Microsoft Project Tutorial 4 Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Task Name Duration

PredecessorsStart Finish Oct 10, '21 Oct 17, '21 Oct 24, '21 Oct 31, '21 Nov 7, '21 Nov 14, '21 Nov 21, '21 Nov 28, '21 Dec 5, '21 Dec 12, '21 Dec 19, '21 Dec 26, '21 Jan 2, '22 Jan 9, '22 Jan 16, '22 Jan 23, '22
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 Commercial 76 Mon Mon
Scheduling Project days 10/11/21 1/24/22

2 Mobilization 1 day Mon 10/11/21Mon 10/11/21


3 Install Temp Fencing
5 days4 Wed 10/13/21Tue 10/19/21
4 Permits 1 day 2 Tue 10/12/21Tue 10/12/21
5 Demo Plumbing 5 6 Fri 10/22/21 Thu
Fixtures days 10/28/21

6 Remove Exterior 2 3 Wed Thu


Windows/Storefront
days 10/20/21 10/21/21
Doors

7 Sawcut Concrete, 5 5SS Fri 10/22/21 Thu


Excavate days 10/28/21

8 Uninstall 2 3,4,5,6,7 Fri 10/29/21 Mon


Underground days 11/1/21
Plumbing
9 Inspection - Rough 1 day 8 Tue 11/2/21 Tue 11/2/21
in Underground

10 Pour Patch Concrete


2 days9 Wed 11/3/21Thu 11/4/21
11 Rough Fire Protection
7 days12FF Wed 11/3/21Thu 11/11/21
12 Metal Stud Framing5 days10 Fri 11/5/21 Thu 11/11/21
13 2x4 Wood Blocking2 days12FF Wed 11/10/21Thu 11/11/21
14 Rough Plumbing 7 days12 Fri 11/12/21 Mon 11/22/21
15 Rough Mechanical 7 days12 Fri 11/12/21 Mon 11/22/21
16 Rough Fire Alarm 7 12 Fri 11/12/21 Mon
System days 11/22/21

17 Rough Electrical 7 days12 Fri 11/12/21 Mon 11/22/21


18 Inspection - Rough 1 day 11,12,14,15,16,17
Tue Tue
Mech 11/23/21 11/23/21

19 Inspection - Rough 1 day 11,12,14,15,16,17


Tue Tue
Framing 11/23/21 11/23/21

20 Inspection - Rough 1 day 11,12,14,15,16,17


Tue Tue
Plumbing 11/23/21 11/23/21

21 Inspection - Rough 1 day 11,12,14,15,16,17


Tue Tue
Electric 11/23/21 11/23/21

22 Insulation 2 days18,19,20,21Wed 11/24/21Thu 11/25/21


23 Inspection - Insulation
1 day 22 Fri 11/26/21 Fri 11/26/21
24 Gyp Board Walls/Ceiling
2 days23 Mon 11/29/21Tue 11/30/21
25 Painting 5 days24 Wed 12/1/21Tue 12/7/21
26 Wall Base 2 days24,25SS Wed 12/1/21Thu 12/2/21
27 Wall Tile 5 days26 Fri 12/3/21 Thu 12/9/21
28 Cabinets 3 days25 Wed 12/8/21Fri 12/10/21
29 Acoustical Ceiling 5 days27 Fri 12/10/21 Thu 12/16/21
30 Inspection - 1 day 29,24 Fri 12/17/21 Fri 12/17/21
Hardlid/ACT

31 Porcelain Tile 5 days30 Mon 12/20/21Fri 12/24/21


32 Wall Protection 2 days31SS Mon 12/20/21Tue 12/21/21
33 Cove Base 5 days31SS Mon 12/20/21Fri 12/24/21
34 Luxury Vinyl Tile 5 days31 Mon 12/27/21Fri 12/31/21
35 Carpet 5 days34 Mon 1/3/22 Fri 1/7/22
36 Bathroom Accessories
3 days31,34,32,33,35
Mon 1/10/22Wed 1/12/22
37 Microwave 1 day 31,32,33,34,35
Mon 1/10/22Mon 1/10/22
38 Desk and Chairs 2 days31,32,33,34,35
Mon 1/10/22Tue 1/11/22
39 Lockers 2 days31,32,33,34,35
Mon 1/10/22Tue 1/11/22
40 Finish Fire Protectrion
7 days30,31,32,33,34,35,36,23
Thu 1/13/22 Fri 1/21/22
41 Finish Plumbing 7 days30,31,32,33,34,35,36,23
Thu 1/13/22 Fri 1/21/22
42 Finish Mechanical 7 days30,31,32,33,34,35,36,23
Thu 1/13/22 Fri 1/21/22
43 Finish Electrical 7 days30,31,32,33,34,35,36,23
Thu 1/13/22 Fri 1/21/22
44 Finish Fire Alarm 7 30,31,32,33,34,35,36,23
Thu 1/13/22 Fri 1/21/22
System days

45 Inspection - Final 1 day 40,41,42,43,44


Mon 1/24/22Mon 1/24/22
46 Project Finish 0 days45 Mon 1/24/22Mon 1/24/22 1/24

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Project1
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Wed 12/1/21
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

Page 1

You might also like