ID Task Name Duration Start

July 2021 Finish Predecessors August 2021 September 20


27 30 2 5 8 11 14 17 20 23 26 29 1 4
0 CSS Training Manual 18 days Mon 2/8/21 Wed 25/8/21
1 Research Phase 13 days Wed 4/8/21 Fri 20/8/21
2 Investigate the Software 5 days Fri 13/8/21 Thu 19/8/21 Writer 1[50%],Writer 2[50%]
3 Search the Web 1 day Fri 20/8/21 Fri 20/8/21 2 Writer 1,Staff Assistant 1
4 Interview Subject Matter Experts 2 days Wed 4/8/21 Thu 5/8/21 Writer 1[50%],Project Manager 1[50%]
5 Outline Phase 2 days Mon 2/8/21 Tue 3/8/21
6 Draw Content Outline 1 day Mon 2/8/21 Mon 2/8/21
7 Present to Publisher 2 days Mon 2/8/21 Tue 3/8/21 Project Manager 1[50%],Travel Expenses[$1,000.00]
8 Review Outline 1 day Mon 2/8/21 Mon 2/8/21 Editor 2
9 Development Phase 10 days Tue 3/8/21 Mon 16/8/21
10 Write Lesson 1-5 5 days Tue 3/8/21 Mon 9/8/21 8 Writer 1
11 Write Lesson 6-10 5 days Tue 3/8/21 Mon 9/8/21 10SS Writer 2
12 Create Graphics 5 days Tue 10/8/21 Mon 16/8/21 11 Artist 1
13 Edit Phase 1 day Thu 12/8/21 Fri 13/8/21
14 Check for Grammar Inconsistencies 1 day Thu 12/8/21 Fri 13/8/21 12FS-50% Editor 2,Editor 1
15 Review Phase 5.5 days Fri 13/8/21 Fri 20/8/21
16 Quality Review 1 2.5 days Fri 13/8/21 Tue 17/8/21 14 Editor 1,Editor 2
17 Quality Review 2 3 days Wed 18/8/21 Fri 20/8/21 16 Editor 2
18 Print Phase 3 days Mon 23/8/21 Wed 25/8/21 17

Task Split Duration-only


Critical Task External Tasks Manual Summary Rollup
Milestone Project Summary Manual Summary
Project: CSS Training Manual Summary Group By Summary Start-only
Date: Fri 10/12/21
Rolled Up Task Inactive Task Finish-only
Rolled Up Critical Task Inactive Milestone Progress
Rolled Up Milestone Inactive Summary Deadline
Rolled Up Progress Manual Task

Page 1

You might also like