Download as pdf or txt
Download as pdf or txt
You are on page 1of 28

7/31/2010

Two-day Short-Course on Recent Development in Ground


Improvement
p Techniques
q and Case Histories,, 10-11 August
g 2010

Ground reinforcement methods


and Recent Development
Jian Chu
Nanyang Technological University, Singapore
Kenny Yee
Secretary General, Association of Geot Society of SEA (AGSSEA)
Menard Asia, Malaysia

C1. Vibro replacement or


stone columns
C2. Dynamic replacement

C3. Sand compaction piles


C3
C. Ground
improveme C4. Geotextile confined
nt with columns
admixtures C5. Rigid inclusions (or
or composite foundation)
inclusions C6. Geosynthetic
y reinforced
column
C7. Microbial methods
C8. Other methods
2

1
7/31/2010

C1. Vibro Replacement or Stone


Columns

www.ptc.fayat.com/1-2-11-78/Vibrolance.htm

Wet Top Feed

Merits Larger diameter and larger, stones 40 to 75mm water to stabilise


hole faster (200 – 250m per shift)
Limitations: source of water; desiltation, environmental issue.
Application: For sites with soft soils (cu < 30 kPa).
4

2
7/31/2010

Dry Bottom Feed

Merits collapse of hole minimised; no water; clean working platform.


Limitations: smaller column diameter; smaller size stones (15 -30mm);
slower installation
Application: For sites with firmer (cu >25 kPa) and low sensitivity.
5

70 – 110cm

3
7/31/2010

WET PROCESS – TOP FEED

DRY PROCESS - BOTTOM FEED


Crane or excavator-based rigs depends on the length of
stone columns to be installed.

4
7/31/2010

C2. Dynamic Replacement (DR)

1. Pre-excavation of column print


2. Fill with granular materials (fines < 5%)
3. Pounding to form a compacted “plug”
4. Further filling of granular materials
5. Increase pounding with more energy to
form column to ground level. DR columns are constructed according to a pre-
determined drop heights, blow counts and grid
spacing following a field calibration test.
9

Dynamic replacement
Merits:
•flexible choice of granular backfill (sand Æ
rock pieces of 300mm).
•larger diameter at the top decreasing with
depth (ideal for load distribution)
•fast production (10,000m2 per rig-mth)

Limitations:
•surface vibration may affect sensitive
structures less than 20m away.
• stable
t bl platform
l tf ((min.
i 11m above
b GWT)

Application:
For large sites with shallow depth of
improvement (< 6m).

1
0

5
7/31/2010

CHARACTERISTICS OF DR COLUMN

Amount backfill per column ~ 25 - 35m3


Typical “average” diameter ~ 2.5 – 3.2m
Typical spacing ~ 4 - 8m
Typical production ~ 10,000m2 per mth

11

DR METHOD – PUNCHING AND


COMPACTING

DR punching pounder to create DR compaction pounder to


columns compact surface after columns.
1
2

6
7/31/2010

DR COLUMNS – SAND BACKFILL

Av. column diameter ~ 3 m


Pre and post treatment CPT and PMT tests carried out.
Post treatment PMT: EY = 28 MPa PL = 1 MPa
PBT: 12mm at 180 kPa; 17mm at 270 kPa
1
3

DR COLUMNS – AGGREGATE
BACKFILL

Av. 2.8m diameter aggregate columns (3” – 6”) to support 6 – 12m


high road embankments over very soft soil deposit (cu < 10 kN
kN/m
/m2).
1
4

7
7/31/2010

DR AGGREGATE / SAND COLUMNS

1
5

Typical Column Properties

8
7/31/2010

Underwater Dynamic Replacement

MERITS OF DR
• The merits of stone columns are equally applicable to DR columns:
• DR has flexibility with backfill materials (sand, aggregate, rock
pieces).
i )
• DR has larger diameter and hence, a higher bearing load
(approx. 80 tons per column).
• DR column has better load distribution at the surface due to its
“inverted” conical shape.
• DR can be used in landfill, collapsible fill and non-engineered fill
in combination with DC.

1
8

9
7/31/2010

LIMITATIONS OF DR
• Organic soils if present in more than 1 column diameter thick
(> ~ 2m) are not suitable for DR sand column – aggregate
columns
l with
ith higher
hi h compaction
ti energy may bbe usedd instead
i t d
but limit to shallow depth < 6m.
• Surface vibration may cause damage to sensitive structures
within close distance; need to monitor PPV during pounding.
• Need minimum area (> 10 10,000
000 m2) in order to be cost
cost-effective
effective
due to mobilization of heavier base crane.
• DR columns are rather short columns; generally less than 6m.

1
9

King Abdullah Univ Sci Tech


(KAUST) site in Saudi Arabia

Sabkah N=1‐2
SM‐ML

Loose 
SM
M dense 
SM

10
7/31/2010

Dynamic replacement (DR) at


KAUST

C3. Sand Compaction Pile (SCP)


• SCPs are installed offshore
by driving a casing into the
soft ground to a
predetermined depth. Sand
is then forced through the
casing into the ground to
displace the soft soil and
thereby form a sand pile.
• SCP is a good alternative for
sandd key
k method
th d to
t avoid
id
dredging and disposing of
soft soil.

22

11
7/31/2010

Applications

Examples

After
Kitazume
(2005)

24

12
7/31/2010

Types of Installation

Pipe
Φ = 30 cm
SCP
Φ = 40 – 50 cm

After Kitazume (2005)


Hammer compaction
25

Pipe
Φ = 40-50 cm
SCP
Φ = 50 – 70 cm

Vertical vibrating compaction


26 After Kitazume (2005)

13
7/31/2010

Installation Patterns

as = (πd2/4)/D2 as = (√3πd2)/(8D2) as = (πd2/4)/(D1D2sinθ)

Replacement ratio as = As/A


as ≤ 0.3 for sand, 0.3 to 0.8 for clay. When as =
0.78, the SCPs are in contact with each other.

Stress concentration ratio

σA = σcAc + σsAs = σc (Ac + σs/σcAs) = σc (Ac + nAs)

Define stress concentration ratio n = σs / σc

The vertical stress on clay:


σc = σ/[1 + (n -1) as]

14
7/31/2010

Bearing capacity of a single pile

Vertical stress: P = σA = σc (As n + Ac)

Horizontal stress: σh = σs (1 – sin φs’)/(1 + sinφs’) & σh ≤ σc + σu

Stress concentration ratio σ s 1 + sin φs' ⎛ σ u ⎞


n= = ⎜1 + ⎟
σ c 1 − sin φs' ⎜⎝ σ c ⎟⎠

σu = upper yield stress of clay ground, may be taken as 2cu

The bearing capacity


1 + sin φs
P = σu ( As n + Ac )
(n − 1) + (n + 1) sin φs

Bearing capacity of SCP group

P = Pa + Pc = [asqs + (1 – as)qc] A

The capacity of the clay qc and the capacity of the SCP qs are
estimated separately using Terzaghi’s bearing capacity theory:

Clay: qc = cuNc/Fs
Sand: qs = 0.5BγsNγ/Fs

After Kitazume (2005)

15
7/31/2010

Stability - Overall

Circular slip method: Composite shear strength


τ = (1 − as )[c0 + kz + μc Δσ z (cu / p)U ]
Fs = R = ∑
M R (τΔl )
+ (γ s z + μ s Δσ z )as tan φs con 2θ
MD ∑ (Wx) c0 = cu at seabed; μc = σc/σ; μs = σs/σ;
U = degree of consolidation;
Δσz = surcharge; γs = unit weight of sand

Stability –Sliding failure

Ppc + Frf + Frc


Fs =
Pae + Pac

16
7/31/2010

Settlement – no good method yet

S = βS0
β = 1/[1 + (n – 1) as]
S0 = [Δe/(1 + e0)]H
= HCclog (σ2/σ1) or
S0 = mvσ H
Cc: compression index
mv: compression modulus

C4. Geotextile confined columns


(GCC)
A closed bottom geotextile “sock” is placed into a 80 cm 
diameter steel casing before a sand column is formed
diameter steel casing before  a sand column is formed.

34

17
7/31/2010

C4. GCC (con’d)

35

C5. Rigid inclusions

• Controlled modulus columns (CMC)


• Multiple stepped pile
• Grouted gravel or stone column
• Vibro-concrete column
• Cast-in-situ, large diameter hollow
concrete pile
• Y or X shaped pile

18
7/31/2010

Controlled modulus columns (CMC)


A borehole is formed using a pressing tool and a column of 
φ250‐450mm is formed by pressure‐grouting. The modulus of 
the column is controlled by varying the strength of the grout.
the column is controlled by varying the strength of the grout. 
 

Grout
fl
flow

Soft soil

CONSTRUCTION OF CMC COLUMNS


Penetration Withdrawal Completion

Soil Injection of Full


displacement cement grout Column

A displacement auger powered by a very large torque


and high static downward thrust is used. Soil is displaced
laterally with minimum spoil and no vibration. The
inclusion takes up 70 – 90% of the stress..
3
8

19
7/31/2010

Typical Design Parameters


Diameter: 250 – 450 mm; Length: typical 10m to 25m
Grout strength: 5 – 10 MPa
Allowable load: 15 – 35 tons per col.
col
Spacing: typical 1.2m to 3m
Area replacement as: typical 2% - 8%

3
9

Merits and Limitations of CMC

• Merits:
• Combined effect of densification and reinforcement to create a
composite soil-column mass.
• Flexible choice of grout strength to achieve a pre-determined
stiffness ratio with the surrounding soil.
• Miminimum spoil and no vibration – urban technology.
• Fast production (15,000m per rig-mth)
• Limitations:
Li it ti
• Delay caused by delivery of grout inside city.
• Relatively competent substrata to found columns.

20
7/31/2010

Hybrid or Bi-modulus method

Peat

CMC displacement aurger CMC bottom Stone columns top TSM drilling tool

The lower part of the column is performed by controlled 
modulus columns (CMC) and the upper part by stone columns. 

Cast-in-situ, large diameter hollow


concrete (PCC) pile

Liu et al. (03, 07)

21
7/31/2010

PCC pile construction process

Pile cap for PCC pile

0.3 0.5 m
m

22
7/31/2010

Design parameters of PCC pile

• The depth of vibro-sinking is up to 25 m


• Th outer
The t diameter
di t is
i ffrom 11.0
0 tto 1
1.5
5m
• The thickness of the wall is from 100 to 150 mm
• The grade for concrete is C10 to C15 for normal
soil improvement, and C30 for coastal
engineering
• Pile spacing is from 2.5 to 4 m for composite
foundation

Pile core excavation

void, necking or fractures?

23
7/31/2010

Grouted gravel/stone column

Y-shaped vibro pile technique

12cm
R





弧度
模板
90°

中隔板

24
7/31/2010

Construction of Y-shaped vibro pile

Pile after extrusion

25
7/31/2010

Embankment Piles

51

Embankment Piles

After Bergado (2005)

26
7/31/2010

Example: Bridge Approach


Effective length of improved section, Le

Lc= Le/2 Ls= Le/2

Approach slab Design crown level


Vertical crest curve
Bridge Anticipated total settlement
PVC
of the improved
impro ed section
G1
S1 Vertical sag curve
S2 Existing ground level
PRVC
Estimated crown level after
20 years, for no soil improvement So
G2
EMBANKMENT
Anticipated crown level after primary
P3 PVT
consolidation (with soil improvement)

Weathered Crust

0.5m diameter DMM piles


Spacing:
S=0.50m
After S=1.0m
S=1.5m SOFT CLAY
Bergado
P2 Parabolic curve
(2005)

P1
x Ls/2 = Le/4 MEDIUM STIFF CLAY
Lc= Le/2

C7 Microbial method

• Bio-cementation (biogrouting) => strength


• Bio clogging =>
Bio-clogging > reduce permeability
• Bio-gas => produce tiny gas bubbles in sand to
increase liquefaction resistance

(van der Ruyt & van der Zon 09) Chu et al. (2008)

27
7/31/2010

GI TECHNIQUES
soft clay loose sand
REINFORCEMENT methods
CONSOLIDATION COMPACTION
methods Semi-Rigid Inclusions Non-Rigid Inclusions methods
(cement grout etc.) (sand, stone, etc.)

Prefab. Vertical Drains Controlled Modulus Dynamic Replacement Dynamic Compaction


Columns

Vacuum Consolidation Deep Soil Mixing Vibro Replacement Vibro Compaction

55 After Yee (2009)

28

You might also like