Professional Documents
Culture Documents
Indian Feasibility Report
Indian Feasibility Report
1) Executive Summary
Kuppli- Koyyam Mineral Sands Deposit-I,
Project
Pre-concentration Plant (PCP).
M/s. Andhra Pradesh Mineral Development
Name of Company / Mine Owner
Corporation Limited, Hyderabad.
Location
Kuppilli, Koyyam, Dharmavaram,
Village
Bonthalakoduru villages
Mandal Etcherla
District Srikakulam
State Andhra Pradesh
Longitude:
83005’64.47’ to 83055’43.03”
83048’33.64” to 83048’07.76”
3 Name of Rivers/ Nallahs/ Tanks/ Nagavali river- Adjacent
Spring/ Lakes etc Kadivalasa River- 15.5 km, SW
4 Name of Reserve Forest(s), Wild life Kotapalem PF (0.5 km, SW)
Sanctuary/ National parks etc. Kuppili PF (within ML area)
Dharmavaram PF (within ML area)
Srikakulam RF (11.6 km, NE)
5 Topography of ML area The mining lease area forms part of a
barren sandy stretch with an elevation of
1-18 m above the mean sea level.
6 Name of the mineral mined Ilmenite, Rutile, Zircon, Garnet,
Sillimanite and Monazite
7 Rate of Production (in MTPA) proposed Heavy Mineral Sands 2.0MTPA
8 Life of Mine Approx. 10-11 years.
9 Mineral Reserve in million tonnes Geological Reserves 76.0 million tonnes
10 Drilling/Blasting No drilling and Blasting is carried out
11 Ultimate depth of mining 8–9m
12 Ground water level 10 m RL
13 Ground water intersection 1.5 – 2.0 m
14 Drainage pattern/water courses Nagavali river- Adjacent
Kadivalasa River- 15.5 km, SW
Drainage Pattern: Northeast to
Southwest
15 Break-up of Land Utilization Pattern Attached as Annexure I
16 Water requirement & Source The requirement 500 m3/hour from
Nagavali River
17 Solid waste Total 1.74 Million Tonnes/annum
18 IBM Approval : Date Mining Plan is under preparation for
rated capacity of raw sand of 2.0 MTPA
19 Public hearing : Date -
20 Cost of project Rs 400 Crores
21 Any Other (specify) None
1
2) Introduction of the Project / Background Information
The Andhra Pradesh Mineral Development Corporation Ltd., (APMDC) was incorporated
on 24th Feb., 1961 as a wholly owned undertaking of the Government of Andhra Pradesh
to develop mineral resources in Andhra Pradesh including exploration, exploitation,
conservation, processing, beneficiation, conversion into value added products and
promotion of mineral based industries. APMDC registered under the Companies Act 1956
with an authorised capital of Rs. 50 lakhs with full participation by Government of
Andhra Pradesh. The Authorised capital is increased from time to time, to Rs. 10
Crores. The paid up capital is Rs. 630.62 Lakhs.
Awards
The Corporation has been awarded with “Coal India Productivity Organizational Award ”
for the year 2006-07 by the Indian Institute of Industrial Engineering on 12 th October,
2007 at Thiruvananthapuram for its exceptional performance in the exploration of the
minerals in the state. Earlier, best documentary film award-2008 at Nandi film fare
awards has been awarded for the documentary pictured on Bauxite deposits by the
corporation.
The Project involved mining of beach sand and separation of heavy minerals (Garnet,
Ilmenite, Leucoxene, Sillimanite and minor amount of Rutile Zircon and Monazite ) and
set-up an export-oriented and value added mining unit.
2
2.2 Brief Description of the Nature of the Project.
The Project involves Production of Heavy Mineral Sands Mine 12.0 MTPA.
2.3 Need for the Project and its importance to the country and or region
As per the projections of 12th plan document prepared for beach sand minerals and as
per the IBM report (Mineral year book) India is currently producing annually ilmenite 7.5
LT, Rutile 0.18 LT, Zircon 0.5 LT, Sillimanite 0.6 LT. Garnet 12.0 LT and Monazite from
East-West coast Beach sands. Out of these minerals majority of rutile and Zircon
requirement is being met by import currently. The chloride grade Ilmenite is also
imported to meet the domestic requirement. However, there is demand of Ilmenite
garnet Sillimanite for export to earn foreign exchange.
Since the project is proposed to be taken up in Northern part of Andhra Pradesh, the
surrounding areas in Srikakulam, Vijayanagaram and Vishakapatnam towns will be
benefited by way of employment, infrastructures and other developments.
The proposed value addition like rutile grade pigment, Titanium slag, Titanium metal,
zircon flour and zirconium chemicals will be taken up at later stage. This project assumes
greater significance in the field of beach sand minerals development in the country.
In view of the above the project is a step towards import substitution, value addition and
establishment of other downstream ancillary industries. The project will also contribute
substantially to the Government exchequer and offer significant employment
opportunities to the locals.
Sr. No
Minerals Production (TPA) Import (TPA)
1 Ilmenite 7,50,000 65,876
2 Rutile 18,000 9,826
3 Zircon 50,000 34,651
4 Garnet 12,00,000 1,115
5 Sillimanite 60,000 74
3
5 Sillimanite 11,151
Sr. No
Minerals Demand (TPA) Export (TPA)
1 Ilmenite 3,19,000 7,91,735
2 Rutile 40,000 2,322
3 Zircon 1,30,000 31,600
4 Garnet 7,00,000 5,05,281
5 Sillimanite 40,000 11,151
About 100 departmental and 300 contract employees will be engaged for the project.
Mining of heavy mineral sand @ 2.0 MTPA with Pre-Concentration Plant @ 333 TPH and
to be produce Ilmenite, Rutile, Zircon, Sillimanite and Garnet minerals.
3.2 Location (map showing general location, specific location and project
boundary & project site specific layout) with coordinates.
The Applied Mining Lease area is located in the jurisdiction of villages Kuppilli, Koyyam,
Dharmavaram, Bonthalakoduru, Etcherla Mandal of Srikakulam district, Andhra Pradesh
Latitude: 18009’20.91” to 18009’44.14” & 18012’33.03’ to 18013’03.26” and 83005’64.47’
to 83055’43.03” &83048’33.64” to 83048’07.76”. The lease area is approachable from
Srikakulam and at a distance of 20 Km. Village wise survey numbers and land details are
enclosed in Annexure-II.
Survey Nos.
Name of the Proposed Geo-Co-ordinates
Plant
Pre Concentration Within the lease area Mining Area
Plant (PCP)
Temporary/Floati Within the lease area Mining Area
ng PCP
(iii) Details of alternate sites considered and the basis of selecting the
proposed site, particularly the environmental considerations gone into
should be highlighted.
As the proposed project is being the mining of beach sand and separation of heavy
minerals (Garnet, Sillimanite, Ilmenite, Leucoxene, and minor amount of Rutile Zircon
and Monazite). Hence, No alternative sites are considered.
4
3.4 Size or Magnitude of operation.
Proposed Production
Mining: 2.0 MTPA of raw sand ROM with 333 TPH Pre-Concentration Plant.
Note:
a) The concentrate output and mineral output from the Pre Concentration Plant and and
value addition plants may vary depending upon the mineral content in the above
mentioned ROM excavated from a particular mining area.
3.5 Project Description with Process details (a schematic diagram/ Flow chart
showing the project layout, components of the project etc. should be given.
Mining of heavy mineral sand @ 2.0Million tonnes per annum with Pre-Concentration
Plant @ 333 TPH and to be produce Ilmenite, Rutile, Zircon, Sillimanite and Garnet
minerals.
The method of mining will be carried out open cast mechanized mining method &
refilling will be done concurrently, wherein Run-of-Mine is mined and advanced
environmental friendly technology, the tailings generated from pre-concentration plant
will be backfilled and afforestation on reclaimed land takes place simultaneously thus
limiting the gap between mining and rehabilitation to pre-mining state to only a few
months. Another unique feature of the above method is that water used as a medium of
transportation and concentrations re-circulated and there is no water consumption
except for the evaporation losses and leakages. The external water to make up this
water loss also goes to recharge the area thus improving the water regime and
vegetation of the area and nearby villages.
5
FIGURE-1
STUDY AREA MAP
6
PCP [PROPOSED FLOW CHART]
ROM Sand
Over size
TROMMEL SCREEN Waste
Unders
Tailings
Middlings Middlings
Conc Conc
Tailings
Conc Conc
MINE BACK
MSP FILLING
Concentrate
7
(vi) Availability of water, its source,
Water Requirement: -
Water requirement for the project is estimated at 800 m3/hour
Source: - Nagavalli River
Dewatering
Cyclone
Deslimed Ore Dewatering Cyclone
Tailings Tailings 50
200 m3/h m3/h
Settling Tank
Thickener-II Thickener-I 50m3/h (U/F)
100m3/h (U/F) 100m3/h (U/F)
Rejects to Mine
Note: There is no consumption of water and make up water goes to re-charge the
surrounding areas & nearby villages thus improving the water regime and vegetation.
8
(vii) Quantity of wastes to be generated (liquid and solid) and scheme for
their management / disposal.
Solid waste to be generated is free silica sand tailings from the pre concentration plant
and mineral separation plant. These waste materials will be used for refilling and
reclaiming the mined out lands. No liquid waste will be generated from the mining
operations.
4) SITE ANALYSIS
(i) Connectivity
Present During
S. Conceptual
Particulars Land scheme
No. period
use period
1 Area of excavation/refill/afforestation 0.00 80.0 800.0
2 Storage for topsoil 0.00 0.00 0.00
3 Overburden dump 0.00 0.00 0.00
4 Mineral storage 0.00 0.00 0.00
Infrastructure (workshop, 0.00
5 2.00 2.00
administrative building etc.)
6 Roads 1.50 3.00 3.00
7 Railways 0.00 0.00 0.00
8 Green belt 0.00 11.00 11.0
9 Area under Aqua Culture 3.00 3.00 3.00
10 Effluent treatment plant 0.00 0.00 0.00
11 Nallah/ River 0.00 00.00 20.00
12 Township area/Settlement area 30.00 30.00 30.00
13 Others check dam & retention walls 0.00 1.00 3.00
14 Area un-utilized 965.50 870.00 161.0
Total 1000.00 1000.00 1000.00
9
FIGURE-2
SURFACE PLAN
10
(iii) Topography along with maps
The mining lease area forms part of a barren sandy stretch with an elevation of 1-20 m
above the mean sea level.
(iv) Existing Land Use pattern and distances from forests, CRZ, etc
The proposed AML area involves forest land of 742.12ha and 4 villages are existing in
the ML area. However, Mining operations shall exclude the human habitation in the
village area by providing safe zone around the villages and roads.
Rivers
Forests
Road: The AML area is connected by a tar road connecting Srikakulam with places like
Srikurmam temple, Kuppili Village over a stretch of 15 km.
Secondary information on meteorological conditions has been collected from nearest IMD
station at Kalingapatnam which is at a distance of 12.0 Km, SE from the plant site. IMD
data for ambient temperature, relative humidity, wind speed and rainfall is given in the
Table-2 below.
TABLE-2
CLIMATE DATA KALINGA PATNAM
Primary schools, village temples and primary health centres are existing in the nearby
villages.
11
EXISTING POPULATION DATA
5) Proposed Infrastructure
Rest shelters, Drinking water & First Aid facilities will be provided within the lease area
whereas Office Canteen, transport and others will be constructed out side the mining
lease area in the close proximity.
(6) Power requirement
About 6 MW of power is required for the proposed sand mining operations, Pre-
Concentration Plant and Mineral Separation Plan
APMDC shall under take plantation activities in and around the ML area and on the
backfilled reclamation land. Green belt will be developed 7.5 m wide along the periphery
of the AML area.
12
9 Project Schedule & Cost Estimates
(ii) Estimated project cost along with analysis in terms of economic viability of the
project.
Sr.
Description Cost in Crores
No
1 Land cost expenditure 23.0
Cost of infrastructure, Equipment, vehicles, Manpower,
2 175.0
machineries, etc.
3 Environmental protection 1.25
4 Socio-economic development 0.75
TOTAL 200.00
The project will improve the socio-economic status of the society in the region by
generating direct and indirect employment opportunities. The project will contribute
additional revenue to the State & Central exchequers in the form of taxes, cess, etc.
Human settlement is expected to increase after this project gets operational. In the long
term, the project will have impact on the population growth due to migration of people
from outside area. Indirect employment opportunities will also add to this.
The literacy level of the project area is likely to increase as there will be influx of many
educated people taking up jobs in the project, which is likely to result in establishment of
better educational facilities.
The impact of the project on the civic amenities will be minimal. Health care facilities will
be developed for the employees of the proposed project. These medical facilities will be
extended to surrounding villages.
The project related construction activities will benefit the local populace in a number of
ways such as supply of construction labourers – skilled, semi-skilled and un-skilled,
tertiary sector employment and provision of goods and services for daily needs including
transport. The proposed project will provide employment to the skilled as well as un-
skilled persons. The local population will be given preference depending upon their
suitability to the job requirement. Besides direct employment, indirect employment
opportunities will also open up. The project will have positive impact in the region.
Quality of life of the people will improve, which in-turn will improve the socio-economic
conditions of the area.
***********
13
ANNEXURE I
In Ha.
S Present During
Conceptual
. Particulars Land scheme
period
No. use period
1 Area of excavation/refill/afforestation 0.00 80.0 800.0
2 Storage for topsoil 0.00 0.00 0.00
3 Overburden dump 0.00 0.00 0.00
4 Mineral storage 0.00 0.00 0.00
Infrastructure (workshop, 0.00
5 2.00 2.00
administrative building etc.)
6 Roads 1.50 3.00 3.00
7 Railways 0.00 0.00 0.00
8 Green belt 0.00 11.00 11.0
9 Area under Aqua Culture 3.00 3.00 3.00
10 Effluent treatment plant 0.00 0.00 0.00
11 Nallah/ River 0.00 00.00 20.00
12 Township area/Settlement area 30.00 30.00 30.00
13 Others check dam & retention walls 0.00 1.00 3.00
14 Area un-utilized 965.50 870.00 161.0
Total 1000.00 1000.00 1000.00
ANNEXURE 2
14
KOYYAM VILLAGE BLOCK AML DETAILS
Sr. Survey Status Of Extent Extent
Remark
No Number the Land in Acres in Hecters
1 349 Pvt. Land 7.29 2.95
2 350 Pvt. Land 11.59 4.69
3 351 Govt. land 17.35 7.02
4 352 Pvt. Land 10.17 4.12
5 409 Pvt. Land 4.13 1.67
6 410 Pvt. Land 2.63 1.06
7 411 Pvt. Land 17.91 7.25
8 412 Pvt. Land 11.24 4.55
9 413 Pvt. Land 1.69 0.68
10 414 Pvt. Land 55.04 22.27
11 415 Pvt. Land 10.03 4.06
12 416 Pvt. Land 4.74 1.92
13 421 Govt. land 13.87 5.61
14 422 Govt. land 14.14 5.72
15 423 Pvt. Land 5.20 2.10
16 424 Govt. land 8.12 3.29
17 425 Govt. land 15.05 6.09
18 426 Govt. land 65.52 26.52
19 427 Govt. land 62.37 25.24
20 428 Pvt. Land 24.02 9.72
21 429 Pvt. Land 20.00 8.09
TOTAL 382.10 154.62
15
BONTHALAKODURU VILLAGE BLOCK AML DETAILS
Sr. Survey Status Of Extent Extent
Remark
No Number the Land in Acres in Hecters
pvt. land
150
1 482.2 195.14
TOTAL 482.2 195.14
16