Professional Documents
Culture Documents
Indoebtke METI Nov 24 No 2021 - Priyandaru
Indoebtke METI Nov 24 No 2021 - Priyandaru
Indoebtke METI Nov 24 No 2021 - Priyandaru
By:
Prijandaru Effendi
President of
Indonesia Geothermal Association (Inaga-API)
Presented for :
Indoebtke
• The Indonesia energy transition was designed to shift towards a more frugal energy system
based on decarbonized energy sources that are renewable, clean and safe
• As such, Government has Enacted Presidential Decree in 2014 as a National Energy blue
print for targeting the energy mix scenario in 2050 based on complimentary, not competition
• In that decree, Geothermal is targeted to share 7,2 GWH in 2025, 10 GWH in 2030 and 17
GWH in 2050. Indeed, it is a very ambitious target
• In addition, our President has made his Commitment to Paris Agreement to emission
reduction in 2030 to 29% on own efforts and to 41% with international supports. This is a
binding commitment
• Net zero emission is aimed in 2060 and still long way to go especially in meeting the share of
geothermal share as targeted
• The implementation of energy transition from fossil fuel to renewable energy would be a key
strategy of Indonesia energy development to support sustainable national development
2
Investment Opportunities
3
Country Updates of Geothermal Development
• Current installed capacity at 2,175 MW and we are still expecting additional installed
capacity of 95 MW before end of year to make total installed capacity becomes 2,270
MW
• Government drilling ‘de risking’ program has commenced. This is a program that is
intended to reduce exploration risk in order to make Geothermal tariff more
competitive
• The presence of Covid-19 pandemic delays the COD of some geothermal projects and
holding up new investment decision. We hope pandemic will be gone soon to let us
catch up what is left behind
4
Installed Capacity
Geothermal Power Total Capacity
No. Geothermal Working Area/ Location Developer/ Operator
Plant (MW)
2 Cibeureum – Parabakti, WEST JAVA Salak Star Energy Geothermal Salak, Ltd 377
6 Lahendong – Tompaso, NORTH SULAWESI Lahendong PT. Pertamina Geothermal Energy 120
12 Lumut Balai, South Sumatra Lumut Balai PT. Pertamina Geothermal Energy 55
13 Likipinangawan Muara Laboh Muara Laboh PT. Supreme Energy Muara Laboh 85
14 Sorik Marapi, North Sumatra Sorik Marapi I & 2 PT. Sorik Marapi Geothermal Power 87
TOTAL 2175.5
GREEN RUPTL 2021-2030
• Asumsi :
– Increase renewable energy portion to 51%
16.524,0
13.423,0
10.002,0
9.442,0
8.602,0
7.767,0
7.242,0 7.357,0
5.474
4.666
3.471,0 4.426
2.776,0
3.086,0 3.853 3.976
2.396,0
3.563
2.243,5 2.278,5
1.858,5 2.023,5
1.643,5 2.552 2.693
1.189,0 1.226,0 1.336,0 1.343,5 1.403,5 1.438,5
2.064 2.118 2.254 2.362
1.694 1.884
1.439
1.189 1.189 1.226 1.336 1.344 1.404
870 808
290 450 240
0 37 110 7,5 60 35 205 165 140 180 161 136 108 190 141 123
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2040 2050
Target Kapasitas Under RUEN Incremental Actual Kapasitas Terpasang RUPTL 2021 - 2030 Incremental RUPTL
(MW) (MW) (MW) (MW) (MW)
Is the Target Achievable?
• Challenge
– Tariff gap between buyer’s affordability and developer’s expected return. Buyer’s affordability is
based on its average production cost while developer’s expected return is based on economics of
the projects
– Government is still looking for best development scheme that results on frequent changes in
regulation; frequent changes in regulation creates uncertainties and risks to the investors
– Single Buyer – State Owned Utility Company and B to B negotiation. It requires patience,
determination and uncertainty when conducting negotiation
– Long lead development time. Average of project completion take around 10 years. Mostly due to
negotiation time, land acquisition and procuring permits. Lots of efforts made by Government to
accelerate the development time, especially for the permit approval process
8
Way Forward
10