SCHEEM NO -04

CONSTRUCTION OF C.C PAVING FLOORING AT STREET NO-01 NEAR MASJID


USMANIA WARD-3 UC-01 DAWOOD CHOWRANGI DMC MALIR.

S.No Items No Length Breadth Depth Quantity Amount

Preparing Sub-grade i/c earth


excavation of refilling to an
average depth of 9" dressing
1
to camber & consolidation
with power roller etc complete
(H.W Sch page -2/9)
3 100 8 = 2400
1 60 8 = 480
2880
2880 526.28 % sft 15,157

Cement Concrete bricks on


stone ballast 1-1/2” x 2”
gague
2
ratio 1:4:8 (G.S.I.No. 4 P-
15).

F.S.Wall 3 100 8.00 0.33 = 792


F.Path U Base 1 60 8 0.33 = 158.4
950.4
950.40 9416.28 P. %Cft 89492

Erection and removal of


centring for reinforced or
plain cement concrete
3
works of partal wood (2nd
class). Vertical .(S.I No.19
(b) /ii/P-18)
2 100 1 200.00
200.00 3127.41 P. %Cft 6255

cement concrete plain i/c


placing compacting
finishing and curing
and curing complete i/c
4 screening and washing of
stone aggregate
Without shuttering ration
1:2:4.

Cement Concrete Plain


F.S.Wall 2 100 0.75 0.75 112.50
112.50 14429.25 P.%Cft 16233
Providing and fixing
Precast Edge Block 3750
PSI industrial made 6" dia
thick x 12 long x 18" high
i/c the cost of cartage ,
5 excavation , from work for
haunching , 1450 PSI lean
concrete, 2250 PSI
Concrete for haunchin 1:4
cement sand mortor .(HW
.S .I No. 39/14 P-16)
2.5 100 = 250
250.00 297.01 P.Rft 74253

Providing /Fixing cement


paving blocks flooring havi
ng size 197 x 97 x 60 mm
of city /quddra/ coubble
shape with pigment, having
strength between 5000 to
6 8500 PSI including filling
the joints with hil sand and
laying in specified manner/
pattern & design etc
complete. (G.S.I No.72 P-
49).
3 100 8.00 2400
1 60 8.00 480
2880
2880.00 223.97 P.Sft 645034

Manufcturing and supplying


R.C.C Ring slab of 21" dia
inside 36" dia out side 7.5"
width and 6" thick i/c 3/8"
dia tor steel bars two
concentric rings with 3/8"
dia 8 Nos cross link bars
7
welded and two sunk type
hooks cast in a 1:1-1/2:3
concerete with embedded
15 Kg C.I frame. It will be
transported in perfect
position i/c transportation
charges for an average
lead of 20 Km
13 1 = 13.00
13.00 1906.60 Each 24786
Manufcturing and supplying
R.C.C Manhole covers cast
in 1:2:4 concrete ratio 3"
inch deep at center,
reinforced with 1/2" dia tor
steel bars @ 4" c/c etc,
8
welded to 3/16" thick 2"
wide M.S. plate, two hooks
of 3/8" dia tor bar i/c
compacting, curing and
transportation within ten
miles 21" dia.
13 1 = 13.00
13.00 913.63 Each 11877

TOTAL AMOUNT 883,086

Add 10 % Above on item no 11,198


2,3,4 (111980)
Add diff of cement 111 Bags @ 19,980
Rate 180/- per bag
Add Cartage Amount 35,649

TOTAL AMOUNT 949,913

Add SRB 5% 47,496

TOTAL AMOUNT 997,408

SAY AMOUNT 998,000

SUB ENGINEER
D.M.C MALIR (B&R)

`
ASSISTANT EXECUTIVE ENGINEER EXECUTIVE ENGINEER
D.M.C MALIR (B&R) D.M.C MALIR (B&R)
SCHEEM NO -04
CONSTRUCTION OF C.C PAVING FLOORING AT STREET NO-01 NEAR MASJID USMANIA
WARD-3 UC-01 DAWOOD CHOWRANGI DMC MALIR.

MATERIAL STATEMENT

S.No Items Qty Cement Hill Sand Crush Stone Bricks Steel

1 C.C. (1:6:12)

1 C.C. (1:4:8) 950.40 91.2384 456.192 912.384

2 R.C.C (1:2:4)

3 C.C. Plain (1:2:4) 112.50 19.8 49.5 99

4 C.C. Plain (1:3:6)

5 C. Plaster 1/2"

6 C. Plaster 3/8"

7 C. Plaster 3/4"

8 Pacca Brick (1:6)

9 Pacca Brick in mud

10 Pacca Brick in

11 Fabrication
12 Paving 2880.00 11520

QTY 111.0384 456.192 99 912.384 11520

RATE 18.33 1162.68 1325.48 1390.6 1242.14

AMOUNT 2035.33387 5304.0531 1312.2252 12687.6119 14309.4528

TOTAL CARTAGE 35,649

SUB Engineer
D.M.C MALIR (B&R)
SCHEEM NO -04

CONSTRUCTION OF C.C PAVING FLOORING AT STREET NO-01 NEAR MASJID


USMANIA WARD-3 UC-01 DAWOOD CHOWRANGI DMC MALIR.

RATE ANALYSIS STATEMENT

From Cement Factory to Site of


Cement:
Work (20Miles)
1st Mile to 2 Mlie 7.53
Remmaining Miles 18 0.60 10.80
18.33

From Hill Sand Ghaghar to Site


Hill Sand:
of Work ( 18 Milles)
1st Mile to 6 Mlies 771.96
Remmaining Miles 12 32.56 390.72
1162.68

From crush plant to Site of


Crush/Bajri:
Work (23 Milles)
1st Mile to 6 Mlies 771.96
Remmaining Miles 17 32.56 553.52
1325.48

From orangi hills to site of


Stone:
work (25miles)
1st Mile to 6 Mlies 771.96
Remmaining Miles 19 32.56 618.64
1390.60

From site area to sit of


Steel
work(18 Mils)
1st Mile to 6 Mlies 771.96
Remmaining Miles 12 32.56 390.72
1162.68

From umerkot To Site of work(


Bricks
29 Miles)
1st Mile to 6 Mlies 617.54
Remmaining Miles 23 26.05 599.15
1216.69
From factory to Site of Work
Paving Block
30(Miles)
1st Mile to 6 Mlies 616.94
Remmaining Miles 24 26.05 625.20
1242.14

Sub engineer
D.M.C MALIR (B&R)