UNIDO - Technical Guidelines For The Development of Small Hydropower Plants

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 50

Technical Guidelines for the

Development of Small Hydropower Plants


Design

Part 6-1: Hydraulic Machinery


and Turbine Generator

SHP/TG 002-6-1: 2019


DISCLAIMER
This document has been produced without formal United Nations editing. The designations and the presentation of the material in this
document do not imply the expression of any opinion whatsoever on the part of the Secretariat of the United Nations Industrial Development
Organization (UNIDO) concerning the legal status of any country, territory, city or area of its authorities, or concerning the delimitation
of its frontiers or boundaries, or its economic system or degree of development. Designations such as “developed”, “industrialized” and
“developing” are intended for statistical convenience and do not necessarily express a judgement about the stage reached by a particular
country or area in the development process. Mention of company names or commercial products does not constitute an endorsement by
UNIDO. Although great care has been taken to maintain the accuracy of information herein, neither UNIDO nor its Member States assume
any responsibility for consequences which may arise from the use of the material. This document may be freely quoted or reprinted but
acknowledgement is requested.

© 2019 UNIDO / INSHP- All rights reserved


Technical Guidelines for the
Development of Small Hydropower Plants
Design

Part 6-1: Hydraulic Machinery


and Turbine Generator

SHP/TG 002-6-1: 2019


Technical Guidelines for the Development of Small Hydropower Plants – Design

ACKNOWLEDGEMENTS
The technical guidelines (TGs) are the result of a collaborative effort between the United Nations Industrial Development
Organization (UNIDO) and the International Network on Small Hydro Power (INSHP). About 80 international experts and 40
international agencies were involved in the document’s preparation and peer review, and they provided concrete comments
and suggestions to make the TGs professional and applicable.

UNIDO and the INSHP highly appreciate the contributions provided during the development of these guidelines and in particular
those delivered by the following international organizations:

- The Common Market for Eastern and Southern Africa(COMESA)

- The Global Network of Regional Sustainable Energy Centres (GN-SEC), particularly the ECOWAS Centre for Renewable Energy
and Energy Efficiency (ECREEE), the East African Centre for Renewable Energy and Energy Efficiency (EACREEE), the Pacific
Centre for Renewable Energy and Energy Efficiency (PCREEE) and the Caribbean Centre for Renewable Energy and Energy
Efficiency (CCREEE).

The Chinese government has facilitated the finalization of these guidelines and was of great importance to its completion.

The development of these guidelines benefited greatly from the valuable inputs, review and constructive comments as well
as contributions received from Mr. Adnan Ahmed Shawky Atwa, Mr. Adoyi John Ochigbo, Mr. Arun Kumar, Mr. Atul Sarthak,
Mr. Bassey Edet Nkposong, Mr. Bernardo Calzadilla-Sarmiento, Ms. Chang Fangyuan, Mr. Chen Changju, Ms. Chen Hongying ,
Mr. Chen Xiaodong, Ms. Chen Yan, Ms. Chen Yueqing, Ms. Cheng Xialei, Ms. Chileshe Kapaya Matantilo, Ms. Chileshe Mpundu
Kapwepwe, Mr. Deogratias Kamweya, Mr. Dolwin Khan, Mr. Dong Guofeng, Mr. Ejaz Hussain Butt, Ms. Eva Kremere, Ms. Fang
Lin, Mr. Fu Liangliang, Mr. Garaio Donald Gafiye, Mr. Guei Guillaume Fulbert Kouhie, Mr. Guo Chenguang, Mr. Guo Hongyou, Mr.
Harold John Annegam, Ms. Hou Ling, Mr. Hu Jianwei, Ms. Hu Xiaobo, Mr. Hu Yunchu, Mr. Huang Haiyang, Mr. Huang Zhengmin, Ms.
Januka Gyawali, Mr. Jing Songkun, Mr. K. M. Dharesan Unnithan, Mr. Kipyego Cheluget, Mr. Kolade Esan, Mr. Lamyser Castellanos
Rigoberto, Mr. Li Zhiwu, Ms. Li Hui, Mr. Li Xiaoyong, Ms. Li Jingjing, Ms. Li Sa, Mr. Li Zhenggui, Ms. Liang Hong, Mr. Liang Yong, Mr.
Lin Xuxin, Mr. Liu Deyou, Mr. Liu Heng, Mr. Louis Philippe Jacques Tavernier, Ms. Lu Xiaoyan, Mr. Lv Jianping, Mr. Manuel Mattiat,
Mr. Martin Lugmayr, Mr. Mohamedain Seif Elnasr, Mr. Mundia Simainga, Mr. Mukayi Musarurwa, Mr. Olumide Taiwo Alade, Mr.
Ou Chuanqi, Ms. Pan Meiting, Mr. Pan Weiping, Mr. Ralf Steffen Kaeser, Mr. Rudolf Hüpfl, Mr. Rui Jun, Mr. Rao Dayi, Mr. Sandeep
Kher, Mr. Sergio Armando Trelles Jasso, Mr. Sindiso Ngwenga, Mr. Sidney Kilmete, Ms. Sitraka Zarasoa Rakotomahefa, Mr. Shang
Zhihong, Mr. Shen Cunke, Mr. Shi Rongqing, Ms. Sanja Komadina, Mr. Tareq Emtairah, Mr. Tokihiko Fujimoto, Mr. Tovoniaina
Ramanantsoa Andriampaniry, Mr. Tan Xiangqing, Mr. Tong Leyi, Mr. Wang Xinliang, Mr. Wang Fuyun, Mr. Wei Jianghui, Mr. Wu
Cong, Ms. Xie Lihua, Mr. Xiong Ji, Ms. Xu Jie, Ms. Xu Xiaoyan, Mr. Xu Wei, Mr. Yohane Mukabe, Mr. Yan Wenjiao, Mr. Yang Weijun,
Ms. Yan Li, Mr. Yao Shenghong, Mr. Zeng Jingnian, Mr. Zhao Guojun, Mr. Zhang Min, Mr. Zhang Liansheng, Mr. Zhang Zhenzhong,
Mr. Zhang Xiaowen, Ms. Zhang Yingnan, Mr. Zheng Liang, Mr. Zheng Xiongwei, Mr. Zheng Yu, Mr. Zhou Shuhua, Ms. Zhu Mingjuan.

Further recommendations and suggestions for application for the update would be highly welcome.

IV SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

Table of Contents
Foreword VII
Introduction VIII
1 Scope 1
2 Normative references 1
3 Terms and definitions 1
4 Turbine 1
4.1 General requirements for turbine type selection 1
4.2 Selection of the rated head 3
4.3 Turbine type selection 3
4.4 Selection of the basic parameters of the reaction turbine 5
4.5 Selection of basic parameters of the Pelton turbine 7
4.6 Calculation of the regulation guarantee of the unit 9

5 Generator 9
5.1 General requirements for generator type selection 10
5.2 Rated data and main parameter selection 10
5.3 Selection of the generator mechanical structure 15
5.4 Generator auxiliary system 16

6 Turbine governing system 17


6.1 Basic principles for governing system type selection 17
6.2 Operating capacity of the governor 18
6.3 Control system of governor 18

7 Main valve of the turbine 19


7.1 Basic principles for the main valve type selection 19
7.2 Selection of the main valve 19
7.3 The seal type selection of the main valve 21

8 Auxiliary system 21
8.1 Technical water supply and the drainage systems 21
8.2 Oil system 22
8.3 Compressed air system 22
8.4 Hydraulic monitoring system 23
8.5 Selection of the lifting equipment 23
8.6 Heating and ventilation 23
8.7 Allocation of maintenance equipment for the electro-mechanical equipment 24
8.8 Schematic diagrams of typical oil, air and water systems 24

9 Fire extinguishing system 24


9.1 Basic principle for the design of the fire extinguishing system 24
9.2 Technical requirements 24

SHP/TG 002-6-1: 2019 V


Technical Guidelines for the Development of Small Hydropower Plants – Design

10 Layout of the powerhouse 25


10.1 Basic principle for the layout of the powerhouse 25
10.2 Technical requirements 25

Appendix A (Normative) Reference formula for the basic parameter


calculation for the reaction turbine 27
Appendix B (Normative) Reference formula for the basic parameter
calculation of the impulse turbine 32
Appendix C (Normative) Reference formula for the working capacity
calculation of the governing system for some turbines 36

VI SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

Foreword
The United Nations Industrial Development Organization (UNIDO) is a specialized agency under the United
Nations system to promote globally inclusive and sustainable industrial development (ISID). The relevance of
ISID as an integrated approach to all three pillars of sustainable development is recognized by the 2030 Agenda
for Sustainable Development and the related Sustainable Development Goals (SDGs), which will frame United
Nations and country efforts towards sustainable development in the next fifteen years. UNIDO’s mandate for
ISID covers the need to support the creation of sustainable energy systems as energy is essential to economic
and social development and to improving quality of life. International concern and debate over energy have
grown increasingly over the past two decades, with the issues of poverty alleviation, environmental risks and
climate change now taking centre stage.

INSHP (International Network on Small Hydro Power) is an international coordinating and promoting
organization for the global development of small hydropower (SHP), which is established on the basis of
voluntary participation of regional, subregional and national focal points, relevant institutions, utilities
and companies, and has social benefit as its major objective. INSHP aims at the promotion of global SHP
development through triangle technical and economic cooperation among developing countries, developed
countries and international organizations, in order to supply rural areas in developing countries with
environmentally sound, affordable and adequate energy, which will lead to the increase of employment
opportunities, improvement of ecological environments, poverty alleviation, improvement of local living and
cultural standards and economic development.
UNIDO and INSHP have been cooperating on the World Small Hydropower Development Report since year
2010. From the reports, SHP demand and development worldwide were not matched. One of the development
barriers in most countries is lack of technologies. UNIDO, in cooperation with INSHP, through global expert
cooperation, and based on successful development experiences, decided to develop the SHP TGs to meet
demand from Member States.

These TGs were drafted in accordance with the editorial rules of the ISO/IEC Directives, Part 2 (see www.iso.
org/directives).

Attention is drawn to the possibility that some of the elements of these TGs may be subject to patent rights.
UNIDO and INSHP shall not be held responsible for identifying any such patent rights.

SHP/TG 002-6-1: 2019 VII


Technical Guidelines for the Development of Small Hydropower Plants – Design

Introduction
Small Hydropower (SHP) is increasingly recognized as an important renewable energy solution to the
challenge of electrifying remote rural areas. However, while most countries in Europe, North and South
America, and China have high degrees of installed capacity, the potential of SHP in many developing countries
remains untapped and is hindered by a number of factors including the lack of globally agreed good practices
or standards for SHP development.

These Technical Guidelines for the Development of Small Hydropower Plants (TGs) will address the current
limitations of the regulations applied to technical guidelines for SHP Plants by applying the expertise and
best practices that exist across the globe. It is intended for countries to utilize these agreed upon Guidelines
to support their current policy, technology and ecosystems. Countries that have limited institutional and
technical capacities, will be able to enhance their knowledge base in developing SHP plants, thereby attracting
more investment in SHP projects, encouraging favourable policies and subsequently assisting in economic
development at a national level. These TGs will be valuable for all countries, but especially allow for the
sharing of experience and best practices between countries that have limited technical know-how.

The TGs can be used as the principles and basis for the planning, design, construction and management of
SHP plants up to 30MW.

• The Terms and Definitions in the TGs specify the professional technical terms and definitions commonly
used for SHP Plants.

• The Design Guidelines provide guidelines for basic requirements, methodology and procedure in terms
of site selection, hydrology, geology, project layout, configurations, energy calculations, hydraulics,
electromechanical equipment selection, construction, project cost estimates, economic appraisal,
financing, social and environmental assessments—with the ultimate goal of achieving the best design
solutions.
• Units Guidelines specify the technical requirements on SHP turbines, generators, hydro turbine governing
systems, excitation systems, main valves as well as monitoring, control, protection and DC power supply
systems.

• The Construction Guidelines can be used as the guiding technical documents for the construction of SHP
projects.

• The Management Guidelines provide technical guidance for the management, operation and maintenance,
technical renovation and project acceptance of SHP projects.

VIII SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

Technical Guidelines for the


Development of Small Hydropower Plants
Design

Part 6-1: Hydraulic Machinery


and Turbine Generator

SHP/TG 002-6-1: 2019 1


Technical Guidelines for the Development of Small Hydropower Plants – Design

1 Scope
This Part of Design Guidelines specifies the type selection design and the arrangement of the main and
auxiliary hydraulic machinery, the type selection design and arrangement of the turbine as well as the design
of the heating, ventilation and fire control systems of the SHP station. It includes the basic principles of the
type selection for the different machines, the selection and calculation of the basic parameters, the scheme
comparison as well as the examples of typical diagrams of the different powerhouse layouts.

2 Normative references
The following documents are referred to in the text in such a way that some or all of their content constitutes
requirements of this document. For dated references, only the edition cited applies. For undated references,
the latest edition of the referenced document (including any amendments) applies.

SHP/TG 001, Technical guidelines for the development of small hydropower plants —Terms and definitions.

3 Terms and definitions


For the purposes of this document, the terms and definitions given in IEC TR 61364 and SHP/TG 001 apply.

4 Turbine

4.1 General requirements for turbine type selection


4.1.1 The turbine type and the basic parameters shall be selected through technical and economic comparison
in accordance with the hydraulic energy parameters, the layout of the hydropower station and its operating
characteristics, the technical features, economic indexes, operation reliability, technical level of the design
and manufacture, the transportation and in combination with the field conditions.

4.1.2 The turbine type selection shall include the following contents:

a) Selection of the type and installation mode;

b) Selection of the number of installed units and the unit capacity;

c) Selection of the rated head of the turbine;

d) Selection of the basic parameters of the turbine, including the shaft power, runner diameter, rated speed,
rated discharge, efficiency, draft height and the setting elevation. For the impulse turbine, it is necessary
to select the jet diameter, number of nozzles and the draining height;

e) Selection of the appropriate model runner and the plotting of the turbine operating characteristic curve;

f) Estimation of the overall dimensions, weight and cost of the main components of the turbine;

4.1.3 Basic information for the selection of the hydropower station particulars shall include:

a) Operating head of the turbine (including the maximum head, minimum head and weighted average head).

2 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

b) Water intake system of the hydropower station;

c) Installed capacity of the hydropower station;

d) Upstream/downstream water levels;

e) Parameters of the power generation and water conveyance systems (including the type, arrangement,
length, pipe diameter and head losses of all the water conveyance systems from the water inlet for the
generation to the tailwater outlet of the hydropower station);

f) Tailwater level versus the discharge relation curve;

g) Guaranteed output of the hydropower station, the power weighting factor can be provided when necessary;

h) Operation mode of the hydropower station in the electrical power system, reservoir operation and power
evacuation modes;

i) Quality of the water passing through the turbine (including the sediment concentration through the
turbine, the particle size grading, Moh’s hardness, mineral composition, PH value and water temperature);

j) Meteorological conditions of the hydropower station (including the air temperature, water temperature
and relative humidity);

k) Geographic position of the hydropower station (including the sea level elevation, atmospheric pressure
and gravitational acceleration of powerhouse).

4.2 Selection of the rated head


4.2.1 The rated head shall be selected through technical and economic comparison in accordance with the
head variation of the hydropower station, the regulating characteristic of the reservoir, the stable operation
requirements of the unit, the operation mode of the hydropower station in the electrical power system and
the characteristics of the power generation and water conductor systems.

4.2.2 As for the hydropower station with the medium/high head, the rated head should be selected within
the scope of 0.85 to 0.95 times the weighted average head.

4.2.3 As for the run-of-river hydropower station, the rated head shall guarantee that the hydropower station
may generate the installed capacity.

4.2.4 As for the hydropower station on an overloaded river with the reservoir operating in a mode of “storing
clear water and discharging muddy water”, the rated head should be selected within the scope between the
weighted average head and the lower limit productive head in the storage period of the reservoir.

4.2.5 When the rated head is close to the minimum head, it is necessary to demonstrate its rationality and
economic efficiency. With regard to the impulse turbine with high head with small variation of the reservoir
water level, the minimum head may be used as the rated head of the turbine.

4.3 Turbine type selection


4.3.1 The turbine type shall be selected within the operation head scope in accordance with the basic
principles in 4.1. See Table 1 for the common turbine types and the applicable head scope.

SHP/TG 002-6-1: 2019 3


Technical Guidelines for the Development of Small Hydropower Plants – Design

Table 1 Turbine types and the applicable head scope

Turbine type

Classification as per the Classification as per the Classification as per the Applicable head scope, m
energy conversion mode water flow direction structural feature

Bulb turbine

shaft-extension-type
Through-flow turbine
tubular turbine 3~30
pit turbine

Reaction turbine rim-generator turbine,

Propeller turbine
Axial-flow turbine 3~80
Kaplan turbine

Inclined-flow turbine 40~120

Francis turbine 20~500

Pelton type turbine 100~1700

Impulse turbine inclined-jet turbine 30~150

cross flow turbine 20~100

NOTE The applicable head scope is the parameter under normal conditions, which may be determined through comprehensive
comparison according to the specific situation and the special requirements of the different projects when selecting the type of small
turbine. The applicable head scope for the various types of units in the junction head section may be appropriately broadened.

4.3.2 As for the run-of-river hydropower station with a maximum head of 20m or lower and a capacity
greater than 10MW, the through-flow turbine should be selected by preference.

4.3.3 When there are two applicable turbine types under the junction head, it is necessary to select one
through technical and economical comparison in the respect of the technical characteristic parameters, the
economic indicators, operational reliability and the design and manufacturing difficulty.

4.3.4 The model runner should be selected in combination with the selected turbine type and according to
the operation head of the hydropower station, after appropriate technical and economical comparisons.

4.3.5 The model runner of the turbine shall have relatively higher energy and cavitation performance, and its
performance shall be free from any obvious pressure fluctuations and cavitation in all operating conditions.

4.3.6 For the hydropower station on an overloaded river, it is necessary to select the model runner with a
relatively lower rotating speed; for the hydropower station with big head variation, it is necessary to select
the model runner with the wider stable operating range; for the hydropower station in high altitude localities,
it is necessary to select the model runner with the appropriate cavitation performance in combination with
the setting elevation element.

4.3.7 The layout of the vertical shaft and horizontal shaft Francis turbines and impulse turbines should be
combined with the single unit capacity, the diameter of the runner, and the appropriate speed and plant
layout. The horizontal shaft should be preferred.

4.3.8 See Appendix C.4 to Appendix C.7 for the small turbine generator units with the conventional vertical
shaft and the horizontal shaft.

4 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

4.4 Selection of the basic parameters of the reaction turbine


4.4.1 The basic parameters of the reaction turbine shall be selected after the primary selection of the unit
capacity, rated head and model runner is determined; the main parameters include the runner diameter,
rated speed, rated discharge, rated efficiency, rated power, draft height, maximum runaway speed, maximum
head, minimum head, design head and the weighted average efficiency.

4.4.2 According to the comparative calculation, the different parameter combination schemes should
be combined with the power plant layout, the actual topography and geological conditions, the operating
water head range and the reservoir regulation characteristics, and the technical characteristics, economic
indicators, operational reliability, and design and manufacturing technology level, after technical and
economy comparison, a reasonable scheme for the basic parameters of the hydraulic turbine is selected.

4.4.3 After determining the main parameters of the turbine, the turbine operating performance curve
including the iso-efficiency curve, the iso-cavitation curve and the output limitation curve should be drawn.

4.4.4 Axial hydraulic thrust and the main component weight of the turbine should be estimated.

4.4.5 The turbine shall have the relatively higher weighted average efficiency and the operational scope shall
include the high efficiency area. The overall operating condition of the turbine in the working water head
should be better, and there is no obvious vibration area.

4.4.6 The draft height and setting elevation of the turbine shall be determined according to the following
requirements:

a) The draft height of the reaction turbine shall be respectively calculated in accordance with the operating
conditions under the different characteristic heads and their corresponding initial cavitation coefficients
σi. If no initial cavitation coefficient σi is available, it may be calculated with the critical cavitation
coefficient multiplied by the ratio coefficient Kσ.

b) Under the condition that the power plant units share the tail water pool, when 1 or 2 units are installed,
the requirements of the suction height and the tailwater level of a unit at 50% maximum output operation
under various water heads should be satisfied; when more than 2 units are installed, the requirements of
the suction height and the tailwater level of one unit at maximum output operation under various water
heads should be satisfied.

c) The design tailwater level for determining the setting elevation shall be selected with comprehensive
consideration given to the relation curve between the tailwater level and the discharge, the power
generation requirement at the preliminary stage, the requirements for flood control and the operational
water level of the downstream cascade power stations.

d) The setting elevation of the turbine shall meet the requirements for the draft height and the corresponding
tailwater level under various operating conditions, and shall comply with the requirement that the
minimum submerged depth of the upper edge of the draft tube (or the tailrace tunnel, excluding the
tailrace tunnel with sloping ceiling) outlet shall not be less than 0.3m to 0.5m.

e) In addition to satisfying the aforementioned conditions a), b), c)and d), the final selection of the installation
elevation should be based on the actual topographic and geological conditions of the project, the layout of
the plant hub and other factors, and the comparison between technique and economics.

4.4.7 The maximum runaway speed of the Francis or propeller turbine should be determined according to the
maximum net water head and the maximum unit runaway speed. The maximum runaway speed of the Kaplan
turbine should be calculated according to the coupled relationship. When there are special requirements, it
can be calculated according to the damage from the on-cam operating condition.

SHP/TG 002-6-1: 2019 5


Technical Guidelines for the Development of Small Hydropower Plants – Design

4.4.8 The turbine runner diameter shall be calculated by the formula (1).

Nf
D1  .....................................................................(1)
9.81Q H sj1.5T f
'
1
where

D1 is the runner diameter,in m;

Nf is the rated power of generator, in kW;

Q1’ is the unit discharge under design conditions, in m3/s;

T is the prototype turbine efficiency;

f is the generator efficiency.

4.4.9 The rated rotating speed shall be calculated by the formula (2):

n1' H pj
nr  ........................................................................................ (2)
D1
where

nr is the rated speed, in r/min;

n1’ is the unit speed, r/min; (1-1.05)n10’is taken for Francis turbine; 1.1n10’is taken for high specific speed
ial-flow turbine;

Hpj is the weighted average head, in m.

4.4.10 See Appendix A for reference formulas for the rated discharge Qr , draft height H S , setting elevation
 of the turbine and the correction calculation of the reaction turbine efficiency.

6 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

4.5 Selection of basic parameters of the Pelton turbine


4.5.1 The basic parameters of the Pelton turbine shall be selected after the primary selection of the unit
capacity, rated head and model runner is determined; the main parameters include the rated head, rated
speed, rated discharge, rated power, pitch diameter, jet diameter, m (D1/d0), that of the ratio m(D1/d0) of the
runner diameter to the jet diameter, the bucket numbers, rated efficiency, maximum head, minimum head,
design head, runaway speed and discharging head. The selection of the basic parameters of the turbine shall
be determined through technical and economic comparison.

4.5.2 After the main parameters of the turbine are determined, the turbine operating performance curves
including the turbine output limitation curve and the equivalent efficiency curve shall be drawn.

4.5.3 The basic parameters of the Pelton turbine may be calculated with the fixed specific speed method
and converted according to the combined characteristic curve of the model, or calculated with the variable
specific speed method.

4.5.4 The number of nozzles of the Pelton turbine is usually 1, 2, 4 or 6; the number of nozzles shall be
selected with consideration given to the arrangement of the nozzles to avoid the mutual interference of the
jet flow.

4.5.5 When selecting the number of nozzles, it is necessary to avoid the jet flow funnel phenomenon,
meanwhile the arrangement and machining of the buckets shall be taken into account.
4.5.6 As for the multi-nozzle turbine, its jet flow intersection angle shall not be a multiple integer of the
intersection angle between the adjacent buckets.

4.5.7 For ensuring the relatively higher efficiency of the turbine, it is necessary to select the value m within
the scope of 10 to 20; when selecting the value m, it is necessary to consider the manufacturing of the runner
and the strength of the bucket; usually, the higher value is taken for the high head and the smaller value is for
the low head.

4.5.8 When calculating the unit discharge of the turbine, it is necessary to consider that the value m of the
real turbine is different from that of the model turbine; its unit discharge may be converted by the formula
(3):

Q1 = (m/m M ) 2 Q1' ..........................................................................(3)


where

Q1" is the unit discharge of the model turbine, in m3/s;

Q1' is the unit discharge of the real turbine, in m3/s;

m is the value m of the real turbine;

mM is the value m for the model turbine.

SHP/TG 002-6-1: 2019 7


Technical Guidelines for the Development of Small Hydropower Plants – Design

4.5.9 The efficiency of the Pelton turbine is usually same as the efficiency of the model turbine and will not
be corrected. When the value m of the turbine exceeds the scope of 10 to 20, about 0.5% negative correction
may be considered.

4.5.10 The design head of the turbine shall be the head corresponding to the maximum efficiency point of the
model, and the operation scope of the turbine shall include the high efficiency area.

4.5.11 The maximum unit runaway speed of the Pelton turbine may usually be 70r/min.

4.5.12 The draining height of the Pelton turbine shall be selected to ensure the safe and stable operation of
the turbine, avoid the influence of the tailwater surge and keep sufficient aeration height for the tailrace at the
maximum tailwater level and under any power generating condition of the hydropower station.

4.5.13 The discharge height should be the diameter (1 to 1.5) D1 of the runner pitch circle. The horizontal
shaft unit should have a low value, the vertical shaft unit should have a large value. When determining the
discharge height, the necessary ventilation height should be ensured, and the ventilation height should be no
less than 300 mm.

4.5.14 The runner diameter and the value m shall be calculated by the formula (4) and the formula (5):

(39 ~ 40) H sj
D1 
nr ........................................................................(4)
D1
m=

d 0 .......................................................................................(5)

where

D1 is the pitch diameter of the bucket, in m;

m is the ratio of the runner diameter to the jet diameter, non-dimensional.

The value m should be within the scope of 10-20. The lower value applies to the low head and the higher
value applies to the high head.

4.5.15 See Appendix B for the reference formulas for the estimation of the jet diameter d 0 , rated speed
nr , nozzle diameter d p and the number of buckets Z1 of the Pelton turbine and the calculation of the draining
height h p and setting elevation  .

4.5.16 The basic parameters of the inclined-jet turbine and the cross-flow turbine may be selected with
reference to the requirements in this section.

8 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

4.6 Calculation of the regulation guarantee of the unit


4.6.1 Calculation of the regulation guarantee of the turbine shall be conducted according to the main electrical
connection mode of the hydropower station, the power grid requirements, type and parameters of the water
conveyance system of the hydropower station, the characteristics and parameters of the turbine generator
units as well as the operating conditions.

4.6.2 As for the hydropower station with bifurcated penstocks, the maximum speed rising ratio of the units
and the maximum pressure rising ratio at the end of the spiral casing shall be calculated according to the
number of units connected to the main penstock and the main electrical connection mode, as well as the
number of units that are able to simultaneously perform load shedding.

4.6.3 As for the hydropower station with a relatively simpler power generation and water conveyance
system, the calculation of the regulation guarantee may be conducted by the empirical formula, and with the
numerical method or the analytical method; as for the hydropower station with a complex water conveyance
system, the calculation shall be made by computer simulation.

4.6.4 Axial-flow and through-flow turbine units should be equipped with a closing device with two gradients
of closing rate to reduce the reverse hydraulic thrust and mitigate the influence of the turbine lifting.

4.6.5 The water flow inertia time constant Tw of the water conveyance system for the turbine without a
pressure regulating facility shall not be more than 4s; the inertia time constant Ta of the reaction turbine unit
shall not be less than 4s and the inertia time constant Ta for the impulse turbine unit shall not be less than
2s.The specific value Tw/Ta shall not be more than 0.4; if Tw/Ta is more than 0.4, the water diversion system
and unit stability calculation shall be performed in case of small fluctuations according to the actual situation.

4.6.6 When calculating the rising ratio of the rotating speed of the axial-flow and through-flow turbine
units, it is necessary to include the influence of the inertia moment of the water flow; the calculation of the
regulation guarantee shall include the pressure of the reverse water hammer.

4.6.7 In case of load shedding, the guarantee value of the maximum rising ratio of the rotating speed shall be
selected according to the following different circumstances:

a) The guarantee value should be less than 50% when the proportion of the unit capacity to the total capacity
of the electrical power system is relatively large or the unit has the frequency adjustment function;

b) The guarantee value should be less than 60% to 65% when the proportion of the unit capacity to the total
capacity of the electrical power system is not large, or the unit has no frequency adjustment function;

c) The maximum rising ratio of the rotating speed of the through-flow turbine unit should be less than 65%;

d) The maximum rising ratio of the rotating speed of the impulse turbine unit should be less than 30%.

4.6.8 In case of load shedding, the guarantee value of the maximum pressure rising ratio at the end of the
spiral casing (in front of the movable guide vane of the through-flow turbine unit) shall be selected as per the
following circumstances:

a) The guarantee value should be 70% to 100% if the rated head is less than 20m;

b) The guarantee value should be 70% to 50% if the rated head is 20m to 40m;

c) The guarantee value should be 50% to 30% if the rated head is 40m to 100m;

d) The guarantee value should be 30% to 25% if the rated head is 100m to 300m;

e) The guarantee value should be less than 25% if the rated head is more than 300m.

SHP/TG 002-6-1: 2019 9


Technical Guidelines for the Development of Small Hydropower Plants – Design

4.6.9 When the unit load suddenly increases or decreases, the minimum pressure at the highest point of
various sections along the entire length of the penstock shall not be less than 0.02MPa, and the negative
pressure flow separation phenomenon shall not occur.

4.6.10 In case of load shedding, the maximum vacuum guarantee value at the entrance section of the draft
tube shall not be more than 0.08MPa.

5 Generator

5.1 General requirements for generator type selection


5.1.1 The type of generator shall be selected through technical and economic comparison mainly in accordance
with the type and the parameters of the turbine as well as the requirements of the electrical power system,
and in combination with the parameters such as the unit output determined during turbine type selection,
the rotating speed, unit structure and layout form.

5.1.2 The type selection for the generator shall include the following contents:

a) Rated power(Pr)or rated apparent power(Sr) of the generator;

b) Rated voltage of the generator (Ur);

c) Rated speed (nr);

d) Rated frequency (fr);

e) Power factor (cosΦ);

f) Insulation grade;

g) Exciting mode;

h) Ventilation-cooling type of the generator;

i) Moment of inertia of the generator (GD2);

j) Estimation of the overall dimensions, weight and cost of the main components of the generator.

5.1.3 Main basis for the generator type selection:

a) Determine the power and rotating speed according to the turbine characteristics;

b) Determine the voltage and power factor according to the requirements of the electrical power system;

c) Determine the moment of inertia of the generator according to the calculation of the regulation guarantee
of the hydropower station and the requirement of the electrical power system;

d) Determine the structural style of the generator according to the general situation.

5.2 Rated data and main parameter selection

5.2.1 Power

The generator power shall meet the following requirements:

10 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

a) Relationship between the generator power and the turbine output:

1) Directly coupled unit: The rated power of the generator shall be equal to the rated output of the
turbine multiplied by the generator efficiency;

2) Booster unit: The rated power of the generator shall be equal to the rated output of the turbine
multiplied by the booster efficiency and by the generator efficiency.

b) Priority selection series (MW) of generator rated power:

0.5, 0.63, 0.8, 1.0, 1.25, 1.6, 2.0, 2.5, 3.2, 4.0, 5.0, 6.3, 8.0, 10.0

5.2.2 Voltage

The generator voltage shall meet the following requirements:

a) The requirements of the power grid of the country where the hydropower station is located.

b) The rated voltage shall be selected with consideration given to the value range of the rated current. The
rated current shall be calculated by the formula (6):

1000 Pr
Ir =
3U r cos ..............................................................................(6)

where

Ir is the rated current, in amperes, in A;

Pr is the rated power, in megawatts, in MW;

Ur is the rated voltage, in volts, in V;

Cosφ is the power factor.

5.2.3 Power factor

The generator power factor shall meet the following requirements:

a) The rated power factor may lag 0.8 or 0.92 under the premise of meeting the requirements of the power
grid;

b) Under rated power of the generator, the leading phase operation depth is allowed;

c) It is preferable to select a higher power factor value when the system permits, select a lower value when
the hydropower station is close to the load centre and select a higher value when the transmission
distance is great.

SHP/TG 002-6-1: 2019 11


Technical Guidelines for the Development of Small Hydropower Plants – Design

5.2.4 Synchronous speed

The generator synchronous speed shall meet the following requirements:

a) The rated synchronous speed of the generator shall be determined by the turbine type. It shall be
calculated by the formula (7):

60 fr
nr =
p .....................................................................................(7)

where

nr is the rotating speed, in revolutions per minute, in r/min;

fr is the grid frequency, in Hz;

p is the number of pole pairs, 2p refers to the number of poles.

b) See Table 2 for the rotating speed of the conventional generator.

Table 2 Optional rotating speed for the synchronous generator

Number of
4 6 8 10 12 14 16 (18) 20 (22) 24
poles 2p

nr (50Hz) 1500 1000 750 600 500 428.6 375 (333.3) 300 (272.7) 250

nr (60Hz) 1800 1200 900 720 600 514.3 450 (400) 360 (327.3) 300

Number of
(26) 28 30 32 (34) (36) 40 42 (44) 48 (50)
poles 2p

nr (50Hz) (230.8) 214.3 200 187.5 (176.5) (166.7) 150 142.9 (136.4) 125 (120)

nr (60Hz) (276.9) 257.1 240 225.0 (211.8) (200) 180 171.4 (163.6) 150 (144)

Number of
(52) 56 60 64 (66) (68) 70 (72) (78) 80 …
poles 2p

nr (50Hz) (115.4) 107.1 100 93.8 (90.9) (88.2) 85.7 (83.3) (76.9) 75 …

nr (60Hz) (138.5) 128.6 120 112.5 (109.1) (105.9) 102.9 (100) (92.3) 90 …
NOTE The rotating speeds not in parentheses are the recommended speeds; the rotating speeds in parentheses may be selected when
necessary.

c) The coefficient for determination of the unit rotating speed shall be calculated by the formula (8); the
coefficient for determination of the rotating speed shall meet the provisions of Table 3:

Kn = Pr(10 3 nr ) 3 .............................................................................(8)
where

Kn is the coefficient for determination of the rotating speed;

Pr is the rated power, in megawatt, in MW;

nr is the rated rotating speed, in revolutions per minute, in r/min.

12 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

Table 3 Coefficient for determination of the rotating speed

2<Kn≤4

For the vertical


type nr≥1000
Kn Kn≤0.01 0.01<Kn≤0.15 0.15<Kn≤2 Kn>4
For the
horizontal type
nr≥1500

Rotating speed type Ultra-low speed Low speed Medium speed High speed Ultra-high speed

NOTE Neither the ultra-low


speed nor the ultra-high
rotating speed is preferable
for the units. It is necessary to
perform the detailed technical
assessment when the ultra-
high rotating speed has to be
selected.

5.2.5 Generator efficiency

The generator efficiency is positively correlated to the capacity and the rotating speed. At the rated power
factor, the relationship between generator power and efficiency shall meet the requirements in Table 4.

Table 4 Relationship between output and efficiency

P (MW) 0.5<P≤1.0 1.0<P≤2.0 2.0<P≤5.0 5.0<P≤10

Efficiency (%) 90~94.5 90~95.5 92~96 93~96.5

5.2.6 Insulation grade

The insulation grade of the generator shall be Grade F. In the high altitude region or under special ambient air
temperature, the temperature rise shall be corrected.

5.2.7 Moment of inertia

The moment of inertia shall meet the following requirements:

a) The mechanical time constant shall be calculated by the formula (9); the value range shall meet the
provision of Table 5.


Tmec = 2.74GD 2 (10 3 nr ) 2 / Pr ................................................................(9)
where

Tmec is the mechanical time constant;

GD2 is the moment of inertia, in t.m2;

nr is the rated speed, in revolutions per minute, in r/min;

Pr is the rated power, in megawatts, in MW.

SHP/TG 002-6-1: 2019 13


Technical Guidelines for the Development of Small Hydropower Plants – Design

Table 5 - Value range of Tmec

nr (r/min) 1500≤nr≤1000 750≤nr≤428.6 375≤nr≤200 nr<200


Tmec (s) 2~3.5 2.5~5 3~6 3.5~6.5

NOTE For the low-


speed generator
and the high-power
generator, it is allowed
to select the higher
value in Table 5;
for the high-speed
generator and low-
power generator, it is
necessary to select the
lower value.

b) Method for the increasing moment of inertia:

1) A small amount of increase may be realized by increasing the weight of the rotor section with the
larger rotary diameter;

2) A relatively greater amount of increase may be realized by increasing the size of the stator bracket;
3) For the horizontal unit, the moment of inertia may be increased by installing the additional flywheel
according to the provisions in Table 6.

Table 6 - Moment of inertia increased by the additional flywheel

nr (r/min) 1500 1000 750 600、500 ≤428.6

GD2 (tm2) 0.2~0.7 0.3~1.4 0.5~3 0.75~4.5 1~6


NOTE Take the higher value for high-power generator and the smaller value for low-power generator.

d) Determination of the moment of inertia of the unit:

1) The moment of inertia for the unit shall be determined through calculation of the regulation guarantee
of the hydraulic system of the hydropower station;

2) The value for the moment of inertia shall be reasonable; when the relatively higher moment of inertia
is required, it is necessary to comprehensively consider the influences on generator dimension,
appearance, efficiency, stability and weight.

14 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

5.2.8 Short-circuit ratio

The value for the generator short-circuit ratio shall be in the range provided in Table 7.

Table 7 Value for the power factor and the short-circuit ratio

Power factor (lag) 0.8 0.85 0.9

Short-circuit ratio 0.9~1.0 0.95~1.05 1.0~1.1

NOTE Higher value is for the unit


operating in the small power grid and
for the low-speed unit, and the lower
value is for the high-speed unit.

5.3 Selection of the generator mechanical structure

5.3.1 Size of the stator bracket

The size of the stator bracket shall be selected as follows:

a) Common sizes include(mm): 740, 850, 990, 1180, 1430, 1730, 2150, 2600, 2860, 3250, 3300, 3600, 3850,
4250, 4650, 5000, 5500 and 6000;
b) The conventional size of the stator bracket may be estimated by the formula (10):

Pr 1.25 0.25
D 1500( kd )
nr ....................................................................... (10)

where

D is the preliminarily- calculated diameter of the stator bracket size, in mm;

Pr is the rated power, in MW;

nr is the rated speed, in r/min;

Kd is the value coefficient, take 1.35 for ultralow speed, 1.4 for low speed and 1.5 for other speeds.

c) The size of the stator bracket of the vertical reaction turbine unit may be calculated by the formula
(11):
 2.7 
D  K S D1 1  
 2 P  .......................................................................... (11)

where

D1 is the runner diameter, in mm;

Ks is the take 1.35 for the axial-flow turbine and 1.45 for the Francis turbine;

2P is the number of poles of the generator.

d) The value D for the generator shall be estimated by the formula (10), another value D for the vertical
reaction generator shall be estimated by the formula (11) as if the head cover is lifted out in its
entirety from the inner circle of the core; the higher value shall be selected after comparison, and

SHP/TG 002-6-1: 2019 15


Technical Guidelines for the Development of Small Hydropower Plants – Design

then a similar size is selected;

e) It is necessary to select the smaller size for the horizontal unit to reduce the centre height of the unit and
to improve the unit stability.

5.3.2 Bearings

There are mainly two bearing types, i.e. rolling bearing and sliding bearing:

a) Each generator shall be fitted with at least two bearings which shall be selected by the manufacturer
according to the load condition.

b) Rolling bearing applies to the series of the horizontal generator with a bracket diameter of990 mm or
smaller and the unit has two or three or four fulcrums, as well as the vertical generator with a bracket
diameter of 1180 mm or smaller which does not sustain the weight of the rotary part and the axial
hydraulic thrust of the turbine.

c) Sliding bearing applies to all the generators.

d) Except that the horizontal impulse unit is fitted with only two transverse bearings, the generator unit of
the other types shall be fitted with at least one thrust bearing.

5.4 Generator auxiliary system

5.4.1 Ventilation-cooling system

The cooling mode of the generator is air cooling - the ventilation patterns mainly include closed recirculation,
duct ventilation and open-type ventilation.

a) Closed recirculation: The hot air generated from the cooling of the generator is cooled in the air cooler,
and then returned to the generator in a closed loop which applies to generators of all types. The closed-
recirculation air cooler of the horizontal generator may be arranged in the turbine pit by the side or on
the top of the generator.

b) Duct ventilation: Including the ordinary duct ventilation structure employing the direct axial air inlet
mode and the closed-pipeline ventilation structure absorbing air from the turbine pit.

c) Open-type ventilation: Take air from the powerhouse to cool down the generator and then discharge the
hot air directly in the powerhouse.

d) See Table 8 for the application scope of the different ventilation types.

Table 8 Application scope of the different ventilation types

Ordinary pipeline Closed pipeline Closed recirculation


Ventilation pattern Open-type ventilation
ventilation ventilation ventilation

Power Pr (MW) ~1.0 0.8~3.2 2.5~6.3 3.2~

NOTE Both ventilation patterns within the power range overlapping two columns may be selected for the generator.

16 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

5.4.2 Braking device and jack system

The unit with the sliding bearing should be equipped with mechanical braking devices, while the impulse
turbine unit with reverse jet braking should not be equipped with mechanical braking

a) The braking medium of the mechanical braking device should be0.7MPa compressed air or the pressure
oil of the regulator after pressure reduction.

b) The brake shoes shall be made of non-asbestos environmentally-friendly material.

c) In the mechanical braking device for the vertical generator, the pressure oil shall be able to jack up the
rotating part of the unit and the lock safely on any position - the brake with a piston diameter of more
than 100mm shall employ the oil-gas separation structure.

5.4.3 Fire extinguishing apparatus

The fire extinguishing method shall be selected for the hydropower station and generators according to the
local fire control specifications.

5.4.4 Dehumidification device

The generator shall determine whether to install the dehumidification device according to different
environmental humidity and unit capacity. The dehumidification device may be electric the heater and the
dehumidifier. In case of the electric heater, it is necessary to ensure that the air temperature in the turbine
pit is 5K higher than the ambient temperature, meanwhile a local high temperature which might damage the
insulation is unacceptable.

6 Turbine governing system

6.1 Basic principles for governing system type selection


6.1.1 The governing system shall be able to reliably control the unit under all operating conditions and
start/stop the machine in the time required by the calculation of the regulation guarantee. The governor
parameters shall be decided by the turbine manufacturer, and have sufficient safety margins.

6.1.2 The operating capacity of the governor shall match with the turbine. The governor shall use the most
advanced and latest technology, operate reliably, be convenient for maintenance and easily realize the
automation of the hydropower station.

6.1.3 The unit which might operate in the isolated grid shall be equipped with the microprocessor-based
automatic turbine control system for the convenience of ensuring the safety of the equipment in the
hydropower station and the electrical safety of the users when the unit is disconnected from the system.

6.1.4 As for the small and miniature units without the frequency regulation task and with no need to
guarantee the auxiliary power when the unit breaks down, it is allowed to select the electric actuator or the
hydraulic actuator, but it is necessary to ensure that the unit could stop safely and reliably when it breaks
down. As for the hydropower station without the DC operating power supply, the actuator selected shall have
the emergency shutdown device acting in case of power failure.

6.1.5 As for the governor with the pressure regulating valve control function, the control of its pressure
regulating valve shall employ the hydraulic-coordinated mechanism.

SHP/TG 002-6-1: 2019 17


Technical Guidelines for the Development of Small Hydropower Plants – Design

6.1.6 The governor should employ the structural style of the high oil pressure (10MPa and above) bladder
type accumulator and be fitted with the external servomotor.

6.1.7 The governor shall satisfy all kinds of requirements for automatic regulation and remote control. It
could be operated manually and meet the demands in the process of starting, stopping, emergency stopping,
and the overhaul process of the unit.

6.2 Operating capacity of the governor


6.2.1 The operating capacity of the governor shall be selected so that the unit could be reliably controlled
under the maximum head and the maximum discharge and be started and stopped as per the time required
by the calculation of the regulation guarantee. The operating capacity of the governor shall have sufficient
reserve allowance.

6.2.2 The operating capacity of the control systems for the medium and small sized Francis and axial-flow
fixed blade propeller turbine may be calculated by the formula (12):

A = KQ H max D1
........................................................................ (12)

where

A is the operating capacity of servomotor, in N·m;

K is the coefficient, value range: 250 to 300;

Q is the rated discharge of unit, in cubic meters per second, in m3/s;

Hmax is the maximum head, in meters, in m;

D1 is the diameter of the turbine runner, in m.

6.2.3 See Appendix C for the reference formulas for the calculation of the operating capacity of the governing
systems of the impulse turbine, Kaplan turbine, shaft-extension through-flow and bulb through-flow turbines.

6.3 Control system of governor


6.3.1 The control system of the governor should employ the single microcomputer system and be connected
with the PID structure in parallel.

6.3.2 The technologically advanced and latest hardware and supporting electronic components should be
adopted, and the hardware should be the programmable logic controller (PLC) or the single chip, and the
interface communicating with the monitoring system shall be equipped.

6.3.3 The control system of the governor shall have the following basic auxiliary functions: the frequency
tracking (for fast synchronization), trouble detection and treatment, artificial dead band, non-disturbance
manual automatic switchover, auxiliary test and partial fault-tolerance functions.

18 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

7 Main valve of the turbine

7.1 Basic principles for the main valve type selection


7.1.1 For the SHP stations that supply several turbines by a single penstock, the main valve should be set in
front of each turbine in order to ensure that each unit can generate electricity separately, conduct maintenance
separately and provide accident protection.

7.1.2For the unit water conveyance system of the dam toe hydropower station with the short penstock, or
the low head unit water conveyance system of the runoff type hydropower station or the river bed type
hydropower station, the intake or tailwater outlet has been equipped with the fast gate as the unit accident
protection, so the intake valve cannot be installed before the turbine.

7.2 Selection of the main valve


7.2.1 The selection of the intake valves for the hydraulic turbines should be based on comprehensive analysis
of the technical, economic and operational safety and reliability, according to the head of the power station,
the maximum transient pressure, the rated flow rate of the turbine, the diameter of the spiral case inlet and
the sediment characteristics.

7.2.2 The selection of main valve shall include the following contents:

a) Intake valve type;

b) Design pressure and nominal diameter of the intake valve;

c) Operation mode of the intake valve;

d) Sealing type of the intake valve;

e) Type and diameter of the bypass valve;

f) Opening and closing time of the intake valve.

7.2.3 Basic information for the type selection of the intake valves:

a) The maximum static head and the maximum transient pressure at the intake valve of the power station;

b) Rated flow rate of the turbine;

c) Spiral case inlet diameter;

d) The content and characteristics of the sediment passing through the machine;

e) Length of the diversion system and the emptying time.

SHP/TG 002-6-1: 2019 19


Technical Guidelines for the Development of Small Hydropower Plants – Design

7.2.4 Selection of the main valve type:

a) The butterfly valve, spherical valve and gate valve are often used as the main valves of the turbine. When
the head is lower than 250m, the butterfly valve should be selected. When the head is higher than 250m
(inclusive), the spherical valve or the gate valve should be selected. The butterfly valve used as the main
valve of the turbine shall be of the eccentric structure, the valve body shall be marked with an arrow
indicating the water flow direction. Full-bore fixed spherical valve shall be used and arranged horizontally.
The gate valve shall be of full-bore structure and the valve shaft shall be installed vertically.

b) The main valve of the turbine shall be able to be closed in flowing water - the closing time shall not
exceed the time allowable for the continuous operation of the unit under maximum runaway speed. The
main valve can be opened normally and will not produce harmful vibration when the pressure difference
between both sides is not more than 30% of the maximum static water pressure.

7.2.5 Selection of the basic parameters of the main valve:

a) The design pressure of the main valve is the maximum transient pressure, in MPa.

b) The nominal diameter of the butterfly valve may be calculated by the formulas (13) and (14):

D0
Df =
................................................................................. (13)

= 1 0.06873 H max
..................................................................... (14)

where

Df is the diameter of the butterfly valve, in m;

Do is the diameter of section of the spiral casing inlet, in m;

α is the coefficient related to the head;

Hmax is the maximum static head of the hydropower station, in m.

c) The operating mode of the main valve shall meet the following requirements:

1) The main valve may be operated manually, hydraulically or electrically. As for the hydropower station
designed to be unattended (or attended with few people), the main valve shall be electrically or
hydraulically driven. Manually operated main valve is used for very small turbines.

2) The hydraulically-driven main valve has mainly two types – namely the counterweight and the
accumulator type. The counterweight hydraulic control device opens the valve with the oil pressure
supplied by the oil pump and closes the valve with the counterweight. The accumulator type control
device opens or closes the valve with the oil pressure supplied by the accumulator and the oil pump
is equipped to maintain the oil pressure in the accumulator. The hydraulically-driven main valve shall
be equipped with the manual mechanical locking device for overhaul.

3) The manual valve shall be fitted with a legible arrow indicating the closing direction.

d) The type selection and diameter of the bypass valve shall meet the following requirements:

1) The bypass valve may employ the straight-through valve or the angle valve. As for the medium and
low heads, the straight-through valve is usually used and, as for the high head, the angle valve is used.

20 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

2) The discharge capacity of the bypass valve shall be greater than the water leakage of the guide vane -
its nominal diameter shall not be less than 10% of the nominal diameter of the main valve.

3) As for the high sediment concentration and the relatively higher head, the diameter of the bypass
valve may be preliminarily calculated by the formula (15):

Qsj
D p = (0.29 ~ 0.33)
H sj
.............................................................. (15)

where

Qsj is the design discharge of the turbine, in m3/s;

Hsj is the design head of the turbine, in m.

e) The adjustable scope of the opening and closing time of the main valve should be 60s to 120s. The
closing time of the main valve in flowing water shall not exceed the allowable operating time of the
unit at maximum runaway speed.

7.3 The seal type selection of the main valve

When the head is medium or low and the sediment concentration in the water flow is high, the rubber soft
seal should be used; when the head is high and the sediment concentration is low, the metal hard seal should
be used. The shaft end seal may employ the entire-loop solid rubber seal.

8 Auxiliary system

8.1 Technical water supply and the drainage systems


8.1.1 The selection of the water source should be based on the requirements of the water consumption
equipment for water volume, water pressure, water temperature and water quality, and the specific conditions
of the power station. Water sources may be taken from reservoirs, penstock, power station tail water or other
water sources.
8.1.2 The technical water supply mode shall be determined according to the head range of the hydropower
station; when the minimum head is lower than 30m, the water should be supplied by pump; when the net
head is 30m to 100m, the water should be supplied by automatic flowing or automatic flowing with pressure
reduction; when the net head is higher than 100m, the water should be supplied by automatic flowing with
pressure reduction and others.

8.1.3 The technical water supply system shall be able to be operated automatically.

8.1.4 The water for the main shaft seal of the turbine should be provided with the standby water source
which could be put into use automatically.

8.1.5 When the water is supplied by pump, it is necessary to provide the standby water pump.

8.1.6 The technical water supply system shall be equipped with the water filter. When the water filter is
filtering the dirt, the water supply for the system shall not be interrupted. The quality of the water used for

SHP/TG 002-6-1: 2019 21


Technical Guidelines for the Development of Small Hydropower Plants – Design

the bearing lubrication and main shaft sealing shall meet the requirements for cleanliness for the desired
use.

8.1.7 The water drainage for unit overhaul (dewatering) and for leakage in the power plant should be
realized with separate but interconnected drainage systems. Two drainage pumps shall be installed for the
maintenance of the unit, and the total displacement shall be guaranteed to exclude the total displacement
of one unit for maintenance within 4h to 6h. There shall be no less than two drainage pumps for the water
collecting well in the plant, one of which is standby, and the drainage pump shall be automatically controlled
according to the change in water level of the water collecting well.

8.1.8 The outdoor drainage system in the plant area shall be an independent system, which shall not feed
water into the water-collecting well or the water-collecting gallery in the plant.

8.1.9 Power station leakage and drainage shall not be directly discharged into the river without treatment.

8.2 Oil system


8.2.1 The hydropower station should be equipped with the independent turbine oil system, and equipped
with oil handling and storage equipment.

8.2.2 Insulation oil system for the hydropower station may not be necessary.

8.2.3 The volume of the turbine oil tank shall meet the requirements for oil storage, oil replacement during
overhaul and oil purification. The volume of the turbine oil tank should be 110% of the oil consumption of
the unit with maximum capacity.

8.2.4 The oil treatment equipment shall include the oil pump and oil purification equipment. Their types,
capacity and quantity shall be determined according to the oil consumption of the hydropower station.

8.2.5 A central oil service system should be established for the cascade hydropower stations or a group of
hydropower stations. The central oil service system shall be equipped with the oil storage, oil treatment and
oil purification equipment. The configuration of the oil system for the hydropower station equipped with
central oil service system shall be simplified.

8.3 Compressed air system


8.3.1 The medium pressure and low pressure compressed air system may be established in the powerhouse
according to the requirement of the hydropower station.

8.3.2 The pressure of the medium pressure air compressor system for the inflation of the oil pressure supply
unit shall be determined according to the rated operating pressure of the oil pressure supply unit; two air
compressors shall be provided, one for use and one for standby and one air tank shall be provided. The
volume of the air tank may be determined according to the air compensation for the pressure oil tank. The
rated operating pressure of the air tank should be 0.2MPa to 0.3MPa higher than the rated operating pressure
of the pressure oil tank. The air tank shall be fitted with the safety valve, pressure gauge and blow-down valve
and the condensate removal arrangement.

8.3.3 The pressure of the low pressure air compressor system for the braking, overhaul and maintenance of
the unit as well as the sealing of the shroud ring of the turbine main shaft and the sealing ring of the butterfly
valve shall be 0.7MPa to 0.8Mpa; the braking air for the unit shall meet the following requirements:

a) The braking air system of the unit shall be equipped with the special air tank and the air supply pipeline
for the braking air system of the unit;

22 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

b) The total volume of the air tank for unit braking shall be determined according to the total air consumption
of the units to be braked at the same time;

c) The capacity of the air compressor shall be determined as per the air consumption of the units to be
braked at the same time and the time for resuming the operating pressure of the air tank. The time for
resuming the operating pressure of the air tank may be10min to 15min;

d) The braking air of the unit shall be supplied with the standby air compressor or other standby air source
in addition to supply from the air compressor.

8.4 Hydraulic monitoring system


8.4.1 The hydraulic monitoring system shall meet the requirements for safe, reliable and economic operation
and automatic control of the turbine generator.

8.4.2 The hydropower station should be provided with the conventional measurement items including
the upstream water level, downstream water level, surge-chamber water level, hydropower station head,
pressure difference between the front and back of the trashrack reservoir as well as the reservoir water
temperature. The unit should be provided with pressure at the intake of the spiral casing, the head cover
pressure, the pressure at the intake of the draft tube as well as the cooling water pressure of the unit, while
the selective measurement items may be provided as well, such as the flow passing through the unit, the
pressure fluctuation of the turbine, the unit efficiency, unit vibration, unit throw and the pressure (vacuum)
in the draft tube.

8.4.3 The hydraulic monitoring system shall be designed and arranged in combination with the automatic
monitoring system of the hydropower station for the purpose of the optimal generating by the hydropower
station.

8.5 Selection of the lifting equipment


8.5.1 The main powerhouse of the hydropower station shall be equipped with the crane or other lifting
equipment. Single-trolley or double-trolley bridge cranes may be used. The type and rated lifting capacity
of the crane shall be determined according to the total weight of the heaviest object to be lifted plus the
lifting tools, and with reference to the standards for the crane series. The span of the crane may be selected
according to the standard span for the crane and power station dimensions. The lifting height and speed of
the crane shall meet the requirement for installation and overhaul.
8.5.2 The hydropower station having the GIS room shall be equipped with the crane for the installation and
overhaul of the GIS room.

8.6 Heating and ventilation


8.6.1 The heating and ventilation patterns of the hydropower station shall be determined according to the
local meteorological conditions, the powerhouse type and the requirements of the production places for the
air parameter and shall comply with the relevant provisions in the country.

8.6.2 The main machine hall of the surface powerhouse, the erection bay and the auxiliary powerhouse
should employ natural ventilation. When the indoor air parameter requirements could not be met by natural
ventilation, the combination of natural ventilation and mechanical ventilation, mechanical ventilation and
local air conditioning may be adopted.

SHP/TG 002-6-1: 2019 23


Technical Guidelines for the Development of Small Hydropower Plants – Design

8.6.3 If the generator is ventilated through the pipeline, the hot air shall be led out of the powerhouse.

8.6.4 The oil tank room and the oil treatment room shall be equipped with separate ventilation systems. The
air outlets of the ventilation system shall be 1.5m higher than the roof.

8.6.5 The ventilation rate of the GIS room shall be 8 times/hr., and the air inlet shall be set in the lower part
of the room.

8.6.6 The heating device shall be equipped when the indoor temperature of the main and auxiliary
powerhouses is lower than 5℃.

8.6.7 Necessary ventilation facilities shall be installed in the gallery at the bottom of the dam.

8.7 Allocation of maintenance equipment for the electro-mechanical equipment


8.7.1 The turbine maintenance equipment shall be selected according to the overhaul work on the
electromechanical equipment, the connectivity with nearby towns and the coordination and processing
conditions of the outsourcing work.
8.7.2 The cascade hydropower stations or a group of hydropower stations should be provided with a central
repair workshop.

8.8 Schematic diagrams of typical oil, air and water systems


See Figures C.5, Figures C.6 and Figures C.7 for the schematic diagrams of typical oil, air and water systems.

9 Fire extinguishing system

9.1 Basic principle for the design of the fire extinguishing system
9.1.1 Fire protection system of the power station and unit equipment should follow the fire protection
standards of the country.

9.1.2 The fire hazards and fire resistance rating shall be classified for the buildings and structures in the
hydropower station.

9.2 Technical requirements


9.2.1 The fire lane in the plant area shall not be less than 4.0m in width and should be used as the access road
as well. The dead-end of the fire lane shall be designed with a turnaround.

9.2.2 There shall be at least two evacuation exits for the powerhouse of the hydropower station. On the
generator floor and the floors below, the distance from the farthest workplace indoors to the nearest
evacuation exit on this floor shall not exceed 60m.

9.2.3 It is necessary to provide a 100% oil storage pit or a20% oil storage pit and a common oil storage
tank for the main oil-immersed transformer with single oil capacity over 1000kg and the other oil filling
equipment.

9.2.4 The power cables and the control cables shall be laid in layers. The cables laid in layers shall be separated
with clapboards with fire endurance not less than 0.5h.

24 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

9.2.5 Every 100m of cable tunnels and ditches should be equipped with a fire-proof partition. Closure and
partition measures should be implemented for the through-wall.

9.2.6 The automatic fire extinguishing system such as water spray shall equip the generator with a unit
capacity not less than 12.5MV·A and the indoor main oil-immersed transformer with a unit capacity not less
than 12.5MV·A.

9.2.7 The powerhouse shall be equipped with smoke discharging facilities and these shall be combined with
the ventilation system.

9.2.8 The fire water for the plant area may be supplied with natural water flows, the special fire water tank
and fire water pump, and may be combined with the living and the generation water supply systems. The
water supply quality, water pressure and water volume shall meet the requirements for firefighting water
supply.

9.2.9 The firefighting apparatuses shall be powered as per the level-II load and employ the separate and
fail safe power supply loop. The control equipment for the firefighting apparatus shall be installed in the
central control room. When the water is supplied with the firefighting water pump, the starting device for the
firefighting water pump shall be set in the firefighting cabinet.

9.2.10 The emergency lighting and evacuation indication signs shall be provided in the escape route in the
powerhouse at all floors, staircases, exits and in the firefighting water pump house.

9.2.11 The automatic fire alarm shall be installed in the hydropower station.

10 Layout of the powerhouse

10.1 Basic principle for the layout of the powerhouse


The hydraulic machinery and the electrical equipment should be arranged in different areas. The length and
width of the unit section of the main powerhouse shall be determined according to the dimensions of the
unit as well as the passageway, governor, oil pressure supply unit, main valve and electrical panel/cabinet,
and in combination with the requirements for the installation, overhaul, operation, transportation and civil
engineering design. The width of the main powerhouse shall also meet the requirement for the dimensions of
the components to be lifted by the crane and the dimensions of the main valve. The layout of the powerhouse
shall be designed with full consideration given to the requirements for ecology and environmental protection.

10.2 Technical requirements


10.2.1 The lifting height in the main powerhouse shall meet the following requirements:

a) The requirement for the integral lifting of the generator rotor together with the shaft;

b) The requirements for assembling the turbine and the shaft sleeve and for integral lifting;

c) The requirement to send the main transformer to the factory for overhaul if necessary;

d) The requirement to turn over the components like the water distributor for the bulb tubular unit;

e) The distance between components lifted by the crane and the fixed object shall not be less than 0.3m in
the vertical direction nor be less than 0.4m in the horizontal direction.

SHP/TG 002-6-1: 2019 25


Technical Guidelines for the Development of Small Hydropower Plants – Design

10.2.2 The surface area of the erection bay shall be determined according to the demand for the expanded
overhaul of one of the unit-main components of the unit shall be arranged within the working scope of the
crane hook and meet the following requirements:

a) Requirement of the sequence for lifting large pieces in the installation and overhaul process;

b) Net distance between the large pieces of the unit as well as between big pieces and wall (column) or fixed
equipment shall be 0.8m to 1.0m;

c) The requirement for vehicles coming into the plant for the loading and unloading of the components shall
be met;

d) The turbine oil room may be set up in the powerhouse while the insulation oil tank maybe set up outside
the powerhouse and the oil treatment room shall be arranged near the oil tank room;

e) Other auxiliary machinery shall be arranged for the convenience of the installation, operation, overhaul
and maintenance of the equipment.

26 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

Appendix A
(Normative)
Reference formula for the basic parameter calculation for the
reaction turbine

A.1 Calculation of the rated discharge

Qr = Q1'r D12 Hr
........................................................................(A.1)

where

Qr is the rated discharge, in m3/s;

Q'1r is the unit discharge under the rated working condition, in m3/s;

Hr is the rated head, in m;

D1 is the nominal diameter of the runner, in m;

A.2 Calculation of the draft height and determination for setting the elevation of
the turbine

A.2.1 See formula (A.2) for the calculation of the draft height


Hs  10   K   mH
900 .............................................................(A.2)
where

Hs is the draft height, in m;

Kσ is the ratio of device cavitation coefficient to model cavitation coefficient;

σm is the cavitation coefficient of the turbine model;

H is the turbine head, in m.

Usually it may be calculated as per rated head; for the minimum head of the axial-flow turbine as well as the
maximum head and corresponding σm of the Francis turbine shall be verified.

A.2.2 See formula (A.3) for setting the elevation of the vertical-shaft Francis turbine.

b0
  w  Hs 
2 .....................................................................(A.3)
where

▽ is the setting elevation, in m;

▽w is the tailwater level, in m;

b0 is the guide vane height, in m.

SHP/TG 002-6-1: 2019 27


Technical Guidelines for the Development of Small Hydropower Plants – Design

A.2.3 See formula (A.4) for setting the elevation of the vertical-shaft axial-flow turbine.

  w  Hs  xD1
....................................................................(A.4)

where

x is the height efficiency of the axial-flow turbine.

A.2.4 See formula (A.5) for setting the elevation of the horizontal-shaft reaction turbine.

D1
  w  H s 
2 .......................................................................(A.5)

A.3 Reaction turbine efficiency and correction calculation

A.3.1 See formulas (A.6) and (A.7) for the calculation of the prototype turbine efficiency


T  M △ .............................................................................(A.6)

△   T max  M max ......................................................................(A.7)


where

M is the model turbine efficiency;

  is the corrected value for turbine efficiency;

T max is the maximum efficiency of the prototype turbine;

M max is the maximum efficiency of the model turbine.

In addition to the calculation according to the reference formulas listed in A.3.2 to A.3.4 below, the efficiency
correction of the turbine should also take into account the correction caused by the abnormal components
and the process deviation between the prototype and the model turbines. When the diameter of the runner
is less than 1 m, it should be negatively corrected.

A.3.2 For the first method for the turbine efficiency correction, see formulas (A.8) and (A.9).

Francis:
0.2
 D  
△  K (1   M max ) 1  
 1M   ........................................................(A.8)
  D1  

Axial-flow:
0.2 0.1
  D1M   HM  
△  K (1   M max ) 0.7  0.7
     .......................................(A.9)
  D1   HP  

28 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

where

K  is the coefficient, K=0.5-0.7 (low value is for the retrofitted unit and the high value is for the
new unit);

D1m is the runner diameter of the model turbine, inm;

Hm is the test head of the model turbine, in m;

HP is the head of the prototype turbine, in m.

A.3.3 For the second method for the turbine efficiency correction, see formulas (A.10) and (A.11).

Calculation formula for the efficiency correction of the reaction turbine recommended in IEC60193:

0.16 0.16
 Re   Reuref  
 uref
△b   ref 
   
 Re  Re  
 um   up   ............................................... (A.10)

1  bopt m
 r ef  0. 16
 Reur ef  1  Vr ef
  
 Reuopt m  Vr ef
..................................................... (A.11)

where

△  b is the corrected value converted from the model efficiency to the prototype efficiency;

δref is the corrected value converted from the nominal value to the prototype efficiency;

Reuref is the standard Reynolds number;

Reum is the model Reynolds number at the calculating point;

Reup is the prototype Reynolds number at the calculating point;

Reuoptm is the reynolds number at the optimum efficiency point of the model;

ηboptm is the optimum efficiency of the model;

Vref  is the standard loss distribution coefficient (0.8 for the Kaplan turbine, 0.7 for the Fancis
and the fixed blade propeller turbines).

SHP/TG 002-6-1: 2019 29


Technical Guidelines for the Development of Small Hydropower Plants – Design

A.3.4 The third method for the turbine efficiency correction

As for the existing model test curve, the model test data of the Reynolds number and the water temperature,
the efficiency correction may be calculated by the formulas (A.12-14):

  Re 0.16 
△b  (1  boptm )Vm 1  
  um  
 Re  
  up   .................................................. (A.12)

Vm = Vopt m = Vr ef
..................................................................... (A.13)

Reum  Reuref  7 106


............................................................... (A.14)

where

Vm is the oss distribution coefficient of the model;

Voptm is the oss distribution coefficient at the optimum efficiency point of the model.

A.4 Calculation of the rated power


NTr  9. 81Qr H r Tr
.................................................................. (A.15)

where

NTr is the rated power of the turbine, in kW;

ηTr is the prototype turbine efficiency under rated condition.

A.5 Calculation of the maximum runaway speed


The maximum runaway speed of the Francis or the fixed blade propeller turbine shall be determined according
to the maximum head and the maximum unit speed. The maximum runaway speed of the Kaplan turbine
shall be calculated under the condition that the coordination relationship is maintained; in case of any special
requirements, it may be calculated on the assumption that the coordination relationship is broken.

H max
nf max
 n1'f max
D1
................................................................ (A.16)

where

nfmax is the maximum runaway speed, in r/min;

n’1fmax is the maximum unit runaway speed, in r/min;

Hmax is the maximum head, in m.

30 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

A.6 Estimation of the axial hydraulic thrust

 2
Pz  K z D1 H max (kN ) .............................................................. (A.17)
4
where

Pz is the is the axial hydraulic thrust, in kN;

Kz is the is the axial hydraulic thrust coefficient; to be obtained as per the relevant experimental
parameters.

SHP/TG 002-6-1: 2019 31


Technical Guidelines for the Development of Small Hydropower Plants – Design

Appendix B
(Normative)
Reference formula for the basic parameter calculation of the
impulse turbine

B.1 Calculation of the jet diameter

Qsj
d 0  545
K p Z 0 Hsj ................................................................(B.1)

Nf
Qsj 

9. 81Hsj T f .....................................................................(B.2)

where

d0 is the jet diameter, in mm;

Qsj is the turbine discharge under the design condition, in m3/s;

Kp is the number of runners;

Z0 is the number of nozzles per runner;

ηT is the prototype turbine efficiency under the design condition;

ηf is the generator efficiency.

B.2 Calculation of the rated speed

ns Hs1.j 25 ns Hs1.j 25 ns 1Hs1.j 25


nr   
NTr K p Z 0N1 N1
...............................................(B.3)

ns
ns 1 =
K pZ 0
............................................................................(B.4)

NTr
N1 =
K pZ 0
..............................................................................(B.5)

where

ns is the specific speed of the turbine, in m·kW;

ns1 is the specific speed of the single nozzle, in m·kW;

N1 is the output of the single nozzle, in kW.

32 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

B.3 Calculation of the runner diameter and value m

(39 ~ 40) H sj
D1 
nr .....................................................................(B.6)

D1
m=

d 0 ...................................................................................(B.7)

where

D1 is the pitch diameter of the bucket, in m;

m is the ratio of the runner diameter to the jet diameter, non-dimensional.

For ensuring the relatively higher efficiency of the turbine, the value m should be within the range of 10 to 20.
Low value applies to the low head while the high value applies to the high head.

B.4 Estimation of the nozzle diameter and the number of buckets

d p = (1.15 ~ 1.25)d 0
.....................................................................(B.8)

D1
Z 1  6. 67 0
d0
.........................................................................(B.9)

where

dp is the nozzle diameter, in mm;

Z1 is the number of buckets.

B.5 Calculation of the draining height


B.5.1 The draining height refers to the height for the ensuring safe and stable operation of the Pelton turbine,
avoiding surge in case of load variation, guaranteeing the ventilation and preventing the energy losses due to
the vortex and flow splash in the tailrace.

B.5.2 When determining the draining height, it is necessary to ensure the necessary ventilation height which
should not usually be less than 400mm.

B.5.3 Calculation of the draining height, see formula (B.10)

h p  (1.0 ~ 1.5) D1
..................................................................... (B.10)

where

hp is the draining height, m; high value is for the vertical shaft unit and the low value is for the
horizontal shaft unit.

SHP/TG 002-6-1: 2019 33


Technical Guidelines for the Development of Small Hydropower Plants – Design

B.6 Calculation of the setting elevation

B.6.1 The setting elevation shall be determined according to the maximum tailwater level for power
generation. Under any power generation conditions, sufficient draining height should be kept for the tailrace.

B.6.2 For the vertical shaft Pelton turbine

  Wm  hp ........................................................................ (B.11)



where
▽Wm is the maximum tailwater level, in m.

B.6.3 For the horizontal shaft Pelton turbine

D1
  Wm  hp 
2 ................................................................. (B.12)

B.7 Calculation of the rated specific speed

nr NTr
ns r 
H r 5/ 4
....................................................................... (B.13)

where

nsr is the rated specific speed, in m·kW.

B.8 Calculation of the maximum runaway speed

70 H max
nf max

D1
.................................................................... (B.14)

where

nfmax maximum runaway speed, r/min.

B.9 Calculation of the rated power

NTr  9. 81Qr H r Tr


.................................................................. (B.15)

where

NTr is the rated power of the turbine, in kW;

ηTr is the prototype turbine efficiency under rated condition.

34 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

Appendix C
(Normative)
Reference formula for the working capacity calculation of the
governing system for some turbines

C.1 Impulse turbine

For the calculation of the operating capacity of the governing system for the impulse turbine, see formulas
(C.1) and (C.2)
d02 H max
Anz = 10Z (d0 + )
6000 ................................................................. (C.1)


Ade = 11 10 3 d 03 H max Z .................................................................. (C.2)
where

Anz is the operating capacity of the needle servomotor, in N·m;

Z is the number of nozzles;

d0 is the jet diameter of the dependable discharge (or output), in cm;

Hmax is the maximum head, in m;

Ade is the operating capacity of the deflector servomotor, in N·m.

C.2 Kaplan turbine

For the calculation of the operating capacity of the governing system for the Kaplan turbine, see formulas
(C.3) and (C.4)

Aga= K1 Q H max D1 ........................................................................ (C.3)

Aru=K2φHmaxD13............................................................................. (C.4)

where

Aga is the operating capacity of the guide vane servomotor, in N·m;

K1 is the coefficient, value range: 250 to 300;

Q is the rated discharge of the unit, in m3/s;

Hmax is the maximum head, in m;

D1 is the turbine runner diameter, in m;

Aru is the operating capacity of the blade servomotor, in N·m;

K2 is the coefficient;

φ is the intersection angle between two extreme positions of the blade, in radian.

SHP/TG 002-6-1: 2019 35


Technical Guidelines for the Development of Small Hydropower Plants – Design

When the number of blades Z=4, K2=8.0; when Z=5, K2=8.5; when Z=6, K2=9.0.

C.3 Shaft-extension tubular turbine and the bulb tubular turbine

For calculation of the operating capacity of the governing systems for the shaft-extension tubular and the
bulb tubular turbines, see formula (C.5)

A = 400Q H max D1
...................................................................... (C.5)

where

A is the operating capacity of the servomotor, in N·m;

Q is the rated discharge of the unit, in m3/s;

Hmax is the maximum head, in m;

D1 is the turbine runner diameter, in m.

C.4 Vertical unit layout

Key

1 turbine 2 generator

3 bridge crane 4 main valve

Figure C.1 - Transverse cross-section plan of the vertical unit power plant

36 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

C.5 Horizontal unit layout

Key

1 turbine

2 generator

3 bridge crane

Figure C.2- Transverse cross-section plan of the horizontal unit power plant

SHP/TG 002-6-1: 2019 37


Technical Guidelines for the Development of Small Hydropower Plants – Design

C.6 Layout of the shaft-extension tubular type turbine unit

Key

1 bridge crane 2 turbine

3 speed increaser 4 generator

5 fish guiding box of tailwater

6 curtain type regulating weir

7 energy dissipation network

Figure C.3 - Layout of the shaft-extension tubular type turbine unit

38 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

C.7 Layout of the bulb tubular turbine unit

Key

1 trash rack 2 bridge crane

3 generator 4 turbine

5 fast emergency gate

Figure C.4 - Layout of the Bulb Tubular Turbine Unit

SHP/TG 002-6-1: 2019 39


Technical Guidelines for the Development of Small Hydropower Plants – Design

C.8 Schematic diagram of the turbine oil system

Key

1 net oil tank

2 working tank

3 oil purification room

Figure C.5 - Schematic diagram of the turbine oil system

C.9 Schematic diagram of the low pressure compressed air system

Figure C.6 - Schematic diagram of the low pressure compressed air system

40 SHP/TG 002-6-1: 2019


Part 6-1: Hydraulic Machinery and Turbine Generator

C.10 Schematic diagram of the technical water supply and drainage system

Figure C.7 - Schematic diagram of the technical water supply and drainage system

SHP/TG 002-6-1: 2019 41


INTERNATIONAL NETWORK
ON SMALL HYDROPOWER
Vienna International Centre 136 Nanshan Road
P.O. Box 300 · 1400 Vienna · Austria Hangzhou · 310002 · P.R.China
Tel.: (+43-1) 26026-o Tel.: (+86-571)87132793
E-mail: info@unido.org E-mail: secretariat@inshp.org
www.unido.org www.inshp.org

You might also like