Professional Documents
Culture Documents
A101747A Item 06 Fire Pump
A101747A Item 06 Fire Pump
A101747A Item 06 Fire Pump
2017
DATA SHEETS Prep. By: SR
A101747A
Document No: FFS-252
Written by: OIB
Rev.01 / 03.01.2006
SFP HD
FIRE PUMP
SFP 250x350HD
Description
The SFP HD fire pump is a single stage centrifugal pump with horizontal
inlet and vertical outlet. The pump offers a unique combination of high
performance in relation to weight and dimensions.
The SFP HD fire pump is an extremely robust and short built unit, making
it ideal for confined spaces like engine rooms. The pump is tailor-made for
fire fighting duty with reliable operation and minimum maintenance
requirements as main features. The pump is manufactured and performance
tested in Scandinavia in accordance with the highest quality standards.
The sturdy pump feet are an integrated part of the pump casing – thus
making the pump less susceptible of deformation caused by excessive pipe
forces. The standard material for pump shaft and impeller is duplex
stainless steel with superb strength and corrosion resistance. Ball bearing
is permanently grease filled, and re-lubrication is not needed.
Page 1 of 2
Document No: FFS-252
Written by: OIB
Rev.01 / 03.01.2006
SFP HD
FIRE PUMP
SFP 250x350HD
Dimensions
Page 2 of 2
Document No.
Pump performance curve FFS535
Project No. Reference curve
SFP 250x350HD A101747A 25006
Remarks Discharge Date
Fi-Fi pump for Hat-San Shipyard, hull:NB011 250 mm 24.04.2017
Density Viscosity Testnorm Rated speed NPSH
1,025 kg/dm3 1 mm2/s ISO 9906:2012 Grade 2b 1800 rpm 7,8 m
Flow Head Rated power Hydraulic efficiency Impeller diameter
1460 m3/h 110 m 600 kW 74,9 % 523 mm
H (m)
180
160
120
NPSH
100 (m)
10
80 9
8
7
60
6
5
40
4
3
20 2
1
100% 0
80%
Efficiency
60%
40%
20%
700
600
500
Power (kW)
400
300
200
100
0
0 200 400 600 800 1000 1200 1400 1600 1800
Capacity (m3/h)
FFS Pump Selector 1.1.0 2015-08-26
Pump capacity calculation
Project: A101747
Customer Hat-San
Calc.: BSI
Date:
Pump schedule :
Pump 1 1460
Pump 2
Pump 3
Pump 4
Pump 5
Pump 6
Written by: OIB/RS Rev.00
Project: A101747A
Customer: Hat-San Shipyard
Calc. by: BSI
Date: 20.04.2017
Condition satisfied
Page 1 of 1
Doc.no.: FFS-412
Rev.02
Page 1 of 12
Contents
1 GENERAL DESCRIPTION 2
2 BEFORE INSTALLATION 2
2.1 Warranty statement 2
2.2 Safety precautions 2
2.3 Inspection 2
2.4 Storage 3
2.5 Reference drawings and documentation 3
2.6 Needed tools and chemicals 3
3 INSTALLATION 4
3.1 Foundation and fastening 4
3.2 Coupling and alignment 4
3.3 Piping 5
3.3.1 Suction side piping 5
3.3.2 Discharge side piping 7
4 START-UP AND COMMISSIONING 8
4.1 Starting the driver of the pump unit 8
5 OPERATION 8
5.1 Running the pump 8
6 MAINTENANCE 11
6.1 Bearings 11
6.2 Shaft seal 11
6.3 Cleaning 11
6.4 General maintenance 11
6.5 Troubleshooting table 12
1 GENERAL DESCRIPTION
This document is made to describe the installation, operation and maintenance of the SFP fire
pump range designed by FFS AS and made in Sweden. The SFP range consists of the
following sizes: SFP 150x200, SFP 250x350, SFP 300x400 and SFP 400x500.
The SFP 150x200, SFP 250x350 and SFP 300x400 pumps are single stage, single suction
centrifugal pumps. The SFP 400x500 is a single stage and double suction pump. In
combination with the SFP range double volute feature, this design gives minimal bearing
forces and long bearing life.
The SFP pumps offer a unique combination of high performance in relation to weight and
dimensions. The unit is robust and requires minimal maintenance.
Standard material for Pump Casing and Pump Cover is nodular cast iron – optional: nickel-
aluminium-bronze. The material for pump shaft and impeller is duplex stainless steel. Ball
bearing is permanently grease filled and sealed, and re-lubrication is not needed. The sleeve
bearing is also maintenance free.
2 BEFORE INSTALLATION
• Ref. the relevant project specific Scope of Supply, given to customer with the general
FiFi system offer.
• The instructions given in this document must be followed for the warranty to be valid.
• Only use suitable, approved and certified lifting gear for performing lifting operations.
• Stay clear of rotating parts during operation.
• Cleanliness during assembly and installation is of vital importance.
2.3 Inspection
• Inspect the pump unit carefully for any signs of transport damage or other deviations
which may have occurred during transport and handling. Make sure that all equipment
and parts are available.
• Check ID plate for correct part and serial no.
2.4 Storage
• The pump unit should be stored in a dry in-house environment above 15 degrees C.
• Do not stack anything on top of the pump unit.
• Covers fitted to pump suction and discharge side must be retained in place.
• Storage site with vibration levels that could damage bearings must be avoided.
• Bare metal external surfaces (for example drive flanges) are treated with an adhering
rust preventive agent. This must be removed with proper solvent for degreasing metal
surfaces just before further assembly.
• Every 2 months, rotate the pump shaft at least 1 ½ turns in order to move the bearings.
• For longer duration storage (> 12 months), please contact FFS for more detailed storing
instructions.
• FFS Engine Room Arrangement drawing – project specific with project number and the
suffix E1, E2, E3 etc. – depending of number of units per project, PS/SB/midship
locations etc.
• Coupling drawing and documentation for alignment tolerances
• Pump data sheet for SFP 150x200, SFP 250x350, SFP 300x400 or SFP 400x500
• FFS-215 Alignment document
• Common metric spanners, socket wrench, torque wrench type 20-210Nm and Allen
keys
• Where applicable: Suitable torque wrench and thread locking agent as per coupling
manufacturer’s specifications
• Equipment for alignment
3 INSTALLATION
• Pumps should preferably be installed to make inspection and servicing easy. Ensure that
adequate space exists around the pump unit.
• Ensure that the direction of rotation is correct according to the project specific
documentation.
• The construction of the foundation shall be so that vibrations are prevented, pipe stress
absorbed and distributed. The foundation must be designed to have a structural stiffness
to limit displacement of the pump unit’s input shaft/flange in relation to the driver shaft.
• When designing the pump foundation (yard responsibility), the nozzle loadings given in
for example API standard 610, could be used as input for stiffness calculations.
• The pump feet are fully machined flat and parallel. Corresponding surfaces must be in
the same plane. The foundation of the unit must be a plane, machined surface. The feet
must be in the same horizontal plane to avoid warping of the unit when tightening the
connection bolts. The full surface of the pump feet must rest on the foundation plane.
• Use proper ISO standard 8.8 grade or higher bolts/nuts for the connection to foundation.
All these to be tightened to the specified torques and secured by proper thread locking
agent.
• There are threaded jacking bolt holes located in each of the pump feet for alignment
purposes.
• Grouting agents such as Chockfast™ is generally recommended to be used to secure the
installation.
• If using shim plates, only approved and generally accepted types like Vibracon™ or
equivalent are prescribed. No general small shim plate stacks with total height over
15mm are to be used. Ensure a stable arrangement. If shims are used for height
adjustment, the shims shall cover all the foot area.
• For sidewise adjustment, brackets with adjustment bolts make this operation easier.
Refer to FFS project specific Engine Room Arrangement drawing(s), document No.
FFS-215 Alignment and Coupling manufacturer’s documentation.
• Several factors related to the piping system can seriously affect the function of pump.
The piping must first of all be properly engineered regarding water velocities.
• Loads on the pump flanges arising from pipe stresses must be kept at a minimum level.
Excessive pipe stresses can deform the pump casing resulting in locked rotor. Piping
and valves shall be carefully supported. Remember that the pump is NOT a foundation
for the piping. All pipe loads must be carried by proper piping support, and piping must
be fitted so that not any pipe stress can disturb alignment.
• Ensure that pipes and pump are properly cleaned before connection. Debris in the pipes
can lead to seizures and unnecessary wear. Bear in mind that some of the rotating
clearances inside the pump are only a few tenths of a mm.
• Pressure Testing of Piping - When the piping system is pressure tested, the pump is
normally isolated to avoid damage to sealing system or other components. This is
important to remember if the test pressure is above the normal working pressure of the
pump. If in doubt – consult FFS. Before any pressure testing, pump and piping must be
properly vented.
Pipe support
Pipe support
• A suction line valve must be used for isolation only – never to throttle the flow. During
operation this valve must be fully open. Globe and angle valves should normally not be
used since these types can lead to increased suction losses. For most Fi-Fi applications
a butterfly valve is the first choice, also because of simple design and ease of operation.
• A butterfly valve must never be mounted directly to the pump’s inlet flange. The valve
disc will not be able to open fully, since it will protrude from the valve body and hit the
guide ribs in the pump casing. Always use a spool piece between pump inlet and a
butterfly valve, if a flexible bellow is not installed.
• The sea chest must have some sort of grid to prevent debris from entering the suction
line. The maximum opening in this grid shall be 30x30mm to protect the SFP pump’s
internal flow channels. In some cases a strainer or filter is necessary between sea chest
and pump.
Max.
2 m/s
Grid openings
max.30x30mm
• The sea chest intake must have a sufficiently large area not to restrict the flow. The
absolute minimum flow area through the grid is two times the area of the largest
suction pipe.
• To minimise losses further, always use long radius bends and avoid sudden pipe
diameter changes.
• A provision to clean the sea chest by compressed air if clogged is recommended.
• A flexible bellow on the suction side of the pump is not a requirement, but this
arrangement can sometimes be useful. In this way pipe stresses caused by installation
errors or movements of the vessel is not so easily transferred to the pump. If a flexible
bellow is used, it must be located up-stream of the inlet valve in case of rupture. The
bellow should have an inside diameter corresponding to the diameter of the connected
pipe. To minimise suction losses, the inside diameter of the bellow must have a
smooth cylindrical surface.
Flexible bellow
Butterfly
valve
• A discharge valve is normally located in the outlet line close to the pump. There is also
a small size by-pass line for filling the piping system during start-up. A check valve is
sometimes used to prevent back-flow to the pump. This valve is only recommended if
several pumps are operating in parallel to a common manifold or ring line. In case of
check valve being used, this valve must be located up-stream of the discharge valve.
• Acute branch angles and sudden changes in pipe diameter give unnecessary losses and
may cause noise.
• Water velocities in the discharge side of the pump should normally not exceed 4
meters per second. Check the requirements for each specific application.
• Minimum flow - Remember that all centrifugal pumps need a certain flow for self-
cooling and lubrication. This minimum flow requirement is often considered to be
about 10% of the nominal flow. See the actual pump curve for the relevant figures. A
pump likely to operate below its minimum flow rate for more than one minute, should
have a by-pass line installed. A temperature probe in the pump casing could also be
used for protection purposes.
• Maximum Flow - If the pump is operating at a very low counter-pressure, the power
consumption will be high. A typical situation is too many consumers in relation to
available capacity. Excessive power consumption can result in damage to driver,
couplings or pump. To avoid this situation consult the pump curve for the specific
application. The power consumption at a given capacity must not exceed the rating of
the system.
• The driver of the pump unit may be started in pump disengaged state after the following
measures are taken:
- Coupling to driver of the unit (usually main engine or genset front power take-off)
is installed, aligned and tightened according to specifications.
- It is recommended that the control system of the general FiFi system is up and
running. However, in practise during a vessel’s commissioning, engines are started
prior to FFS engineer attendance. It is then of vital importance that the customer
representatives observe locally on the unit.
• It is very important that the unit is not manually engaged with the suction valve to the
pump unit closed. More than 30 seconds of dry running can cause damage to seals and
bearings.
5 OPERATION
• Ensure that the pump turns freely by hand. If it does not, check for foreign matter in the
pump, or pipe stresses causing the impeller to seize in the casing.
• Fill the pump casing by opening the suction valve or in rare cases through a filling pipe.
• It is strongly recommended that the pump is engaged at idle speed of the driver. Consult
FFS for higher speed engagement.
• It is normal to do 1-2 local pump engagements at a typical system commissioning, to
locally verify pump function. Also visual checks of main water piping not leaking, is
done at this stage.
• Make sure the pump unit will have seawater circulation. The suction valve to the pump
and the bypass valve (around the discharge valve) on the pump’s pressure side must
always be open. (For information - Refer to the project specific Piping Arrangement
drawing with FFS project number and the suffix P1).
• Never run the pump for more than 30 seconds against a completely closed discharge
valve if a by-pass line is not installed. Otherwise there is a danger of overheating and
serious damage to the pump.
• The pump unit can – after the above mentioned verifications – be engaged remotely
from control system’s panel, typically located on the bridge of the vessel. For this
operation the control system of the general FFS system must be up and running
according to specifications, with all relevant alarms available.
• Gradually open the discharge valve until the required pumping capacity is achieved.
This operation shall only be done after the complete piping system has been water
filled. A partly filled piping system and/or rapid valve movements can cause water
hammer problems. This can result in damage to piping and various components.
• If the pumping capacity is significantly exceeding the specified duty point, it possible
that motor, couplings and pump may be overloaded. Find the capacity at duty point
from the pump curve supplied with every SFP pump.
• Run the system at duty point of the pump and observe that no alarms are activated and
that the project specific value of water pressure is obtained.
• Check that noise and vibration level is acceptable.
• Continue to check bearing temperature until a stable bearing temperature is reached.
• Maximum bearing temperature on the pump drive end is 90 deg C. Observe that
the temperature does not rise rapidly, and not passes this value. It is normal that the
bearing temperature is somewhat higher during the first time start-up, than during later
operation .The bearing on the non-drive end is a sleeve bearing lubricated by seawater.
Check bearing
temperature in this
area between
cooling ribs.
• To stop - Close the discharge valve slowly to avoid excessive pressure fluctuations.
• Stop the pump maximum 30 seconds after closing the valve to avoid overheating.
• Draining - It is strongly recommended to drain the pump casing after operation.
Flushing with fresh water is beneficial. Stagnant seawater can cause corrosion at high
temperatures often existing in an engine room. A ½” or ¾” BSP plug is located in the
lowest part of the pump casing for drainage purpose. A permanently installed drain line
+ valve make drainage easier.
• ATTENTION! - Suction valve must be fully open during operation. There must
always be a minimum of water circulation through the pump. No water circulation
will lead to rapid overheating and serious damage to the equipment. Pay extra
attention to this risk during start and stop procedure for the pump.
6 MAINTENANCE
6.1 Bearings
• Both the water lubricated bearing (non drive end) and ball bearing (drive end ) are
maintenance free. Observe bearings during operation for unusual noise or vibrations.
• The standard seal arrangement for all sizes SFP pumps is a soft packed gland. The
pump can also be supplied with a mechanical seal or a Lip seal.
• Check that the gland is dripping adequately. If overheating occurs, loosen the gland
nuts to increase the leakage and thereby the cooling effect. If leakage is excessive,
tighten the nuts 1/6 turn at 5 – 10 minute intervals.
• Leakage rate at 30 – 60 drips per minute is normal. Allow greater leakage rate for the
first few hours of operation Adjustment of seal gland should preferably be done with
the pump stationary.
• The gland packing seal is lubricated by water from the pressure side of the pump. This
is done via a stainless steel pipe connected to a lantern ring located between the soft
packing rings on the SFP 400x500 pump. The other SFP pump sizes do not have this
arrangement with pipe and lantern ring. Here lube water supply is provided internally.
• Mechanical seal: Check that overheating does not occur. The seal must never run dry.
Just a few seconds of dry running can ruin a mechanical seal completely.
• Lip seal: Reliable and maintenance free non-leaking seal. No adjustments needed. Dry
running is acceptable for a short periode, maximum 5minutes.
6.3 Cleaning
• In order to observe the state of the pump unit best possible, its exterior should be kept
clean.
• Do not clean the unit with high pressure washer – a high pressure water jet can in worst
case force water into the bearing area. Use freshwater and mild solvent (industrial
degreaser/white spirit) and apply by hand.
Over-throttling, i.e. the flow is too small Check operation – Ref 5.1