Case Study On Concurrent Engineering
Case Study On Concurrent Engineering
(Boeing 777)
During the research for this case study, United Airlines had taken
delivery of the first 777 on schedule on May 17, 1995 in Seattle,
Washington. "The Working Together concept was very dynamic," said
United 777 Program Manager Gordon McKinzie. "Working closely with
Boeing, we helped resolve hundreds of design elements". "The result is
that the 777 is the exact plane we wanted, and we're proud to have been
part of it." Boeing President Phil Condit commented regarding United
Airlines: "Their input to the design process has clearly resulted in the
right airplane, for the right market, at the right time." Condit notes that
since the program was launched, the 777 has captured more than 75
percent of its market.
The goal for the 777 program was to reduce the "noncomformance
events" (parts that don’t fit) by 50%; the actual reduction was 75-80%.