Professional Documents
Culture Documents
IPS-MBD21907-In-510C-Data Sheet of Level Gauge (Top Mounted) - A
IPS-MBD21907-In-510C-Data Sheet of Level Gauge (Top Mounted) - A
DATA SHEET
OF
This document has been prepared for the above project or named part thereof and should not be relied upon or used for any other project without prior written consent from IPS-
Mehtalia Pvt. Ltd. IPS-Mehtalia Pvt. Ltd. accepts no responsibility or liability for the consequence of this document being used for a purpose other than the purposes for which it was
commissioned. Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be taken to confirm his agreement to indemnify IPS-
Mehtalia Pvt. Ltd. for all loss or damage resulting there from. IPS-Mehtalia Pvt. Ltd.accepts no responsibility or liability for this document to any party other than the person by
whom it was commissioned.
Cover Page
IPS-MEHTALIA PVT. LTD. Client NSCL
Consulting Engineers . Construction Management . Commissioning & Qualification Project No. MBD21907
B101-109, 1st Floor, Kailash Vaibhav Industrial Estate, Vikhroli (W), Mumbai – 400 079 Made/App. NPK/SSP
Document Title Data sheet of Level Gauge (Top Mounted) - Float & Board Type Rev A
Document No. IPS-MBD21907-IN-510C Date 15-Jul-2021
Units: Flow :- Liquid: Kg/h Gas: Nm3/h Steam:Kg/h; Pressure: Bar (g); Temperature:- °C; Level/length:- mm
3 Process Connection & Size 40 NB ,Flanged, ASA 150# ANSI B 16.5, 3 Nos.
Epoxy Painted red colored Al pointed incorporation Nylon rollers on its chases to provide frictionless movement
7 Level Indication
along with Scale Board.
8 Calibration Scale Board 6” Wide Al, epoxy painted in white color (Least Count – 5mm) and numerical in Red Color.
9 Brackets Adjustable brackets at 1 mtr intervals (common bracket for each joint)
Pulleys with PTFE bushing and SS Shafts to provide Friction Free movement and housed in Weatherproof IP65,
10 Pulley assemblies for measuring rope.
Aluminium Enclosures.
Protection conduits for measuring
11 Horizontal 1 No. Vertical 2 Nos. steel pipes, pipe size, STS
rope.
Note :-
1. STS : Supplier to Specify
2. RFS : Refer Follow Sheet.
3. Vendor to highlight deviation if any, from the above specification along with technical reason for the same.
4. Vendor to submit the catalogue along with offer.
5. Vendor to submit Mat. Test Report, Performance Test Report, Guarantees etc. in triplicate along with delivery.
6. Vendor to submit the Instrument installation manual & G.A. Drawings in hard copies 2 set.