Download as pdf or txt
Download as pdf or txt
You are on page 1of 80

LECTURE 6:

PROJECT
COST
MANAGEMENT

Information Systems Department IS 350D: Project Management


OBJECTIVES

 Discuss the Project Cost Management Processes.

 Understand the processes involved in cost budgeting and


preparing a cost estimate and budget for an
information technology project.

 Discuss different types of cost estimates and methods


for preparing them.

 Understand the benefits of earned value management.

Information Systems Department 2


Information Systems Department 3
WHAT IS COST MANAGEMENT?

Information Systems Department 4


What is Cost ?

Cost is a resource sacrificed or


foregone to achieve a specific
objective.

Information Systems Department 5


What is Cost ?

Cost is Something given up in


exchange.

Costs are usually measured in monetary units like


dollars.

Information Systems Department 6


WHAT IS PROJECT COST MANAGEMENT?

Project cost management includes the processes


required to ensure that the project is completed within
an approved budget.

Information Systems Department 7


PROJECT COST MANAGEMENT PROCESSES
No Process Name Description Output

1 Planning cost Involves determining the policies, Cost management plan


management procedures, and documentation that
will be used for planning, executing,
and controlling project cost.

2 Estimating Developing an approximation or Activity cost estimate, basis of


costs estimate of the costs of the resources estimate and project
needed to complete a project. document updates

3 Determining Allocating the overall cost estimate to Cost performing baseline,


the budget individual work items to establish a project document updates
baseline for measuring performance.

4 Controlling Controlling changes to the project Work performance


costs budget. measurement, project
document updates
Information Systems Department 8
PROJECT COST MANAGEMENT PROCESSES

1. Planning Cost

A cost management plan includes:


1. Level of accuracy and units of measure

 Activity cost estimates normally have rounding


guidelines, such as rounding to the nearest $100
 Each unit used in cost measurements, such as labor
hours or days, should be defined.

Information Systems Department 9


PROJECT COST MANAGEMENT PROCESSES

1. Planning Cost

A cost management plan includes:


2. Organizational procedure links
 Refer to the work breakdown structure (WBS) component used
for project cost accounting as the control account (CA).
 Each control account (CA) is often assigned a unique code
that is used in the organization’s accounting system.
 Project teams must understand and use these codes properly.

Information Systems Department 10


PROJECT COST MANAGEMENT PROCESSES

1. Planning Cost

A cost management plan includes:


3. Control thresholds
 Similar to schedule variance, costs often have a
specified amount of variation allowed before
action needs to be taken, such as ±10 percent of the
baseline cost.

Information Systems Department 11


PROJECT COST MANAGEMENT PROCESSES

1. Planning Cost

A cost management plan includes:


4. Rules of performance measurement.
 If the project uses earned value management
(EVM), the cost management plan would define
measurement rules, such as how often actual costs
will be tracked and to what level of detail.

Information Systems Department 12


PROJECT COST MANAGEMENT PROCESSES

1. Planning Cost

A cost management plan includes:


5. Reporting formats
 Describe the format and frequency of cost reports
required for the project.
6. Process descriptions
 Describe how to perform all of the cost management
processes.
Information Systems Department 13
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Not the Dilbert way

Information Systems Department 14


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Information Systems Department 15


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

16
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Information Systems Department 17


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

 Project managers must take cost estimates seriously


if they want to complete projects within budget
constraints.

 It’s important to know the types of cost estimates, how


to prepare cost estimates, and typical problems
associated with IT cost estimates.

Information Systems Department 18


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of cost estimates:

1. A Rough Order of Magnitude (ROM) estimate

2. A Budgetary estimate

3. A Definitive estimate

Information Systems Department 19


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

If we have a project with an actual cost of: $130,000

 Rough Order of Magnitude (ROM) estimate = $ 250,000

 Budgetary estimate = $ 133,000

 Definitive estimate = $ 129, 000

Information Systems Department 20


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 1. A Rough Order of Magnitude (ROM) estimate

1. A Rough Order of Magnitude (ROM) estimate:

 Provides an estimate of what a project will cost.

 Done very early in a project or even before a project

is officially started.

Information Systems Department 21


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 1. A Rough Order of Magnitude (ROM) estimate

1. A Rough Order of Magnitude (ROM) estimate:

 Actual costs could be 50% below the ROM


estimate or 100% above.

 For example, the actual cost for a project with a


ROM estimate of $120,500 could range from …..

Information Systems Department 22


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 1. A Rough Order of Magnitude (ROM) estimate

1 50% = 50/100 = 0.5


100% = 100/100 = 1

2 0.5 X 120,500 = 60250


1 X 120,500 = 120,500

3 120,500 - 60250 = 60250


120,500 + 120,500 = 241,000
Information Systems Department 23
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 1. A Rough Order of Magnitude (ROM) estimate

1. A Rough Order of Magnitude (ROM) estimate:


 Actual costs could be 50% below the ROM estimate or
100% above.

 For example, the actual cost for a project with a ROM


estimate of $120,500 could range from …..

$60,250 to $241,000
Information Systems Department 24
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 2. Budgetary Estimate

2. A Budgetary estimate:

 Used to allocate money into an organization’s


budget.

 Many organizations develop budgets at least two


years into the future.

Information Systems Department 25


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 2. Budgetary Estimate

2. A Budgetary estimate:
 The actual costs could be 10% less or 25% more
than the budgetary estimate.

 For example, the actual cost for a project with a


budgetary estimate of $120,500 could range
from…

Information Systems Department 26


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 2. Budgetary Estimate

1 10% = 10/100 = 0.1


25% = 25/100 = 0.25

2 0.1 X 120,500 = 12,050


0.25 X 120,500 = 30,125

3 120,500 - 12,050 = 108,450


120,500 + 30,125 = 150,625
Information Systems Department 27
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 2. Budgetary Estimate

2. A Budgetary estimate:
 The actual costs could be 10% less or 25% more
than the budgetary estimate.

 For example, the actual cost for a project with a


budgetary estimate of $120,500 could range
from…
$108,450 to $150,625
Information Systems Department 28
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 3. A Definitive Estimate

3. A Definitive estimate:

 Provides an accurate estimate of project costs.

 It used for making many purchasing decisions


for which accurate estimates are required and for
estimating final project costs.

Information Systems Department 29


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 3. A Definitive Estimate

3. A Definitive estimate:

 The actual costs could be 5% less or 10% more


than the definitive estimate.

 For example, the actual cost for a project with a


definitive estimate of $120,500 could range
from…

Information Systems Department 30


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 3. A Definitive Estimate

1 5% = 5/100 = 0.05
10% = 10/100 = 0.1

2 0.05 X 120,500 = 6025


0.1 X 120,500 = 12,050

3 120,500 - 6025 = 114,475


120,500 + 12,050 = 132,550
Information Systems Department 31
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates: 3. A Definitive Estimate

3. A Definitive estimate:

 The actual costs could be 5% less or 10% more


than the definitive estimate.

 For example, the actual cost for a project with a


definitive estimate of $120,500 could range from…

$ 114,475 to $ 132,550
Information Systems Department 32
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates

1. Actual cost for a Rough Order of Magnitude (ROM)


estimate of $120,500

$60,250 to $241,000
2. Actual cost for a Budgetary estimate of $120,500

$108,450 to $150,625
3. Actual cost for a Definitive estimate of $120,500
$114,475 to $132,550
Information Systems Department 33
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Types of Cost Estimates

Information Systems Department 34


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Basic tools and techniques for cost estimates:

1. Analogous or top-down estimates: use the actual cost of


a previous, similar project as the basis for estimating the
cost of the current project.
2. Bottom-up estimates: involve estimating individual work
items or activities and summing them to get a project total.
3. Parametric modeling: uses project characteristics
(parameters) in a mathematical model to estimate project
costs.
35
PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Example of Cost Estimate

Information Systems Department 36


PROJECT COST MANAGEMENT PROCESSES

2. Estimating Cost

Typical problems with IT Cost Estimates

 Estimates are done too quickly.


 Lack of estimating experience.
 Human beings are biased toward underestimation.
 Management desires accuracy.

37
PROJECT COST MANAGEMENT PROCESSES

3. Determining the Budget

Determining the project budget

Involves allocating the project cost


estimate to individual work items
over time.

Information Systems Department 38


PROJECT COST MANAGEMENT PROCESSES

3. Determining the Budget

Inputs required for cost budgeting process:


 The WBS - defines the work items.
 Cost management plan
 Scope baseline
 Activity cost estimates
 Project schedule
 Resource calendars
39
PROJECT COST MANAGEMENT PROCESSES

3. Determining the Budget

The main goal of the cost budgeting


process is to produce a cost baseline
for measuring project performance and
project funding requirements.

Information Systems Department 40


PROJECT COST MANAGEMENT PROCESSES

3. Determining the Budget

A cost baseline is a time-phased


budget that project managers use
to measure and monitor cost
performance.

Information Systems Department 41


PROJECT COST MANAGEMENT PROCESSES

3. Determining the Budget

Example of Cost Baseline

Information Systems Department 42


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Project cost control includes:


 Monitoring cost performance.
 Ensuring that only appropriate project changes
are included in a revised cost baseline.
 Informing project stakeholders of authorized
changes to the project that will affect costs.

Information Systems Department 43


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Project cost control includes:


 Several tools and techniques assist in project cost
control such as Earned Value Management
(EVM).

Information Systems Department 44


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

EVM is a project performance


measurement technique that
integrates scope, time, and
cost data.

Information Systems Department 45


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Given a cost performance baseline, project


manager and their teams can determine how well the
project is meeting scope, time, and cost goals by
entering actual information and then comparing it
to the baseline (original plan plus approved changes).

Information Systems Department 46


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Earned Value Management (EVM) involves calculating three


values for each activity or summary activity from a project’s WBS:

1. The planned value (PV)

2. The actual cost (AC)

3. The earned value (EV)

Information Systems Department 47


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Information Systems Department 48


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: An Example on Earned Value

Information Systems Department 49


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

The Planned Value (PV) also called the budget, is the portion of
the approved total cost estimate planned to be spent on an
activity during a given period.

Example
Suppose that a project included a summary activity of purchasing
and installing a new Web server. Suppose further that, according
to the plan, it would take one week and cost a total of $10,000 for
the labor hours, hardware, and software. Therefore, the planned
value (PV) for the activity that week is $10,000.

Information Systems Department 50


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

The Actual Cost (AC), is the total of direct and indirect costs
incurred in accomplishing work on an activity during a given
period.

Example
Suppose that it actually took two weeks and cost $20,000 to
purchase and install the new Web server. Assume that $15,000 of
these actual costs were incurred during Week 1 and $5,000 was
incurred during Week 2.

Information Systems Department 51


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

The Earned Value (EV), is an estimate of the value


of the physical work actually completed.
 EV is based on the original planned costs for the
project or activity and the rate at which the team is
completing work on the project or activity to date.

Information Systems Department 52


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Rate of performance (RP) is the ratio of actual work completed to


the percentage of work planned to have been completed at any
given time during the life of the project or activity.

Example
Suppose the server installation was halfway completed by the
end of week 1: the rate of performance would be 50% because
by the end of week 1, the planned schedule reflects that the task
should be 100 percent complete but only 50% of that work has
been completed.

Information Systems Department 53


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Formulas

Information Systems Department 54


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Formulas

Information Systems Department 55


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Formulas

Term Formula
Earned Value (EV) EV = PV X RP
Cost Variance (CV)
Schedule variance (SV)
CV = EV - AC
SV = EV - PV
EV
Cost Performance Index (CPI) CPI = EV ÷ AC Earned Value
Schedule Performance Index (SPI) SPI = EV ÷ PV is the KING

Information Systems Department 56


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Cost Variance (CV): EV - AC


 If cost variance is a negative number, it
means that performing the work cost more
than planned.
 If cost variance is a positive number,
performing the work cost less than planned.

Information Systems Department 57


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Schedule Variance (SV): EV - PV


 A negative schedule variance means that it
took longer than planned to perform the
work.
 A positive schedule variance means that the
work took less time than planned to perform.

Information Systems Department 58


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Cost Performance Index (CPI): EV/AC is the ratio of earned


value to actual cost.

 If CPI equals to 1 or 100%, then the planned


and actual costs are equal.
 If CPI less than 1 or less than 100%, the project
is over budget.
 If CPI greater than 1 or more than 100% , the
project is under budget.
Information Systems Department 59
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management

Schedule Performance Index (SPI): EV/PV is the ratio of earned


value to planned value.

 If SPI equals to 1 or 100%, then the project is


on schedule.
 If SPI less than 1 or less than 100%, the
project is behind schedule.
 If SPI greater than 1 or more than 100% , the
project is ahead of schedule.
Information Systems Department 60
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Rules of Thumb for Earned Value Numbers

 The Cost Performance Index (CPI) can be used to


calculate the estimate at completion (EAC), an estimated
cost of completing a project based on performance to date.
 Similarly, the Schedule Performance Index (SPI) can be
used to calculate an estimated time to complete the
project.

Information Systems Department 61


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Formulas

Information Systems Department 62


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Example of Earned Value Calculations for One Activity after 5 months

Assume:
 Planned Value (PV) = $ 42,461, Actual Costs (AC) = $48,923
 Rate of performance = 94.204%
 Budget at Completion (BAC) = $100,000
Earned Value Calculation:
EV =
CV =
SV =
CPI =
SPI =
EAC=
Information Systems Department 63
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Example of Earned Value Calculations for One Activity after 5 months

Assume:
 Planned Value (PV) = $ 42,461, Actual Costs (AC) = $48,923
 Rate of performance = 94.204%
 Budget at Completion (BAC) = $100,000
Earned Value Calculation:
EV = 0.94204 * 42,461 = 40,000
CV = 40,000 – 48,923 = - 8,923 Cost more than planned
SV = 40,000 – 42,461 = - 2,461 Took longer than planned
CPI = 40,000/48,923 = 81.761% Over budget
SPI = 40,000/42,461 = 94.204% Behind schedule
EAC=100,000/0.81761 = 122,308 Cost $22,308 more
64
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Example of Earned Value Calculations for One Activity after 5 months

Assume:
 Planned Value (PV) = $ 42,461, Actual Costs (AC) = $48,923
 Rate of performance = 94.204%
 Budget at Completion (BAC) = $100,000
Earned Value Calculation:
EV = 0.94204 * 42,461 = 40,000
CV = 40,000 – 48,923 = - 8,923 Cost more than planned
SV = 40,000 – 42,461 = - 2,461 Took longer than planned
CPI = 40,000/48,923 = 81.761% Over budget
SPI = 40,000/42,461 = 94.204% Behind schedule
EAC=100,000/0.81761 = 122,308
Cost $22,308 more 65
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Example of Earned Value Calculations for One Activity after 5 months

Assume:
 Planned Value (PV) = $ 14,000, Actual Costs (AC) = $13,000
 Rate of performance = 95%
 Budget at Completion (BAC) = $100,000
Earned Value Calculation:
EV =
CV =
SV =
CPI =
SPI =
EAC=
Information Systems Department 66
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Example of Earned Value Calculations for One Activity after 5 months

Assume:
 Planned Value (PV) = $ 14,000, Actual Costs (AC) = $13,000
 Rate of performance = 95%
 Budget at Completion (BAC) = $100,000
Earned Value Calculation:
EV = 14,000 * 0.95 = 13,300
CV = 13,300 – 13,000 = 300 Cost Less than planned
SV = 13,300 – 14,000 = -700 Took longer than planned
CPI = 13,300/13,000 = 1.02 Under budget
SPI = 13,300/14,000 = 0.95 Behind schedule
EAC= 100,000/1.02 = 98,039.22 Cost $1,960 less
67
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Example of Earned Value Calculations for One Activity after 5 months

Assume:
 Planned Value (PV) = $ 14,000, Actual Costs (AC) = $13,000
 Rate of performance = 95%
 Budget at Completion (BAC) = $100,000
Earned Value Calculation:
EV = 14,000 * 0.95 = 13,300
CV = 13,300 – 13,000 = 300 Cost Less than planned
SV = 13,300 – 14,000 = -700 Took longer than planned
CPI = 13,300/13,000 = 1.02 Under budget
SPI = 13,300/14,000 = 0.95 Behind schedule
EAC= 100,000/1.02 = 98,039.22 Cost $1,960 less
68
PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Information Systems Department 69


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Information Systems Department 70


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Information Systems Department 71


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Information Systems Department 72


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Information Systems Department 73


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Information Systems Department 74


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Planned value (PV), the cumulative planned amounts for all


activities by month. Note that the planned value line extends for
the estimated length of the project and ends at the BAC point.

Actual cost (AC), the cumulative actual amounts for all


activities by month.

Earned value (EV), the cumulative earned value amounts for all
activities by month.

Information Systems Department 75


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

Information Systems Department 76


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

 Budget at completion (BAC), the original total budget for the


project, or $100,000 in this example. The BAC point is plotted
on the chart at the original time estimate of 12 months.

 Estimate at completion (EAC), estimated to be $122,308 in


this example. This number is calculated by taking the BAC, or
$100,000 in this case, and dividing by the CPI, which was
81.761%.

Information Systems Department 77


PROJECT COST MANAGEMENT PROCESSES

4. Controlling Costs

Earned Value Management: Earned Value Chart

 The EAC point is plotted on the chart at the estimated time to


complete of 12.74 months.

 This number is calculated by taking the original time


estimate, or 12 months in this case, and dividing by the SPI:
which in this example was 94.204%.
𝑶𝒓𝒊𝒈𝒊𝒏𝒂𝒍 𝒕𝒊𝒎𝒆 𝒆𝒔𝒕𝒊𝒎𝒂𝒕𝒆
𝑬𝒔𝒕𝒊𝒎𝒂𝒕𝒆𝒅 𝒕𝒊𝒎𝒆 𝒕𝒐 𝒄𝒐𝒎𝒑𝒍𝒆𝒕𝒆 =
𝑺𝑷𝑰

Information Systems Department 78


In Class Activity

Information Systems Department 79


REFERENCE

 Schwalbe, K. Information Technology


Project Management (8th Edition).
Chapter 7.

Information Systems Department 80

You might also like