Professional Documents
Culture Documents
Ojiego Joseph It Report
Ojiego Joseph It Report
ON
UNDERTAKEN AT
NIGERIA.
BY
(15BC003986)
SUBMITTED TO
COLLEGE OF ENGINEERING
December, 2020
DECLARATION
I, Ojiego, Joseph chukwukasi, hereby declare that this SIWES Report has been carried out by me
under the supervision of Dr. A.J Gana . It has not been presented for award of any degree in any
…………………… …………………….
Signature Date
CERTICATION PAGE
This SIWES Report by Ojiego, Joseph Chukwukasi, meets the requirements governing the award of
the degree of Bachelor of Engineering (B.Eng.) in Civil Engineering and is approved for its
……………………………………… ……………………..
Supervisor
........................................................ ………………………
........................................................ ………………………
Head of Department
DEDICATION
I dedicate the report to God Almighty for His Grace, favour and mercy over my life and for safety
throughout the course of my SIWES programme. I also dedicate this report to Tpl. Rakiya Sani, who
made it possible for me to work at Federal Housing Authority Nigeria, and to my amazing parents Mr.
& Mrs. Julian Ojiego and my siblings for their love and support. Also, to everyone else that
I am specifically thankful to God almighty for a successful completion of my SIWES programme and
for protecting and keeping me in good health up until this moment. I will also like to acknowledge my
parents Mr. & Mrs. Julian Ojiego for their love, support and words of encouragement. My sincere
appreciation also goes to the management and staff of Federal Housing Authority Nigeria for accepting
I sincerely appreciate my Company’s Supervisor, Engr. A.S Suleman for his love, care, practical
I specially appreciate my level adviser, Engr. Atoyebi Olumoyewa Emmanuel for constantly checking
\
ABSTRACT
This Technical Report contains knowledgeable information on the six months Students’ Work
Experience Scheme (SIWES) which I undertook at Federal Housing Authority Mass housing project,
Zuba, Abuja. Working with the Engineering and Building team as an Intern has given me the
technology, learning its fundamentals, to work with various equipment used in Construction & Project
Management, and also acquiring skills in communicating with experts in the field. I was able to apply
some of the theoretical knowledge gained during my study at the university to real work situations
thereby bridging the gap between school work and actual practice. Generally, I learnt how to read and
interpret the working drawings used in carrying out the construction, I was able to grasp adequate
knowledge and understanding regarding quality assurance and quality control in construction, I learnt
how WBS (Work Breakdown Schedule) helps in organizing what needs to be done in small packages
of activities, I learnt how to effectively carry-out the setting out of a building and supervise the
excavation works as well and finally, I learnt following due steps, the process of carrying-out Sub-
Structure and Super-Structure Construction from excavation to the third suspended floor level.
TABLE OF CONTENTS
DECLARATION i
CERTICATION PAGE ii
DEDICATION iii
ACKNOWEDGEMENT iv
ABSTRACT v
TABLE OF CONTENTS vi
CHAPTER ONE 1
INTRODUCTION 1
1.1 Background Of ITF 1
1.2 Historical Background Of SIWES 2
1.3 Aim Of SIWES 2
1.4 Objectives Of SIWES 2
1.5 Importance of SIWES To Civil Engineering 3
1.6 History & Background of Federal Housing Authority Nigeria 4
1.7 Objectives of The Establishment 4
CHAPTER TWO 6
OVERVIEW OF ACTIVITIES 6
2.1 Introduction 6
2.2 Details of Activities Carried Out During the SIWES Period 6
2.2.1 Sub-Structural Works (Foundation) 6
2.2.1.1 Site Clearance and Preparation 6
2.2.1.2 Setting Out 7
2.2.1.3 Excavation of Foundation 10
2.2.1.4 Blinding of Trenches and Column Bases 11
2.2.1.5 Reinforcement for Footings and Columns 12
2.2.1.6 Concrete Casting of Column Footings and Foundation 13
2.2.1.7 Construction of Rectangular Beam on Strip. (Ground Beams) 14
2.2.1.8 Placing of Form Work for Ground Beam 15
2.2.1.9 Casting of Ground Beams 16
2.2.1.10 Construction and Casting of Concrete Kickers 18
2.2.1.11 Column Formwork and Casting 18
2.2.1.12 Curing of The Casted Columns and Block Work in The Sub-Structure Up to Plinth
Level. 19
2.2.1.13 Laterite Backfilling of The Interior and Exterior Parts of The Blockwork and
Trenches 20
2.2.1.14 Watering, Leveling and Compacting of The Bed in Three Layers 20
2.2.1.15 Installation of Service Pipes (Mechanical and Electrical Outlets) And Starters
Reinforcement for Staircase 20
2.2.1.16 Laying of Hardcore/Form-Work Round the Edges of The Walls 21
2.2.1.17 Laying of Damp Proof Membrane 21
2.2.1.18 Casting of Oversite Concrete (German Floor) 22
2.2.1.19 Laying of Sub-Soil Drainage (French Drain) 22
2.2.2 Super-Structural Works (Concrete Frame) 25
2.2.2.1 Construction and Casting of Ground Floor Columns 25
2.2.2.2 Construction and Casting of First Suspended Floor Slab, Beams and Staircase. 26
2.2.2.3 Construction and Casting of Suspended Slab Columns 29
2.2.2.4 Construction and Casting of Second and Third Suspended Floor Slab, Beams,
Columns and Staircase. 30
CHAPTER THREE 34
PROBLEMS ENCOUNTERED & PROBLEMS SOLVED 34
3.1 Problems Encountered 34
3.2 Problems Solved 34
CHAPTER FOUR 35
CONCLUSION & RECOMMENDATION 35
4.1 Conclusion 35
4.2 Recommendation 35
REFERENCES 36
LIST OF FIGURES
FIG 2. 22: WOODEN PROPS SET UNDERNEATH THE BEAMS AND SLABS 27
INTRODUCTION
The Students Industrial Work Experience Scheme (SIWES) is a skills training program designed to
Agriculture and Colleges of Education for the industrial work situation they are likely to meet after
graduation. The scheme also affords students the opportunity of familiarizing and exposing themselves
to the needed experience in handling equipment and machinery that are usually not available in their
learning, industries, the Federal Government of Nigeria, Industrial Training Fund (ITF), and Nigerian
establish a fund (ITF) to be utilized to promote and encourage the acquisition of skills in industry or
commerce in Nigeria with a view to generating a pool of indigenous trained manpower sufficient to
meet the needs of the economy. The Industrial Training Fund has operated consistently and
painstakingly within the context of its enabling laws Decree 47 of 1971 as Amended in the 2011 ITF
ACT.
ITF begins as a Parastatal “B” in 1971, headed by a Director, the ITF became a Parastatal “A” in 1981,
with a Director-General as the Chief Executive under the aegis of the Ministry of Industry. The Fund
has a 13-member Governing Council and operates with 10 Departments and 4 Units at the
Headquarters, 38 Area Offices, 4 Skills Training Centers, and a Centre for Industrial Excellence.
The main thrust of ITF programmes and services is to stimulate human performance, improve
productivity, and induce value-added production in industry and commerce. Through its SIWES and
Vocational and Apprentice Training Programmes, the Fund also builds capacity for graduates and
youth self-employment, in the context of Small-Scale Industrialization, in the economy. As part of its
responsibilities, the ITF provides Direct Training, Vocational and Apprentice Training, Research and
Consultancy Service, Reimbursement of up to 50% Levy paid by employers of labour registered with
it, and administers the Students Industrial Work Experience Scheme (SIWES). It also provides human
resource development information and training technology service to industry and commerce to
Nigerian universities. The program was created to give students experience in addition to theoretical
learning. The industrial training policy was introduced by the Federal Government of Nigeria in 1973
SIWES has become a necessary pre-condition for graduation. The program is working with disciplines
environmental and applied science. It provides students the opportunity of being exposed and get
acquainted with handling equipment and machines which are usually not available in institutions.
of their field of study by exposing students to machines and equipment, professional work methods
and ways of safeguarding the work areas and workers in industries and other organizations.
ii. It exposes Students to work methods and techniques in handling equipment and machinery
iii. It makes the transition from school to the world of work easier and enhance students’
contact for later job placements and a chance to evaluate companies for which the y
iv. It provides students with the opportunities to apply their educational knowledge in real
work and industrial situations, there by bridging the gap between theory and practice.
v. The programme teaches the students on how to interact effectively with other workers and
engineering.
machineries.
5. It is one of the requirements for the award of Bachelors of Science Degree (B.Sc.) in
Civil Engineering.
1.6 History & Background of Federal Housing Authority Nigeria
The Federal Housing Authority (FHA), a wholly owned agency of the Federal Government of Nigeria,
was established vide Decree 40 of 1973 revised as CAP 136 Laws of the Federation 1990 and now
CAP F14 Laws of the Federation 2004. The Authority is supervised by the Federal Ministry of Works
and Housing. The Authority exists as a body corporate with perpetual succession and a common seal.
i. Preparation and submission to government, from time to time, proposals for National Housing
Programs.
iii. Development and management of real estate on both commercial and profitable bases in all
iv. Provision of site and services scheme for the benefits of all income groups.
electricity, transportation, sewage and water supply as may be relevant to the execution of
EXECUTIVE DIRECTOR
EXECUTIVE DIRECTOR (HOUSING
FINANCE/ACCOUNTING
(BUSINESS DEVELOPMENT)
AND
COORPERATESERVICE)
GM
GM GM
(CONSTRUCTION), GM GM
(HP) , (PRE PROJECTS),
(PROPERTY (F&A) (CS)
(P&ZC) (QUALITY CONTROL)
MANAGEMENT)
OVERVIEW OF ACTIVITIES
2.1 Introduction
Federal Housing Authority is an organization that has the capacity of several fields of study, ranging
from Civil Engineering, Building Technology (Builders), Architecture, Mechanical Engineers, and
several others, all united with the aim and purpose of executing brilliantly and professionally
During this period of SIWES training, I was opportune to work with one of their Engineering and
building teams who were executing a project awarded by the Federal Government to construct mass
residential buildings, ranging from one-bedroom blocks of 16 flats, two-bedroom blocks of 8 flats and
three-bedroom blocks of 8 flats (all 4-storeys) in Zuba, a sub-urban part of the Federal Capital
Territory. Being a member of the team, I and other intern students under the supervision of the
professionals and staff of the F.H.A.’s Engineering and building team in Zuba were assigned tasks to
at least 2 students per building, with the aim of supervising the construction processes and also in the
course of the construction learn the several stages and procedures in carrying-out the construction
projects. This Designation was not permanent, but we were interchanged from time to time to broaden
our knowledge on the different projects at hand and also learn alternatives depending on the structure
construction of a one-bedroom block of 16 flats, starting from the sub-structure to the third floor of the
machinery and hazardous substances from a site, as well as leveling and preparing land for any
planned construction or landscaping. It consists of the removal and disposal of all bushes, trees,
existing fences and loose boulders as well as the grass within the top soil.
necessary structural parts. Also, it establishes the building's correct extent, angle and level. Setting out
is carried in order to accurately define the outline and width of the excavation and to determine the
center line of the proposed building walls, so that construction according to the building professionals’
To perform the setting out, I was opportune to watch carefully with instructions and detailed
descriptions from the site Engineer, materials used in carrying out the task and the method of setting
out employed.
After getting all the materials readily available we went on to establishing a temporary bench-mark
(TBM) which is a fixed point with a known elevation, usually ground floor level. Then we proceeded
to establishing the building layout of which we use the Engineers’ or Builders’ square method to get
For the building layout, which was a rectangle, the outline of the building was marked from the
temporary bench-mark by a line tied to corner posts of wooden pegs with a nail on top of each post to
link the lines together. Then taking the measurements accurately of the edges, we use a Builder’s
square to turn off 90-degree angles for the remaining corners. The posts are usually 50 x 50 mm timber
(wooden) posts driven firmly into the ground using a mallet, then a nail is drilled to the post’s center.
Although I was taught that, where the outline of a building is more complex than the usual rectangle, it
may be necessary to establish a range of points in the same way as for laying out a simple rectangle.
The next step we took was to set up the profiles. After getting the building layout (using 4 wooden
pegs in the ground to establish the outside of our excavations), the profiles were set up at a 1000mm
(1m) away from our layout, while we made sure that all the extensions are same and accurate. Wooden
pegs were used to form all the extensions with distance of 3m (3000mm) intervals and then thin
plywood (tie rods) were nailed to the top of the pegs linking all together to form a rectangle.
Then, using nails we extended and plumbed lines to and fro the profiles cutting vertically and
horizontally across the profile, after which we Established each partition and room’s measurement by
nails (you require five nails at each measurement, two to establish the two sides of block you are going
to place later on then the other two at both ends to serve as the points where you will excavate and then
one to mark the center of the walls. The width of the excavation is usually three times the width of the
block you are using that is if you are using a 9“block then expect to excavate or dig a trench of 27”
wide.
Fig 2. 1: Marking out a profile
Fig 2. 2: Checking structural drawing in reference to marked profile
profile in accordance to the plan. Excavation depth varies according to the requirements of the
The excavations were carried out manually by laborers using diggers, shovels/spades and
wheelbarrows.
After all inspections and approval from the leader of the Engineering / building team and his team
members, we proceeded to commence the excavations of the trenches according to the structural plan,
and with me supervising the digging of the trenches, I was tasked to ensure that the depth of 1.2m
(1200mm/4ft) and width of 0.7m (700m) was achieved evenly and levelled
After the excavation of the trenches, we removed the lines and nailed new lines to mark out the
position for column bases. And then from the actual trench depth of 1.2m, the excavation was extended
by 0.3m down for spaces of column bases. The image above shows the full excavation of both the wall
reinforcements into different measurements as specified in the bar schedule; into Column footings
The diameters of the reinforcements mostly used were Y20 for both the column and the footings and
Then we proceeded to placing the reinforcements into their corresponding positions from the structural
After placing the reinforcements, using the positions on the profile for the columns, we extended lines
and carefully plumed and tied the reinforcements using binding wires and 10mm iron rods to hold the
reinforcements in place in preparation for the concrete casting of the foundation. The tool used for
we commenced the concrete casting of the foundation and column footings using concrete grade M15
and a mix of ratio 1:2:4 (2 heads-pans of cement, 4 head-pans of fine aggregate, 8 head-pans of coarse
sufficient width to reduce the bearing pressures on the sub-strata to an acceptable value. The Ground
beams were constructed according to the specifications given in the drawing throughout the building
along all wall positions. The purpose of this was to transmit the load to the ground beams instead of
The reinforcement used here was Y20 and Y10(for stirrups). The depth of the ground beam used was
600mm.
supervision team and was giving approval for placing of form work. Veneer boards were used as the
form work for the ground beams. It was constructed to have a depth of 600mm and a width of 230mm
by artisans (carpenters). It was Braced both internally and externally to prevent movement of form
we commenced the concrete casting of the foundation ground beams using concrete grade M15 and a
mix of ratio 1:2:4 (2 heads-pans of cement, 4 head-pans of fine aggregate, 8 head-pans of coarse
aggregate).The concrete mixing was done using a Concrete mixer. During casting, the concrete was
vibrated properly to ensure voids removed and prevent the formation of honey combs.
After casting, the form work was removed and the concrete was cured for a period of 4-7 days to attain
full strength.
Fig 2. 11: Casting of Ground Beam
slab/ foundation. It is provided to ensure that the coordinates of the column/ wall are maintained
uniformly between the slabs and essentially throughout the structure. Its purpose is to avoid uneven
steel cover and column wall alignment issues which are almost impossible to rectify once the concrete
is casted. The kickers were formed at each column and was casted to have the same strength or more
poured. In carrying out the form work for the columns in the sub-structure we made use of Steel Form
work (Metal Panels). Most of the Columns were Double Columns i.e. 450mm by 225mm conjoined.
Although in carrying out the form work for the columns in the sub-structure we made use of Steel
Form work. After all necessary alignments and bracing with due inspection and approval, we
proceeded to the concrete casting of the columns using the same concrete mix ratio of 1:2:4. Proper
2.2.1.12 Curing of The Casted Columns and Block Work in The Sub-Structure Up to Plinth Level.
Following the completion of the concrete casting of the columns, the form works were all dismantled
2.2.1.13 Laterite Backfilling of The Interior and Exterior Parts of The Blockwork and Trenches
Backfilling is the process of replacing or reusing the soil that is removed during building construction
pumped into the backfilled soil, so as to allow the soil settle properly and then compact the soil to
2.2.1.15 Installation of Service Pipes (Mechanical and Electrical Outlets) And Starters Reinforcement
for Staircase
From there, the outlets for plumbing and electrical pipes and the reinforcement starters for the staircase
were all properly installed and then the soil around those areas all replaced and compacted.
2.2.1.16 Laying of Hardcore/Form-Work Round the Edges of The Walls
A 200mm thick layer of well compacted hardcore was placed on the compacted soil bed then, a
carpenter made form work round the edges of the entire external walls, in preparation for the concrete
placed on the hardcore layer /block lines to prevent the upward flow of moisture (water) through the
walls of the building or the building itself. When moisture or water flows upward into the walls of a
structure, it weakens the structure over time and could result to cracks or even structure failure.
2.2.1.18 Casting of Oversite Concrete (German Floor)
A concrete slab 150mm thick was done on the bed with the concrete mix ratio of 1:2:4.
underneath and above the soil during raining season. To prevent future failures, we had introduced a
subsoil drainage in order to redirect ground water from the perimeter of the foundation and then
channel it towards the closest drainage system, preventing the water from penetrating and damaging
the foundation. 6’ PVC Pipes were perforated all round as a means of taking water out of soil when
laid. The soil was excavated 600mm away from the column base and 450mm deep.
Fig 2. 18: Placing of Perforated Pipes
Fig 2. 19: Section of Subsoil Drainage
2.2.2 Super-Structural Works (Concrete Frame)
2.2.2.1 Construction and Casting of Ground Floor Columns
After proper curing of the Oversite Concrete (German Floor), kickers 50mm thick were constructed
and casted in alignment with the columns from the foundation. Steel reinforcements were tied to the
previous Columns then Form works were placed directly to the aligned concrete kickers and braced
properly. After all necessary alignments and bracing with due inspection and approval, we proceeded
to the concrete casting of the columns using the same concrete mix ratio of 1:2:4 (2 heads-pans of
cement, 4 head-pans of fine aggregate, 8 head-pans of coarse aggregate).Pr0oper Vibration was carried
out.
2.2.2.2 Construction and Casting of First Suspended Floor Slab, Beams and Staircase.
Construction of the first-floor begins with the Installation of the wooden formwork for both the slab
and the beams done by artisans (carpenters). The depth of beam ranges from 450mm to 600mm
according to the drawing specifications. Wooden runners were put evenly round the building and
supported under with wooden props(bamboos). Then the base of the form works was laid with marine
boards. DPM (Damp proof Membrane) was placed on the base of the formwork before reinforcement
work began. Artisans (Iron Benders) Began The reinforcement work according to the drawing
specifications. The based for the stair case during the flooring of the foundation is left open to serve as
the stair footing. A wooden frame work was constructed to guide the formation of the stair. The frame
work is constructed in a manner that the landing (at least 300m) and rise (150mm) of the stair are made
suitable movement without the threat if injury. Y12 steel bars are used in the Reinforcement frame
work for the stair. When The iron benders had laid their Beams and slab reinforcement, the
Mechanical and Electrical engineers came to place their service pipes and covered them to prevent
concrete from entering them. After a proper Quality Control check from the team leader and his
members alongside their approval, we commenced the concrete casting of the First floor Slab and
Beams using concrete grade M15 and a mix of ratio 1:2:4 (2 heads-pans of cement, 4 head-pans of
fine aggregate, 8 head-pans of coarse aggregate).The concrete mixing was done using a SEMI SELF
LOADER Concrete mixer. During casting, the Beams were vibrated properly to ensure all voids
Fig 2. 22: Wooden Props Set Underneath the Beams and Slabs
Fig 2. 23: Reinforcement for Slab and Beams
After casting, the form work was removed and the concrete was cured for a period of 4-7 days to attain
full strength.
alignment with the columns from the Ground Floor. Steel reinforcements were tied to the previous
Columns then Form works were placed directly to the aligned concrete kickers and braced properly.
After all necessary alignments and bracing with due inspection and approval, we proceeded to the
concrete casting of the columns using the same concrete mix ratio of 1:2:4 (2 heads-pans of cement, 4
head-pans of fine aggregate, 8 head-pans of coarse aggregate).Proper Vibration was carried out.
Fig 2. 26: Checking Vertical Alignment of columns
2.2.2.4 Construction and Casting of Second and Third Suspended Floor Slab, Beams, Columns and
Staircase.
The same process that took place in the construction of the first suspended floor slab reoccurred in the
construction of the second and third suspended floor Slab, Beams and Staircase.
Fig 2. 27: Casting of Second Suspended Floor Slab
challenges and problems I encountered during my industrial training. Listed below were the challenges
i. Due to long hours of transporting materials needed on site, there were days whereby petite
ii. Also due to regular inspection and needed approval from the building team of the Federal
iv. Due to the Coronavirus Outbreak (Covid-19 Pandemic), I was unable to successfully complete
6 months of the SIWES program as all firms and Federal Government Organizations in the
Federal Capital Territory were asked to shut down to curb the spread of the virus, being that it
was amongst the states in Nigeria Affected by the virus. This occurred from 24 th of March and
at the Federal Housing Authority F.C.T. Abuja which is a core scheme in the Industrial Training
Fund (ITF) saddled with the responsibility of strengthening the effective teaching and learning of
skilled based courses such as Civil Engineering and several others. I believe that the knowledge and
practical experience gained during the course of this program would go a long way in supporting and
complementing further knowledge to be gained in my final year in school and future career. I therefore
conclude that SIWES is of great benefit to students in tertiary institutions because the proper and
effective administration of SIWES will go a long way in boosting and enhancing the competencies of
4.2 Recommendation
i. All Organizations should always accept students for SIWES and subsequently assign them to
relevant jobs.
ii. Experienced staff should always be made to train the students on attachment
iii. There should be more funding of the scheme by the government in order for it to be more
effective.
iv. The companies should put in place all the necessary facilities needed to enhance the
v. Adequate facilities (and safety gears) should be made available for students during the
vi. Policies should be put in place to make sure that students are treated well and not taken
FHA, (2020), About Us- Federal Housing Authority Nigeria, [online] Available:
https://www.fha.gov.ng
https://www.funai.edu.ng
Aziza Nigeria, (2017), Industrial Training Fund- History, Objectives. [Online] Available:
https://www.aziza.com.ng