Job Hazard Analysis (JHA) Worksheet

JERP # 3 AROMATIC UNIT

COMPANY: SAACO DATE: MAY26-31, 2012 JHA NOrev. 001


(SUBCON)
WORK DESCRIPTION: Cleaning of Pipe (Internal cleaning) using air EQUIPMENT / TOOLS USED: Air Compressor machine and Hand tools.
compressors

NAME POSITION SIGNATURE


PREPARED BY: Mr. Shon / Mr. Jo Piping Engineer
CONSTRUCTION SUPERVISOR

v. Ferrer/F. De la Cruz HSE SUPERVISOR


APPROVED BY:

Risk
Activity Order Potential Hazards Hazard Control Protective Measures
Rating
1= V/LOW
Against each step list the potential 5=V/HIGH
List the steps required to perform hazards that could cause injury For each hazard identified list the control measures required to eliminate or
the task in the sequence they area when the task is performed, name minimise the risk of injury.
carried out. tools & equipment
1. Preparation of materilas tools and *Unauthorized work 3 *Obtained safe work permit for air blowing activity.
*Correct Barrication & proper signage must be used.
2. Preparation of materials, tools *Personal Injury 2 *Total safety task instruction must be done prior to start the work.
and equipment. *Use basic and proper PPE such as proper working gloves, eye goggles, face guard
proper dust mask.
*Pre-job instruction and discussion to the members involve before starting
the air blowing activities.
*Ensure hose fittings & connectors are fitted with whiplash arrestor.
*Ispect tools and materials, equipment to be used from damages. If found eliminate
*All tools,materials, should properly color coded and compressor should have

JERP - 3/SO:2279
valid certification and documents.

JERP - 3/SO:2279
Job Hazard Analysis (JHA) Worksheet
JERP # 3 AROMATIC UNIT

Risk
Activity Order Potential Hazards Hazard Control Protective Measures
Rating
1= V/LOW
List the steps required to perform Against each step list the potential 5=V/HIGH
the task in the sequence they area hazards that could cause injury For each hazard identified list the control measures required to eliminate or
carried out. when the task is performed, name minimise the risk of injury.
tools & equipment
3. Air blowing activity *Noise Hazard 3 *Proper communication should stablished.
*Annoying interruption *Wear ear muff/ ear plug.High noise can damage your hearings.
(due to high decibles of noise)
*Unauthorized entry 3 *Supervise the blowing activity.Do not permit workers from entering inside.

*Dust, metal dust and other 3


tiny hazardous particles deff *Used Basic and proper PPE's and dust musk. Tiny Particles can cause respiratory
*Keep distance from the blowing point.
*Ensure proper hose rating and approved fittings.
*Use only crimped type clamp on hose and whiplash.
*If working in elevated area wear full body harness with 100% tie off.
*Do not work in red tag area or structures.
*Heat stress 3 *Drink plenty of water and take adequeate rest.
*Housekeeping in the working area after work completion. Cover the Pipe hole.
and put signage or barricade. Turn equipments off before leave.

SAMSUNG DATE: APPROVED:


CONSTRUCTION DEPARTMENT NAME POSITION SIGNATURE
MR. PENAFLOR Piping Engineer

MR. BUENA / MR. DAN PIPING SUPERVISOR

HSE DEPARTMENT MR. MATT / MR RALITO H.S.E. INCHARGE


COMMENTS:

JERP - 3/SO:2279
DAY SATURDAY SUNDAY MONDAY TUESDAY WEDNESDAY THURSDAY FRIDAY
DATE
TOPIC DISCUSSED
Have attended, understand and been given the opportunity to comment:

EMPLOYEE NAME SIGNATURE

JERP - 3/SO:2279
JERP - 3/SO:2279