Ms For Box Culverts - R3
Ms For Box Culverts - R3
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 1 of 5
Date of Rev: 21/12/2017
REVISION
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 6 of 5
Date of Rev: 21/12/2017
Prepared By Reviewed By
Signature
Date
Name R.M.Vishwakarma Umapathy G.K.
Designation Sr. Manager/ QA QC – AFCONS Sr. Manager/Planning - AFCONS
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 9 of 5
Date of Rev: 21/12/2017
Approved By:
Udai Veer Singh Date
(General Manager – AFCONS)
Approved By:
Gaetano Francesco Cassano Date
(Resident Engineer – TEAM Engineering)
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 10 of 5
Date of Rev: 21/12/2017
1. Scope:
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 11 of 5
Date of Rev: 21/12/2017
The work shall consist of placing the reinforcement & concrete in the formwork and vibrating the
concrete to produce the required structural elements of culverts (Box culverts/RUB) with
approved materials as per approved Design and Drawings. The construction shall confirm to the
specific alignment, lines and grades given in the GFC drawing.
k) Water Tank.
3. Material:
As described in methodology for form work/ reinforcement/ concrete or as per drawing and
technical specifications. All materials used in construction of box culvert shall confirm to the
requirements of British specifications. The concrete used shall be of required grade as per
drawing / technical specification and shall be as per approved design mix and shall confirm to
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 14 of 5
Date of Rev: 21/12/2017
British Technical specifications. Concrete shall be produced by batching plant of suitable capacity
& transported to site by transit mixers or by concrete mixers fitted with weigh batchers.
4. Procedure:
a) Prior to start of the work TBM shall be established jointly with the Engineer’s
representative in a location, which shall not be disturbed during the course of work.
b) Setting out of the culvert location shall be done jointly with the Engineer’s representative
as per the working drawings.
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 15 of 5
Date of Rev: 21/12/2017
c) In case of a reconstruction or widening of the culvert, part or the whole existing structure
shall be demolished. Joint measurement with the Engineer’s representative shall be
recorded before taking up this work.
The further execution procedure shall be followed as defined below:-
4.3 Concreting:
4.3.1 Base Slab:
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 17 of 5
Date of Rev: 21/12/2017
The reinforcement shall be placed in position and shuttering (Prefabricated steel) shall be
erected to exact dimensions of base slab and after due checks, base slab shall be concreted to
the top of bottom chamfer and joints shall be maintained as detailed in drawing.
b) The shuttering shall be made to support the wall & top slab and necessary care is taken to
seal the joints to avoid slurry loss from concrete through joints. The steel shall be
positioned and concreted.
c) The formwork shall be removed after due time as per norms and blemishes, if found are
made good.
d) The inlet & outlet structures, the aprons and floor protection works shall be constructed in
similar progression.
e) The surroundings shall be cleared of all surplus stocks, waste materials etc. and cleaned.
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 19 of 5
Date of Rev: 21/12/2017
f) After curing period the outside surface which comes in to contact with fill material shall be
painted two coats with bituminous paint as per specifications.
4.3.4 Curing:
Curing shall be done by sprinkling of water/curing compound.
5. Safety Measures
a) All personnel shall be provided with required PPE’s.
b) All personnel shall be provided with safety belt while working on height.
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 20 of 5
Date of Rev: 21/12/2017
g) Precautionary retro-reflective signs shall be erected & safety cones / bamboos shall be placed
in areas where this activity is being carried out by obstructing existing traffic lane.
h) Proper approach road / diversion road shall be provided.
i) Prior to start of any excavation complete information on the underground structures (such as
pipelines, electrical cable etc.) shall be obtained.
6. SITE RECORDS
Method Statement
MS/8155 /PM/05
Rev No.: R0
Work Procedure for Box culvert/RUB Page No: 22 of 5
Date of Rev: 21/12/2017