.645
2.5 2.18 822.535
5 2.05 822.665
2.5 2.27 822.445
5 2.13 822.585
495 2.38 822.335
510 2.65 822.065
2.5 2.63 822.085
5 2.53 822.185
2.5 2.71 822.005
5 2.6 822.115
525 2.575 822.14
540 2.49 822.225
2.5 2.28 822.435
5 2.18 822.535
2.5 2.49 822.225
5 2.35 822.365
555 2.82 2.13 825.41 822.875 CP7
570 2.53 822.875
2.5 2.59 822.815
5 2.45 822.955
2.5 2.72 822.685
5 2.5 822.905
585 2.37 823.035
600 2.18 823.225
2.5 2.16 823.245
5 2.06 823.345
2.5 2.33 823.075
5 2.03 823.375
615 1.84 823.565
630 1.215 824.19
2.5 1.32 824.085
5 1.03 824.375
2.5 1.15 824.255
5 1.43 823.975
645 3.6 0.54 828.47 824.865 CP8
660 3 825.465
2.5 3.2 825.265
5 3.03 825.435
2.5 3.15 825.315
5 3.05 825.415
675 2.67 825.795
660 2.33 826.135
2.5 2.32 826.145
5 2.02 826.445
2.5 2.45 826.015
5 2.35 826.115
705 1.95 826.515
720 1.35 827.115
2.5 1.25 827.215
5 1.23 827.235
2.5 1.432 827.033
5 1.41 827.055
735 1.432 827.033
750 1.66 0.25 829.88 828.215 CP9
2.5 1.57 828.305
5 1.71 828.165
2.5 1.55 828.325
5 829.875
765 0.28 829.595
5 1.77 880.67
7.5 1.87 880.57
30 1.37 881.07
2.5 1.335 881.11
5 1.435 881.01
7.5 1.535 880.91
2.5 1.5 880.94
5 1.6 880.84
7.5 1.7 880.74
35 1.42 881.02
2.5 1.45 880.99
5 1.55 880.89
7.5 1.65 880.79
2.5 1.56 880.88
5 1.66 880.78
7.5 1.76 880.68
40 1.54 880.9
2.5 1.365 881.08
5 1.465 880.98
7.5 1.565 880.88
2.5 1.85 880.59
5 1.95 880.49
7.5 2.05 880.39
45 1.6 880.84
2.5 1.35 881.09
5 1.45 880.99
7.5 1.55 880.89
2.5 2.1 880.34
5 2.2 880.24
7.5 2.3 880.14
50 1.65 880.79
2.5 1.35 881.04
5 1.45 880.94
7.5 1.55 990.84
2.5 1.29 1.885 881.85 880.55 CP1
5 1.39 880.45
7.5 1.49 880.35
55 1.37 880.48
2.5 1.5 879.95
5 1.6 879.85
7.5 1.7 879.75
2.5 1.7 879.75
5 1.8 879.65
7.5 1.9 879.55
60 1.32 880.13
2.5 1.705 879.75
5 1.805 879.65
7.5 1.905 879.58
2.5 1.42 880.03
5 1.52 879.93
7.5 1.62 879.83
65 1.384 880.06
2.5 1.26 880.19
5 1.36 880.09
7.5 1.46 879.99
2.5 1.78 879.67
5 1.88 879.57
7.5 1.98 879.47
70 1.34 880
2.5 1.31 880.14
5 1.41 880.04
7.5 1.51 879.94
2.5 1.625 879.83
5 1.725 879.73
7.5 1.825 879.63
75 1.39 880.06
2.5 1.33 880.12
5 1.43 880.02
7.5 1.53 879.92
2.5 1.35 880.1
5 1.45 880
7.5 1.55 879.9
80 1.4 880.04
2.5 1.41 880.04
5 1.51 879.94
7.5 1.61 879.84
2.5 1.58 879.87
5 1.68 879.77
7.5 1.78 879.67
85 1.4 880.05
2.5 1.41 880.05
5 1.51 879.95
7.5 1.61 879.85
2.5 1.49 879.96
5 1.59 879.86
7.5 1.69 879.76
90 1.38 880.07
2.5 1.33 880.12
5 1.43 880.02
7.5 1.53 879.92
2.5 1.48 879.97
5 1.58 879.87
VILLAGE TRAVERSING
STATION BS IS FS HI RL DISTANCE REMARK
S1 0.95 865.69 864.735 0 BM
1.19 864.495 15
0.79 864.895 30
S2 3.46 0.29 868.86 865.395 45
2.87 865.985 60
2.25 863.735 75
1.01 867.845 90
S3 3.91 0.18 872.59 868.675 100
2.885 869.7 110
1.545 871.04 120
S4 2.045 0 874.63 872.585 135 STREET-1
1.62 873.01 145
1.285 873.345 155
S5 3.155 0.76 877.03 873.87 160
1.635 875.39 175
S6 3.01 0.695 879.34 876.33 185
1.92 877.42 200
S7 1.6 1.32 879.62 878.02 210.85 STREET-2
1.39 878.23 240.85
1.85 877.77 270.85
S8 0.3 1.91 878.01 877.71 290.85 STREET-3
0.54 877.47 300.85
1.225 876.785 310.85
1.92 876.09 320.85
2.61 875.82 330.85
S9 0.1 3.19 874.92 874.82 340.85
0.78 874.14 350.85
1.335 873.585 360.85
1.8 873.12 370.85
2.325 872.595 380.85
2.67 872.25 390.85
S10 0.02 3.04 871.9 871.88 400.85
1.375 430.85
S11 0.12 2.92 869.1 868.98 460.85
2.14 866.96 490.85
S12 1.165 3.78 866.49 865.32 520.85
1.81 864.676 535.85
1.735 864.751 550
STREET-1
S1 2.02 874.61 872.585 0
1.75 872.855 10
1.7 872.905 20
1.525 873.08 50
1.48 873.125 60
1.415 873.19 70
1.325 873.28 80
S2 3.895 0.47 878.03 874.135 100
2.88 878.15 110
S3 3.89 0.93 880.99 877.1 130
2.21 878.78 150
S4 3.975 0.64 8884.3 880.35 165
2.69 8881.635 180
1.349 8882.976 195
S5 1.675 0.22 885.78 884.105 215
S6 1.742 0.33 887.19 885.449 245
1.352 885.839 252.6
STREET-2
S1 3.63 881.65 878.02 0
2.62 879.03 30
1.63 880.02 60
S2 3.84 0.65 884.84 881 90
1.09 883.75 120
S3 3.57 0.21 888.2 884.63 135
1.01 887.19 165
S4 3.78 0.175 891.81 888.025 173
2.5 889.305 193
2.17 889.635 198
1.57 890.235 208
S5 3.97 0.32 895.46 891.485 223
2.59 892.865 238
1.075 894.38 268
S6 3.465 0.865 898.06 894.59 273
1.765 896.29 303
S7 2.15 0.55 899.66 897.505 333
1.58 898.075 346
STREET-3
S1 3 880.71 877.71 0
S2 3.5 0.915 883.3 879.795 30
1.135 882.16 60
S3 3.91 0.27 886.94 883.025 90
S4 3.475 1.29 889.12 885.645 120
1.215 887.905 150
0.485 888.635 180
BIBLIOGRAPHY