2 National Transmission Vs Alphaomega

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Equipment for Quiot Substation Project (Quiot Substation TRANSCO, for its part, contended that: (a) it had

a) it had conducted
Project).
5
Detailed Engineering prior to the conduct of the bidding; and
(b) it had obtained the necessary government permits and
Republic of the Philippines endorsements from the affected LGUs. It asserted that AIC
In the course of the performance ofthe contracts, AIC
SUPREME COURT was guilty of frontloading– that is,collecting the bulk of the
encountered difficulties and incurred losses allegedly due to
Manila contract price for work accomplished at the early stages of
TRANSCO’s breach of their contracts, prompting it to
the project and then abandoning the later stagesof the
surrender the projects to TRANSCO under protest. In
project which has a lower contract price –and that it
9

SECOND DIVISION accordance with an express stipulation in the contracts that


disregarded the workable portions of the projects not
disagreements shall be settled by the parties through
affected by the lack of supplies and drawings. TRANSCO
arbitration before the CIAC, AIC submitted a request for
G.R. No. 184295 July 30, 2014 further argued that AIC was estopped from asking for
arbitration before the CIAC on August 28, 2006, and,
standby fees to cover its overhead expenses during project
thereafter, filed an Amended Complaint against TRANSCO
suspensions considering that the delays, such as the
NATIONAL TRANSMISSION CORPORATION, Petitioner, alleging that the latter breached the contracts by its failure
unresolved right-of-way issues and non-availability of
vs. to: (a) furnish the required Detailed Engineering; (b) arrange
materials, were factors already covered by the time
ALPHAOMEGA INTEGRATED a well-established right-of-way to the project areas; (c)
extensions and suspensions of work allowed under the
CORPORATION, Respondent. secure the necessary permits and clearances from the
contracts. 10

concerned local government units (LGUs); (d) ensure a


continuous supply of construction materials; and (e) carry
DECISION out AIC’s requests for power shut down. The aforementioned On April 18, 2007, the CIAC Arbitral Tribunal rendered its
transgressions resultedin protracted delays and contract Final Award in CIAC Case No. 21-2006 ordering the
11

PERLAS-BERNABE, J.: suspensions for each project, as follows:


6
payment of actual and compensatory damages which AIC
would not have suffered had it not been for the project
delays attributable to TRANSCO. It found ample evidence to
Assailed in this petition for review on certiorari are the
1
support the claim for the increase in subcontract cost in
Contract Original Duration of Percentage
Decision dated April 8, 2008 and the Resolution dated
2 3
BTRP Schedule I, as well as such items of cost as house
Contract Transco- (%)
August 27, 2008 of the Court of Appeals (CA) in CA-G.R. SP and yard rentals, electric bills, water bills, and maintained
Duration Approved of Original
No. 99454 affirming with modification the Final Award of the
4
personnel, but disallowed the claims for communications
Suspension Contract
Construction Industry Arbitration Commission (CIAC) Arbitral bills, maintenance costs for idle equipment, finance charges,
and/or Duration
Tribunal in favor of respondent Alphaomega Integrated and materials cost increases. According to the Arbitral
Extensions 12

Corporation (AIC) by increasing petitioner National· Tribunal, even if AIC itself made the requests for contract
Transmission Corporation's (TRANSCO) liability from Pl time extensions, this did not bar its claim for damages as a
1) BTRP 560 711 days 127%
7,495,117.44 to Pl 8,896,673.31. result of project delayssince a contrary ruling would allow
Schedule III days
TRANSCO to profit from its own negligence and leave AIC to
The Facts 2) BTRP 270 406 days 170% suffer serious material prejudice as a direct consequence of
Schedule I days that negligence leaving it without any remedy at law. The 13

Arbitral Tribunal upheld AIC’s right to rescind the contracts in


AIC, a duly licensed transmission line contractor, 3) Makban 365 452 days 124% accordancewith Resolution No. 018-2004 of the Government
participated in the public biddings conducted by TRANSCO Substation days Procurement Policy Board (GPPB), which explicitly gives the
and was awarded six ( 6) government construction projects, contractor the right to terminate the contract if the works are
namely: (a) Contract .for the Construction & Erection of 4) Bacolod 360 289 days 80% completely stopped for a continuous period of at least 60
Batangas Transmission Reinforcement Project Schedule III Substation days calendar days, through no fault of its own, due to the failure
(BTRP Schedule III Project); (b) Contract for the of the procuring entity to deliver within a reasonable time,
Construction & Erection of Batangas Transmission 5) Bunawan 330 130 days 39% supplied materials, right-of-way, or other items that it is
Reinforcement Project Schedule I (BTRP Schedule I Substation days obligated to furnish under the terms of the contract, among
Project); (c) Contract for the Construction,Erection & others. The dispositive portion of the Arbitral Tribunal’s
14

Installation of 230 KV and 69 KV S/S Equipment and Various 6) Quiot 300 131 days 44% Final Award reads:
Facilities for Makban Substation under the Batangas Substation days
Transmission Reinforcement Project (Schedule II) (Makban 2119 days 7

Substation Project); (d) Contract for the Construction, WHEREFORE, Respondent, National Transmission
Erection & Installation of 138 & 69 KV S/S Equipment for Corporation [TRANSCO] is hereby ordered to pay Claimant,
Bacolod Substation under the Negros III-Panay III Alphaomega Integrated Corporation, the following sums:
AIC prayed for judgment declaring all six (6) contracts
Substation Projects (Schedule II) (Bacolod Substation rescinded and ordering TRANSCO to pay, in addition to
Project); (e) Contract for the Construction, Erection & what had already been paid under the contracts, moral
Installation of 138 & 69 KV Substation Equipment for the (a) For BTRP Schedule III - ₱6,423,496.67
damages, exemplary damages, and attorney’s fees at
New Bunawan Switching Station Project (Bunawan ₱100,000.00 each, and a total of ₱40,201,467.19 as actual
Substation Project); and (f) Contract for the Construction, (b) For BTRP Schedule I - 5,214,202.30
and compensatory damages. 8

Erection & Installation of 138 and 69 KV Substation

1
not only in part but in their entirety, thus, permitting no work raise only questions of law which must be distinctly set
(c) For Makban Substation - 3,075,870.95
activity at all during such periods.
25
forth." Dynamic’s contention is valid topoint as, indeed, the
matters raised by Hanjin are factual, revolving as they do on
(d) For Bacolod Substation - 1,362,936.77
the entitlement of Dynamic to the awards granted and
The CA upheld the Arbitral Tribunal’s Final Award as having
computed by the CIAC and the CA. Generally, this would be
(e) For Bunawan Substation - 820,481.72 been sufficiently established by evidence but modified the
a question of fact that this Court would not delve upon.
total amount of the award after noting a supposed
(f) For Quiot Substation - 598, 129.03 Imperial v. Jauciansuggests as much. There, the Court ruled
mathematical error in the computation. Setting aside
that the computation of outstanding obligation is a question
TRANSCO’s objections, it ruled that when a case is brought
TOTAL ₱17,495,117.44 of fact:
to a superior court on appeal every aspect of the case is
thrown open for review, hence, the subject error could be
26

rectified. The CA held that the correct amount of the award Arguing that she had already fully paid the loan x x x,
Each Party shall shoulder its own cost of arbitration. should be ₱18,896,673.31, and not ₱17,495,117.44 as petitioner alleges that the two lower courts misappreciated
stated in the Arbitral Tribunal’s Final Award. Dissatisfied,
27
the facts when they ruled that she still had an outstanding
TRANSCO moved for reconsideration but was, however,
28
balance of ₱208,430.
The foregoing amount of ₱17,495,117.44 shall earn interest
denied by the CA in a Resolution dated August 27, 2008,
29

at the rate of six percent (6%) per annum from the date of
hence, the instant petition.
promulgation of this Final Award until it becomes final and This issue involves a question of fact. Such question exists
executory. Thereafter, the Final Award, including accrued when a doubt or difference arises as to the truth or the
interest, shall earn interest at the rate of 12% per annum The Issues Before the Court falsehood of alleged facts; and when there is need for a
until the entire amount due is fully paid. (Emphasis 15
calibration of the evidence, considering mainly the credibility
supplied) of witnesses and the existence and the relevancy of specific
The essential issues for the Court’s consideration are
surrounding circumstances, their relation to each other and
whether or not the CA erred (a) in affirming the CIAC Arbitral
to the whole, and the probabilities of the situation. (G.R. No.
Unconvinced, TRANSCO instituted a petition for review with 16
Tribunal’s findings that AIC was entitled to its claims for
149004, April 14, 2004, 427 SCRA 517, 523-524.)
the CA. damages as a result of project delays, and (b) in increasing
the total amount of compensation awarded in favor of AIC
despite the latter’s failure to raise the allegedly erroneous The rule, however, precluding the Court from delving on the
Before filing its comment to the petition, AIC moved for the
17

computation of the award before the CIAC in a timely factual determinations of the CA, admits of several
issuance of a writ of execution, not for the amount of
18

manner, that is, within fifteen (15) days from receipt of the exceptions. In Fuentes v. Court of Appeals, we held that the
17,495,117.44 awarded in the Final Award, but for the
Final Award as provided under Section 17.1 of the CIAC findings of facts of the CA, which are generally deemed
increased amount of 18,967,318.49. It sought correction of
19

Rules. conclusive, may admit review by the Court in any of the


the discrepancies between the amount of the award
following instances, among others:
appearing in the dispositive portion and the body of the
20

Final Award. The Arbitral Tribunal, however, denied AIC’s


21
The Court’s Ruling
motion, holding that while the CIAC Revised Rules of (1) when the factual findings of the [CA] and the
Procedure Governing Construction Arbitration (CIAC Rules) trial court are contradictory;
TRANSCO seeks through this petition a recalibration of the
would have allowed the correction of the Final Award for
evidencepresented before the CIAC ArbitralTribunal,
evident miscalculation of figures, typographical or
insisting that AIC is not entitled to any damages not only (2) when the findings are grounded entirely on
arithmetical errors, AIC failed to file its motionfor the purpose
because it had previously waived all claims for standby fees speculation, surmises, or conjectures;
within the time limitation of 15 days from its receipt of the
in case of project delays but had eventually failed to perform
Final Award. 22

the workable portions of the projects. This is evidently a


(3) when the inference made bythe [CA] from its
factual question which cannot be the proper subject of the
findings of fact is manifestly mistaken, absurd, or
The CA Ruling present petition. Section 1, Rule 45 of the Rules of Court
impossible;
provides that a petition for review on certiorariunder the said
rule, as in this case, "shall raise only questions of law which
In the Decision dated April 8, 2008, the CAaffirmed the
23

must be distinctly set forth." Thus, absent any of the existing (4) when there is grave abuse of discretion in the
Arbitral Tribunal’s factual findings that TRANSCOfailed to
exceptions impelling the contrary, the Court is, as a general appreciation of facts;
exercise due diligence in resolving the problems regarding
rule, precluded from delving on factual determinations, as
the right-of-way and the lack of materials before undertaking
what TRANSCO essentially seeks in this case. Similar to the
the bidding process and entering into the contracts with (5) when the [CA], in making its findings, goes
foregoing is the Court’s ruling in Hanjin Heavy Industries and
AIC. It found no merit in TRANSCO’s allegation that AIC
24
beyond the issues of the case, and such findings
Construction Co., Ltd. v. Dynamic Planners and Construction
refused to perform the remaining workable portions of the are contrary to the admissions of both appellant
Corp., the pertinent portions ofwhich are hereunder quoted:
30

projects not affected by problems of right-of-way, shutdowns, and appellee;


supplies and drawings, firstly, because the certificates
ofaccomplishments issued by TRANSCO in the course of Dynamic maintains that the issues Hanjin raised in its
project implementation signifying its satisfaction with AIC’s (6) when the judgment of the [CA] is premised on
petitions are factual in nature and are, therefore, not proper
performance negate such claim and, secondly, because all a misapprehension of facts;
subject of review under Section 1 of Rule 45, prescribing that
the orders issued by TRANSCO suspended the contracts a petition under the said rule, like the one at bench, "shall

2
(7) when the [CA] fails to notice certain relevant within fifteen (15) days from receipt thereof upon any of the may not obtain any affirmative relief from the appellate court
facts which, if properly considered, will justify a following grounds: other than what he had obtained from the lower court, if any,
different conclusion; whose decision is brought up on appeal. The disposition, as
42

stated in the fallo of the CIAC Arbitral Tribunal's Final Award,


a. An evident miscalculation of figures, a typographical or
should therefore stand. 43

(8) when the findings of fact are themselves arithmetical error; (Emphasis supplied)
conflicting;
WHEREFORE, the petition is PARTLY GRANTED. The
xxxx
Decision dated April 8, 2008 of the Court of Appeals in CA-
(9) when the findings of fact are conclusions
G.R. SP No. 99454 is hereby AFFIRMED with
without citation of the specific evidence on which
Failure to file said motion would consequentlyrender the MODIFICATION. The compensation awarded in favor of
they are based; and
award final and executory under Section 18. 1 of the same Alphaomega Integrated Corporation in the amount of
rules, viz.: ₱17,495,117.44, as shown in the fallo of the ·construction
(10) when the findings of fact of the [CA] are Industry Arbitration Commission's Final Award dated April
premised on the absence of evidence but such 18, 2007, stands.
Section 18.1 Execution of Award – A final arbitral award
findings are contradicted by the evidence on
shall become executory upon the lapse of fifteen (15) days
record. (G.R. No. 109849, February 26, 1997, 268
from receipt thereof by the parties. SO ORDERED.
SCRA 703, 709)
1âwphi1

AIC admitted that it had ample time to file a motion for


Significantly, jurisprudence teaches that mathematical
correction of the Final Award but claimed to have purposely
computations as well as the propriety of the arbitral awards
sat on its right to seek correction supposedly as a strategic
are factual determinations. And just as significant is that the
move against TRANSCO and, instead, filed with the CIAC
34

factual findings of the CIAC and CA—in each separate


Arbitral Tribunal on June 13, 2007 a "Motion for Issuance of
appealed decisions—practically dovetail with each other.
Writ of Execution for the Total Amount of 18,967,318.49 as
The perceptible essential difference, at least insofar as the
Embodied in the Final Award." The Arbitral Tribunal
35

CIAC’s Final Award and the CA Decision in CA-G.R. SP No.


eventually denied AIC’s aforesaid motion for execution
86641 are concerned, rests merely on mathematical
because, despite its merit, the Arbitral Tribunal could not
computations or adjustments of baseline amounts which the
disregard the time-limitation under the CIAC Rules. Clearly, 36

CIAC may have inadvertently utilized. (Emphases and


31

having failed to move for the correction of the Final Award


underscoring supplied)
and, thereafter, having opted to file insteada motion for
execution of the arbitral tribunal’s unopposed and
In any case, the Court finds no reason to disturb the factual uncorrected Final Award, AIC cannot now question against
findings of the CIAC Arbitral Tribunal on the matter of AIC’s the correctness of the CIAC’s disposition. Notably, while
entitlement to damages which the CA affirmed as being well there is jurisprudential authority stating that "[a] clerical error
supported by evidence and properly referred to in the record. in the judgment appealed from may be corrected by the
It is well-settled that findings of fact of quasijudicial bodies, appellate court," the application of that rule cannot be made
37

which have acquired expertise because their jurisdiction is in this case considering that the CIAC Rules provides for a
confined to specific matters, are generally accorded not only specific procedureto deal with particular errors involving "[a]n
respect, but also finality, especially when affirmed by the evident miscalculation of figures, a typographical or
CA. The CIAC possesses that required expertise in the field
32
arithmetical error." Indeed, the rule iswell entrenched:
of construction arbitration and the factual findings of its Specialis derogat generali. When two rules apply to a
construction arbitrators are final and conclusive, not particular case, thatwhich was specially designed for the
reviewable by this Court on appeal. 33
said case must prevail over the other. 38

While the CA correctly affirmed infull the CIAC Arbitral Furthermore, it must be emphasized that the petition for
Tribunal’s factual determinations, it improperly modified the review before the CA was filed by TRANSCO. AIC never 39

amount of the award in favor of AIC, which modification did elevated before the courts the matter concerning the
not observe the proper procedure for the correction of an discrepancy between the amount of the award stated in the
evident miscalculation of figures, including typographical or body of the Final Award and the total award shown in its
arithmetical errors, in the arbitral award. Section 17.1 of the dispositive portion. The issue was touched upon bythe CA
CIAC Rules mandates the filing of a motion for the foregoing only after AIC raised the same through its Comment (With
purpose within fifteen (15) days from receipt thereof, viz.: Motion to Acknowledge Actual Amount of Award) to 40

TRANSCO’s petition for review. The CA should not have


modified the amount of the award to favor AIC because it is
Section 17.1 Motion for correction of final award– Any of the
well-settled that no relief can be granted a party who does
parties may file a motion for correction of the Final Award
not appeal and that a party who did not appeal the decision
41

You might also like