Master Changan Motors LTD.

Shutdown Activity Plan - QAHSE (Weld Shop)


FROM 4/12/2021 TO 12/12/2021
DAY DAY DAY DAY DAY DAY DAY DAY DAY
WORK TO DO

F202
S# Activity P.I.C (Leader) No. Of TMs Man-Hrs Target
1 2 3 4 5 6 7 8 9

RH OUTER Saad & 2 2 18 90 90 90 90 90 90 90 F202 QC Training


1 INSPECTION Samar 2 2 18 90 Test

LH OUTER Saad & 2 2 18 54 90 54 54 54 54 54 F202 QC Training


2 INSPECTION Samar 2 2 18 90 Test

RH INNER Saad & 2 2 18 90 90 90 F202 QC Training


3 INSPECTION Samar 2 2 18 90 Test

LH INNER Saad & 2 2 18 54 90 54 54 54 54 F202 QC Training


4 INSPECTION Samar 2 2 18 90 Test

REPAIR Saad & 2 2 18 90 90 90 90 90 90 90 F202 QC Training


5 CONFIRMATION Samar 2 2 18 90 Test

Saad & 2 2 18 90 90 90 90 90 90 90 90 90 F202 QC Training


6 AUDIT
Samar 2 2 18 90 90 90 90 90 90 90 90 Test
LINE WISE MAN POWER 24 10 Total Manhours 207 207 207 207 207 279 279 279 279

Total Team Members 23 23 23 23 23 31 31 31 31

* Maintenance & PE supporting works already share with


department.