Professional Documents
Culture Documents
Practice Test Budgeting 1
Practice Test Budgeting 1
Practice Test Budgeting 1
Medium:
NPV profiles Answer: b Diff: M
19. Projects L and S each have an initial cost of $10,000, followed by a series
of positive cash inflows. Project L has total, undiscounted cash inflows
of $16,000, while S has total undiscounted inflows of $15,000. Further, at
a discount rate of 10 percent, the two projects have identical NPVs. Which
project’s NPV will be more sensitive to changes in the discount rate?
a. Project S.
b. Project L.
c. Both projects are equally sensitive to changes in the discount rate
since their NPVs are equal at all costs of capital.
d. Neither project is sensitive to changes in the discount rate, since
both have NPV profiles which are horizontal.
e. The solution cannot be determined unless the timing of the cash flows
is known.
a. The NPV and IRR methods will select the same project if the cost of
capital is greater than 10 percent; for example, 18 percent.
b. The NPV and IRR methods will select the same project if the cost of
capital is less than 10 percent; for example, 8 percent.
c. To determine if a ranking conflict will occur between the two projects
the cost of capital is needed as well as an additional piece of
information.
d. Project L should be selected at any cost of capital, because it has a
higher IRR.
e. Project S should be selected at any cost of capital, because it has a
higher IRR.
Chapter 10 - Page 7
NPV profiles Answer: d Diff: M
22. Project C and Project D are two mutually exclusive projects with normal cash
flows and the same risk. If the WACC were equal to 10 percent, the two
projects would have the same positive NPV. However, if the WACC is less
than 10 percent, Project C has a higher NPV, whereas if the WACC is
greater than 10 percent, Project D has a higher NPV. On the basis of this
information, which of the following statements is most correct?