PENGAJUAN RENCANA ANGGARAN BIAYA

PROYEK : RENOVASI RUMAH


OWNER : COKORDA GEDE OVRAYUANA

NO ITEM PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH

I PEKERJAAN ATAP BANGUNA UTAMA


1 Bongkar Talang Beton M2 2.00 Rp 115,000.00 Rp 230,000.00
2 Bongkar Atap M2 74.20 Rp 77,000.00 Rp 5,713,400.00
3 Bobok Exten Kolom Atap M2 4.32 Rp 103,500.00 Rp 447,120.00
4 Pekerjan Begesting Kolom Plat Atap M2 16.11 Rp 175,350.00 Rp 2,824,888.50
5 Pekerjan Begel Kolom Plat Atap Kg 41.90 Rp 16,280.00 Rp 682,132.00
6 Pekerjan Besi Kolom Plat Atap Kg 62.90 Rp 16,280.00 Rp 1,024,012.00
7 Pekerjan Beton 250 Kolom Plat Atap M3 0.61 Rp 1,548,800.00 Rp 944,768.00
8 Pekerjan Begesting Balok Plat Atap M2 28.71 Rp 175,350.00 Rp 5,033,772.45
9 Pekerjan Begel Balok Plat Atap Kg 134.40 Rp 16,335.00 Rp 2,195,424.00
10 Pekerjan Besi Balok Plat Atap Kg 89.60 Rp 16,335.00 Rp 1,463,616.00
11 Pekerjan Beton 250 balok Plat Atap M3 2.16 Rp 1,548,800.00 Rp 3,345,408.00
12 Pekerjan Begesting Ring Balok Plat Atap M2 16.96 Rp 175,350.00 Rp 2,973,936.00
13 Pekerjan Begel Ring Balok Plat Atap Kg 56.70 Rp 16,280.00 Rp 923,076.00
14 Pekerjan Besi Ring Balok Plat Atap Kg 37.80 Rp 16,280.00 Rp 615,384.00
15 Pekerjan Beton 250 Ring Balok Plat Atap M3 0.73 Rp 1,548,800.00 Rp 1,130,624.00
16 Pekerjan Begesting Plat Beton Atap M2 25.80 Rp 175,350.00 Rp 4,524,030.00
17 Pekerjan Besi M7 2 Layer Plat Beton Atap M2 25.80 Rp 154,000.00 Rp 3,973,200.00
18 Pekerjan Beton 250 Plat Beton Atap M3 3.10 Rp 1,548,800.00 Rp 4,801,280.00
19 Pekerjaan Tembok Atap M2 15.60 Rp 213,325.00 Rp 3,327,870.00
20 Plester Dinding M2 15.60 Rp 74,750.00 Rp 1,166,100.00
21 Aci M2 15.60 Rp 60,500.00 Rp 943,800.00
22 Cat Tembok M3 15.60 Rp 57,500.00 Rp 897,000.00
23 Water Proofing M2 29.10 Rp 120,750.00 Rp 3,513,825.00
24 Pekerjaan Kap Atap Baja Ringan Cempaka M2 59.64 Rp 220,000.00 Rp 13,120,800.00
25 Pas. Atap Kodok M2 59.64 Rp 199,650.00 Rp 11,907,126.00
26 Pekerjaan Bubungan M1 24.90 Rp 211,750.00 Rp 5,272,575.00
27 Pekerjaan List Plank M1 31.06 Rp 127,050.00 Rp 3,946,173.00
Rp 86,941,339.95

II PEKERJAAN PLAFON
1 Bongkar Plafon M2 58.80 Rp 38,500.00 Rp 2,263,800.00
2 Pas. Plafon Gipsum M2 58.70 Rp 132,250.00 Rp 7,763,075.00
Rp 10,026,875.00

III PEKERJAAN TEMBOK BANGUNAN UTAMA


1 Bobok Dinding Dapur M2 5.00 Rp 103,500.00 Rp 517,500.00
2 Pengerikan Permukan Dinding M2 129.11 Rp 55,000.00 Rp 7,101,050.00
3 Pekerjan Grinda Tembok M2 72.80 Rp 55,000.00 Rp 4,004,000.00
4 Plester Dinding M2 112.21 Rp 71,500.00 Rp 8,023,015.00
5 Aci Semen Exposes Putih M2 201.91 Rp 60,500.00 Rp 12,215,555.00
6 Coating Doff Dinding M2 185.01 Rp 55,000.00 Rp 10,175,550.00
Rp 42,036,670.00

IV PEKERJAAN KUSEN
1 Bongkar Kusen Pintu Besar Bh 1.00 Rp 460,000.00 Rp 460,000.00
2 Pekerjan Kusen Kamper 6/12 M1 15.60 Rp 203,435.00 Rp 3,173,586.00
3 Pekerjan Kisi-kisi kayu M1 10.88 Rp 172,500.00 Rp 1,876,800.00
4 Pekerjaan Daun Pintu Kubu Tarung M2 2.46 Rp 1,610,000.00 Rp 3,960,600.00
5 Pekerjaan Daun Jendela Kamper M2 7.26 Rp 1,249,381.85 Rp 9,070,512.23
Rp 18,541,498.23
V PEKERJAAN KANOPI
1 Bongkar Kanopi Ls 1 Rp 575,000.00 Rp 575,000.00

VI PEKERJAAN KAMAR MANDI


1 Perkerjaan Kloset Duduk Std Toto + Plumbing Ls 1.00 Rp 2,420,000.00 Rp 2,420,000.00
2 Jet sprayer Unit 1.00 Rp 316,250.00 Rp 316,250.00
3 Pekekerjaan Shower + Plumbing Ls 1.00 Rp 575,000.00 Rp 575,000.00
4 Grinda Tembok M2 14.80 Rp 55,000.00 Rp 814,000.00
5 Aci Semen Exposes Putih M2 14.80 Rp 60,500.00 Rp 895,400.00
6 Coating Doff M2 14.80 Rp 55,000.00 Rp 814,000.00
7 Pekerjan Kusen dan Daun Pintu Kamar Mandi Bh 1.00 Rp 1,725,000.00 Rp 1,725,000.00
8 Pekerjaan Batarang Shower M3 0.33 Rp 1,776,750.00 Rp 579,220.50
9 Kermaik Bataran M2 4.07 Rp 230,000.00 Rp 936,100.00
Rp 9,074,970.50
VII PEKERJAAN ME
1 Pek. Titik lampu Tik 14.00 Rp 431,250.00 Rp 6,037,500.00
2 Pek. Stop kontak Tik 11.00 Rp 59,800.00 Rp 657,800.00
3 Pek. Stop kontak antena TV Tik 3.00 Rp 59,800.00 Rp 179,400.00
4 Pek. Stop kontak AC Tik 4.00 Rp 70,725.00 Rp 282,900.00
5 Pek. Saklar Tik 14.00 Rp 59,800.00 Rp 837,200.00
Rp 7,994,800.00

Total Rp
174,616,153.68
Dibulatkan Rp -
Terbilang :

VIII PEKERJAAN RENOVASI BANGUNAN MEZANINE


1 Bongkar Atap Mezanin M2 40.20 Rp 77,000.00 Rp 3,095,400.00
2 Pekejaan Tangga Kayu Ls 1.00 Rp 990,000.00 Rp 990,000.00
3 Pekerjaan Kap Atap M2 30.80 Rp 220,000.00 Rp 6,776,000.00
4 Pekerjaan Bubungan M1 6.80 Rp 209,000.00 Rp 1,421,200.00
5 Pekerjaan List Plank M1 25.46 Rp 126,500.00 Rp 3,220,690.00
Rp 15,503,290.00

IX PEKERJAAN BUANGAN
1 Pekerjaan Buangan Per Rit ls 1.00 Rp 500,000.00
2 Pekerjaan Buangan Per Pickup ls 1.00 Rp 300,000.00

Jika terjadi pekerjaan tambah kurang akan dibicarakan terlebih dahulu.


MENYETUJUI : DENPASAR, APRIL 2021
OWNER KONTRAKTOR

COKORADA GEDE OVRAYUANA COKORDA GEDE BASKARA PUTRA, ST