Question 1
Complete
Single word that is based on experience and is derived from an agree-upon process to complete work or achive a result.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 1/13
2/26/2021 Final Exam Project Managemnt
Question 2
Complete
Single word term that defines the degree to which the project fulfills requirements.
Question 3
Complete
This term is used for a tool that is arranged according to an organization’s existing departments, units, or teams, with the project
activities or work packages listed under each department.
Comment:
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 2/13
2/26/2021 Final Exam Project Managemnt
Question 4
Complete
Please match the concepts of quality and grade with the examples.
A product with a limited number of features and many defects. Low quality and low grade.
A product with numerous features and many defects. High quality and low grade.
A product with a limited number of features but no obvious defects. Low quality and high grade.
A product with numerous features and no obvious defects. High quality and high grade.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 3/13
2/26/2021 Final Exam Project Managemnt
Question 5
Complete
Select one:
a. Prepare and submit proposals by the buyer.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 4/13
2/26/2021 Final Exam Project Managemnt
Question 6
Complete
Select one:
a. Ensuring that all change requests are acted on in a timely manner.
b. Influencing the factors that create changes to the authorized cost baseline.
d. Preventing approved changes from being included in the reported cost or resource usage.
e. Monitoring cost performance to isolate and understand variances from the approved cost baseline.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 5/13
2/26/2021 Final Exam Project Managemnt
Question 7
Complete
According to our slides, Quality Management and Pro¿ject Management understand the importance of:
Mark the one that does NOT apply.
Select one:
a. Continuous Improvement.
b. Customer Satisfaction.
c. Governance.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 6/13
2/26/2021 Final Exam Project Managemnt
Question 8
Complete
Please select the option that does NOT belong to the Project Budget Component.
Select one:
a. Activity Cost Estimates.
c. Management Reserve.
d. Contingency Reserve.
e. Control Disbursements.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 7/13
2/26/2021 Final Exam Project Managemnt
Question 9
Complete
Given that we have 20 participants in two groups, ten each. In both groups, everybody talks to a central participant (participant 10
in group 1 and 20 in group 2), but they may not exchange with each other. In the first group, only participant 10 exchanges with
group two's participant 20, and vice-versa. There are no other communication llinks.
Enter your response in this question and draw a diagram of this communications network in excel and upload it as question 9 in
the just in case.
Answer: 91
Comment:
The problem is stating that each participant in each group communicate only with the central participant, this means 9 biderectional
communications, not 45.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 8/13
2/26/2021 Final Exam Project Managemnt
Question 10
Complete
Ernesto, owner of Roboland SA is analyzing the possibility to launch his new product. In doing so he may invest in a market study
that will cost him $35,000 and/or a prototype that will cost him $25,000.
The market study will increase his chances of having a great product to 55% making a profit of $250,000 or making a profit of
$35,000 with the balance of the chances. The prototype will increase his chances of having a great product tu 52% making a profit
of $220,000 and the balance of chances will make a profit of $45,000.
In case he decides to apply both alternatives his chances of success increases to 75% with a profit of $320,000 and a profit of
$55,000 with the remaining chances.
Make sure you show all your calculations, you may use an excel spreadsheet and upload it but include all the formulas and not just
copy numbers. Do not send pictures, but you can make a diagram in you excel.
Question10_VilcacureEder.xlsx
Comment:
The market study is an investment (negative) the first outcome is positive (as you had it) and the second outcome is positive (you
considered negative as a loss, it was just a minor gain, not a loss. The same in all three cases.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 9/13
2/26/2021 Final Exam Project Managemnt
Question 11
Complete
In your project you worked with your Communications Management Matrix, please chart your Communications Management
Matrix and explain it.
Comment:
I expected to find frequent communication with the Users or Sponsors.
https://uevirtual.ue.edu.pe/moodle/mod/quiz/review.php?attempt=364172 11/13
2/26/2021 Final Exam Project Managemnt
Question 12
Complete
Roberto has a few alternative suppliers, he needs to decide which one to use, in work quality and punctuality they are similar.
Contractor 1 is Fixed Price and offering his service including materials and everything for $1,400,000.
Contractor 2 is Time and Materials, he charges $750/hr and 13% of the cost of materials, his estimate is 550 hours and a total in
materials of $800,000.
Contractor 3 is Cost Reimbursable, he charges $800/hr with an estimate of 600 hours and a total in material of $850,000.
Question12_VilcacureEder.xlsx
Comment: