Bar Chart For Dated Action Plan 06-08-2019
Bar Chart For Dated Action Plan 06-08-2019
Project Name: Drilling of Well No. Sylhet-9 (Appraisal/Development Well), Project Code: 4205-0036
Source of Fund: GDF
Bar Chart of Dated Action Plan for Major Activities
FY: 2019-20
Sl. Activities Plan July August September October November December January February March April May June
Date
1 Contract Name: Procurement of Drilling Operation Services, signed between SGFL and BAPEX
Contract Signed on 19-12-2018
a. Mobilization, Testing and Target
Commissioning of rig &
rig equipment to Sylhet-9 Actual
b. Drilling Operation Target
(Target depth 2000 M) Actual
c. Testing and Completion Target
of Well No. Sylhet-9 Actual
d.. Rig down and Target
Demobilization Actual
2 Contract Name: Procurement of Downhole Completion Equipment, signed between SGFL and M/s. Halliburton Far East Pte Ltd., Singapore
Contract Signed on 28-10-2018
Supply of Downhole Target
Completion Equipment Actual Part shipment of materials started on 27-05-2019
3 Contract Name: Procurement of Mud Chemicals and Completion Fluids, signed between SGFL and M/s. Global Drilling Fluids and Chemicals Ltd., India
Contract Signed on 19-02-2019
Supply of Mud Chemicals Target
and Completion Fluid Actual Part shipment of materials started on 03-06-2019
4 Contract Name: Procurement of Wireline Logging Services, signed between SGFL and M/s. China Petroleum Logging Co. Ltd., China
Contract Signed on 27-02-2019
Wireline Logging Services Target
Actual
5 Contract Name: Procurement of Cement, Cement Additives, Cementation Services with Equipment, signed between SGFL and M/s. Sclumberger SEACO Inc., Republic of Panama
12 Contract Name: Procurement of Directional Drilling Services, signed between SGFL and M/s. AlMansoori Petroleum Services LLC, UAE
a. Signing of Contract Target
Actual
b. Directional Drilling Target
Services Actual
13 Contract Name: Procurement of Consultancy Services, signed between SGFL and M/s. Oryx Energy Consultants SDN BHD, Malaysia
Contract Signed on 02-02-2016
13
Sl. Activities Plan July August September October November December January February March April May June
Date
14 Contract Name: Construction of Bituminous Carpeting Road, Box Culverts, Retaining Wall and Drain, signed between SGFL and M/s. Md. Jamil Iqbal & Md. Moyenuddin (Bashi) – JV,
Sylhet.
Contract Signed on 04-11-2018
a. Construction of Road up Target
to WMMBC, Box Culverts,
Retaining Wall and Drain Actual
(Ist phase) Ongoing
15 Contract Name: Construction of Drilling Pad including Rig Foundation and Drain, signed between SGFL and M/s. Mollik Brothers Ltd., Dhaka.
Contract Signed on 21-07-2019
Construction of Drilling Pad Target
including Rig Foundation and
Drain Actual Ongoing
16 Contract Name: Supply and Installation of 2 nos. Deep Tube Well Submersible Pump, Motor, Other Accessories and Construction of Shed for Panel Board signed between SGFL and M/s.
Mohammed Eunus & Brothers (Pvt.) Ltd., Chattogram.
Contract Signed on 19-06-2019
Supply and Installation of 2 nos. Target
Deep Tube Well Submersible
Pump, Motor, Other Accessories
and Construction of Shed for
Panel Board Actual Ongoing
17 Contract Name: Construction of 1 no. Office Building Cum Ansar Shed with Security Post.
a. Signing of Contract Target
Actual
b. Handover of work site to Target
the Contractor Actual
c. Construction of 1 no. Office Target
Building cum Ansar Shed
with Security Post. Actual
Sl. Activities Plan July August September October November December January February March April May June
Date
18 Contract Name: Engineering, Procurement and Construction of 4 km Gas Gathering Pipeline.
a. Tender Preperation, Target
Invitation, Receiving
Evaluation, Approval, Actual
Issuing of NOA etc.
b. Signing of Contract Target
Actual
c. Engineering, Procurement Target
and Construction of 4 km
Gas Gathering Pipeline. Actual
নোটঃ বাপেক্স প্রদত্ত রিগ সিডিউল মোতাবেক সিলেট-৯নং কূ পের খননকাজ নভেম্বর ২০১৯ হতে শুরু হওয়ার কথা। কিন্তু ভূ মির মূল্য না পাওয়া, ভূ মির পরিমাপে ত্রুটি ইত্যাদি
নানাবিধ অভিযোগে খননস্থলের ভূ মি উন্নয়ন এবং আনুমানিক ১ (এক) কি.মি সংযোগ রাস্তা নির্মাণকাজ ভূ মি মালিকদের প্রতিবন্ধকতার কারণে ৩ (তিন) মাস বিলম্বিত
হওয়ায় রিগ ফাউন্ডেশন নির্মাণসহ অন্যান্য পূর্ত কাজ সম্পাদনেও ৩ (তিন) মাস বিলম্ব হওয়ার আশংকা দেখা দিয়েছে। উল্লেখ্য যে, রিগ ফাউন্ডেশন নির্মাণকাজ সম্প্রতি শুরু
হয়েছে এবং তা শেষ হতে আরো আনুমানিক ৪ (চার) মাস সময়ের প্রয়োজন হতে পারে। রিগ ফাউন্ডেশন নির্মাণ শেষ না হওয়া পর্যন্ত খননস্থলে রিগ মবিলাইজ করা সম্ভব হবে
না। উপরোক্ত প্রেক্ষাপটে আলোচ্য কূ প খননকাজ আগামী ফেব্রুয়ারী ২০২০ হতে শুরু হবে বিবেচনা করা হয়েছে।