INSTRUKSI KERJA HARIAN

DARI : DEPT. ENGINEERING TANGGAL : 30-Apr-2021


KEPADA : DEPT. PRODUKSI STRIP :
REF. :

NO. LOKASI INSTRUKSI KERJA KEBUTUHAN ALAT VOLUME KERJA


01 ORE GETTING 1 EXRT-SPM-2012 ZOOMLION 431.55 mT
1 EXRT-KKP-2001 Hyundai HX 210S 1285.55 mT
02 PIT 3 BLOK 1 LOADING ORE
4 DUMP TRUCK 1316.84 mT
03 SIDECAST/STRIPPING OB 2 EXRT-SPM-2013 CAT 320 D 1605.38 Bcm
04 ETO 1 TRIMMER 1 EXRT-KKP-2002 Hyundai HX 210S 1402.45 mT
05 PIT 3 BLOK 1 MAINTENANCE FRONT AND QUARRY 1 EXRT-SPM-2013 CAT 320 D -

06 MHR Maintenance MHR & Jalan di front 1 EXRT-KKP-2002 Hyundai HX 210S


-

NOTE:
SHIFT 1
EXRT-SPM-3002 KOBELCO BREAKDOWN Hose Travel
EXRT-SPM-3001 CAT 329 D BREAKDOWN Menunggu sparepart.
Untuk kendala maupun kegiatan diluar IKH, Tolong cantumkan pada kolom catatan pengawas PIT.

TARGET PRODUKSI ORE TARGET HAULING PIT TARGET STRIPPING OVERBURDEN


431.55 Bcm 1317 mT 1605.38 mT

Mengetahui,

Candra Kirana Andi Dadi Muh. Sarbin Suharman Herman


Koordinator Lapangan MPE Pit Controller Spv.Quality Operation
LAMPIRAN:

ORE GETTING STRIPPING WASTE (OB)


OPSI DIGGER_1
Zoomlion 61.65 Mt/Hr SIDECAST
- Brand : Zoomlion OPSI DIGGER_1
- Bucket Capacity : 0.92 Bcm CAT 320 D 114.67 Bcm/Hr
- Bucket Factor : 120% - Brand : Caterpillar
- Cycle Time : 65.00 second - Bucket Capacity : 1.14 Bcm
- Material : Saprolite Nickel - Bucket Factor : 100%
- Swell Factor : 1.34 - Cycle Time : 25.00 second
- Job Efficiency (MAV) : 85% - Material : Clay Natural bed
- Density : 1.59 - Swell Factor : 1.22
- Job Efficiency (MAV) : 85%

ORE HAULING (PIT-03 BLOK 1 to ETO A) TRIMMING ETO 1


OPSI LOADER_1 TRIMMER_1
HX 210s 183.65 Mt/Hr HX 210s 200.35 Mt/Hr
- Brand : Hyundai - Brand : Hyundai
- Bucket Capacity : 0.92 Bcm - Bucket Capacity : 0.92 Bcm
- Bucket Factor : 110% - Bucket Factor : 120%
- Cycle Time : 20.00 second - Cycle Time : 20.00 second
- Material : Saprolite Nickel - Material : Saprolite Nickel
- Swell Factor : 1.34 - Swell Factor : 1.34
- Job Efficiency (MAV) : 85% - Job Efficiency (MAV) : 85%
- Density : 1.59 - Density : 1.59
OPSI HAULER_1
Nissan Quester : 47.03 Mt/Hr
- Brand : Nissan-DT
- Vessel Capacity : 18.00 Bcm
- Vessel Factor : 61%
- Cycle Time : 18.98 Minute
Hauling Distance : 1.17 Km
Heaped Velocity : 10.00 Km/Hr
Empty Velocity : 15.00 Km/Hr
Loading Time : 4.28 Minute
Heaped Time : 7.02 Minute
Empty Time : 4.68 Minute
Dumping Time : 1.00 Minute
Positioning Time : 1.00 Minute
Delay Time : 1.00 Minute
- Job Efficiency : 85%
- Density : 1.59

Matching Fleet Factor : 102%


OPSI LOADER_1 : 1 unit
OPSI HAULER_1 : 4 unit
OPTIMASI HAULER_1 : 4 unit
PASS BUCKET PER DT : 10.91 kali
LOAD VESSEL PER DT : 17.50 mT
Catatan Pengawas :