Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Why do signalling

projects fail?

Photo Shutterstock/eteimaging
Prepared on behalf of the
International Technical Committee
article by Alan Rumsey

Why do signalling projects fail? Clearly, not all projects do fail, and the technology being implemented. It is
The reason for asking this question many are successfully delivered on a sad reality that often there is a shortage
is that, in recent decades, the schedule and within budget. ‘Greenfield’ (in numbers) of the specific talents
frequency at which projects fail projects on new rail lines, for example, needed to deliver all the complex system
appears to be increasing rather are typically implemented more developments and projects that the
than decreasing. successfully than ‘brownfield’ projects profession is working on today.
on existing operating rail lines. Projects
There is a growing concern and As such, it is not unusual, particularly on
that simply involve the replacement of
frustration amongst some operators the client-side, to increasingly rely on
equipment ‘in-kind’ are typically more
that signalling and telecommunications consultant organisations to provide the
successful than projects that involve
technology deployment is too slow, necessary expertise. There are also many
the introduction of new generations
which leads to the unfortunate railway professionals who have worked
of technology. Project complexity is
perception that the profession exclusively in either a client role or a
therefore seen as an important factor in
lacks innovation and is incapable supplier role. As such, those working in
influencing project success.
of successfully delivering upgrades a client role may not fully appreciate all
in a timely fashion. If this is indeed It could be argued that the principle the implications of changes to software-
the case, then it is important to fully reason for project failures is simply a lack based, real-time, safety systems, while
understand the root cause or causes of of experience, expertise and competence those working in a supplier role may lack
project failures. within the parties responsible for experience with the practical realities
implementing the project (on both the of operating and maintaining a rail
For the purposes of this article, a project
supplier-side and on the contracting transportation system.
is considered to have ‘failed’ if it fails
agency-side). This could include
to deliver the anticipated business There is also a tendency to suggest that
technical, process-related, and project
case benefits in the planned and a real or perceived lack of technical
management-related competences.
contracted time frame i.e. the project expertise and experience on the supplier-
is ‘late’. In extreme cases, the contract With respect to technical competence, side can be mitigated through ‘better’
may be cancelled, and the work never as systems increasingly become and more rigorous processes, and
completed, or the contract may be re- computer-based, communications- high levels of project oversight, on the
bid resulting in additional delay. More based, software-based and information client-side. While appropriate processes
typically, the actual project completion technology (IT) based, and as these can certainly contribute to project
date is many months or years after the enabling technologies continue to success, unfortunately they cannot
originally contracted completion date. evolve at an ever-increasing rate, some replace competent resources. At the
contracting agencies are now beginning end of the day it is people that deliver
When a project is late, there are
to look more to their IT departments, successful projects.
inevitably financial and reputational
rather than their traditional signalling
implications for the parties involved in While a lack of sufficient competent
and telecommunications departments,
implementing the project. In addition, to resources can certainly be an important
to take on the leadership role when
minimise schedule and budget impacts, reason why projects fail, this article
delivering state-of-the-art control and
it often becomes necessary to reduce suggests that it is not the only factor,
communications projects.
the originally contracted scope, with or even the dominant factor, in
potential consequential reductions in the It is certainly clear that for any project project failures.
anticipated business case benefits. In an to be delivered successfully the project
There are three basic and highly
attempt to maintain the schedule, there team on both the client-side and the
interrelated elements of any project,
is an increased risk of ‘cutting corners’, supplier-side must be appropriately
namely scope, cost and schedule. These
leading to errors, omissions and rework staffed with qualified personnel with the
are the key elements of any project,
that further delay project completion. necessary expertise and experience in
and this article suggests that one of the

International Technical Committee Topic 57 Published in IRSE News | Issue 244 | May 2018 1
Photo Shutterstock/Kiattisak Lamchan
principle reasons projects fail is when Specification/scope risks can then require direct information
there is a failure to appropriately balance The risk here is that project scope is exchange between two suppliers
these three elements when viewed within poorly or ambiguously defined by the under two separate contracts), or if the
the context of the delivery risks inherently contracting agency in the contract necessary interface information simply
associated with complex signalling and specifications, or the scope is not is not available, is not up-to-date, or
telecoms projects. consistent with the key business case cannot be trusted.
All too often, the full complexity objectives. This risk includes both Design risks
of a project is not recognised (or under-specifying and over-specifying
The risk here is of a failure to develop
acknowledged) until after contract award, the project requirements. Mitigating this
detailed designs that are consistent
when the project schedule and cost have risk rests with the contracting agency
with contract requirements and the
already been fixed. If the project scope and their consultants, and is discussed in
contracting agencies’ expectations.
is the priority, then this clearly should more detail later in this article.
While mitigating this risk rests primarily
drive the project schedule and cost. It
Adaptation risks with the competence of the supplier, the
is not unusual, however, for the project contracting agency can also influence
schedule i.e. the timeline for completing The risk here is that the level of
adaptation to service-proven products, this risk, both positively and negatively,
the project, to be constrained by external through the specification requirements
political factors unrelated to the realities or the level of new product development
required to meet the requirements of the and the method of working during
of the project delivery. project execution.
contract specification, is underestimated
In this case, if the project schedule by the contracting agency and supplier, Migration, commissioning, and
is the priority, then often either the and thus inadequately reflected in the operational readiness risks
project cost must be increased, or the project schedule and project cost.
project scope reduced. The project The risk here is two-fold. There is
cost, i.e. the total cost required to This risk is closely related to the above a risk that the migration plan and
implement the project scope within the specification/scope risk, and realistically implementation schedule is unrealistic
defined project schedule is, however, can only be mitigated through early given track access constraints, level of
also typically constrained by available interactions between the client and effort required, or the dependencies on
funding. A competitive procurement supplier organisations prior to contract work to be performed by others. There
environment, where lowest cost is the award, and prior to finalising the project is also a risk that the migration plan
primary selection criteria, can also lead to scope, schedule and cost. and implementation schedule result
unrealistic project cost expectations. in unacceptable levels of impact to
Systems integration risks
passenger service during implementation.
To successfully deliver a project The risk here is that there is inadequate
therefore, the primary challenge interface definition and interface Given that control and communications
becomes one of optimising the project management with respect to the projects are inherently tightly linked to
scope to be compatible with the project system’s internal and external interfaces. rail operations, the client organisation,
schedule and cost constraints, and with While the supplier is responsible for the through its own in-house expertise and
consideration and management of the internal interfaces within their scope of knowledgeable staff, is inevitably in the
inherent project delivery risks which supply, it is the external interfaces to the best position to mitigate this risk although
follow. If this is not done it will inevitably infrastructure, to the trains, and to other all too often an attempt is made to
result in project failure, regardless of the legacy systems that are typically more contract-out this risk to the supplier.
competency of the project participants. complex and of higher risk. Safety certification risks
Project delivery risks The contracting agency must play a The risk here is the level of effort required
critical role in risk mitigation both in the for safety certification is underestimated
In this section, some of the inherent
specification of, and the management by the contracting agency or supplier
risks associated with the delivery of any
of, these interfaces. This can be and inadequately reflected in the
complex project are described. Each of
particularly challenging if the contracting project schedule and project cost. While
these risks, if not mitigated, can lead to
agency does not have access to the mitigating this risk again rests primarily
late project delivery and cost overruns.
relevant interface information (which with the supplier, the contracting agency

2 Published in IRSE News | Issue 244 | May 2018 International Technical Committee Topic 57
can also influence this risk, both positively agencies, independent safety assessors, in turn are major factors in influencing
and negatively, through the specification and various public advocacy groups. the project schedule and costs.
requirements and the method of
Politicians, who may not fully appreciate With a complex rail network, it is not
working during project execution. The
the complexities of re-signalling an unusual to implement the project
contracting agency is also responsible
operating rail transportation system, can in phases. While this is a perfectly
for managing the safety certification of
also apply pressure to deliver the benefits appropriate migration strategy, care
those elements of the project that are
of the re-signalling project quicker and must be taken to ensure that the more
external to the supplier’s scope, such as
at a reduced cost. Stakeholder risks can complex and higher risk issues are not
external interfaces and operating and
be mitigated in part by the contracting being pushed into the later project
maintenance readiness.
agency through early stakeholder phases simply to maintain schedule in the
System availability risks engagement and education, and by earlier project phases.
The risk here is a failure to achieve and ensuring, where possible, that any
Insufficient attention to migration
sustain an acceptable level of signalling stakeholder, who has the authority to
planning early in the project lifecycle
system reliability/availability when the make changes or veto decisions, is also
(i.e. prior to contract award) can be a
system is cut-over into revenue service. accountable for the consequences of
significant factor in subsequent project
This could be a result of inadequate or these actions with respect to schedule
schedule and cost overruns.
incomplete system test & commissioning and cost impacts.
(which is primarily a supplier Performance/functionality to be
Optimising signalling project provided
responsibility), but could also be a result
of insufficient attention to maintainability
scope to mitigate project
The project functionality, as well as
and maintenance training (which is delivery risks the safety, availability, and operating
typically a joint supplier/contracting As noted earlier, one of the primary performance levels to be provided,
agency responsibility). factors contributing to project failures is should be driven by the desired business
a failure to optimise the project scope to objectives (such as enhanced safety,
Project management risks be compatible with the project schedule increased capacity, higher levels of
The risk here is ineffective project and cost constraints, when viewed in the automation, improved system availability,
management by the contracting agency context of the above inherent project reduced maintenance requirements,
and/or supplier, because of a lack delivery risks. The discussion on project etc.) and should be consistent with the
of sufficient resources to complete delivery risks also clearly indicates that anticipated concept of operations and
the project on schedule, or a lack the responsibility for mitigating these maintenance after the implementation
of competency as discussed earlier risks is a shared responsibility between of the project.
in this article. the supplier and the contracting agency,
and it is particularly important that this Although the benefits of top-down
Stakeholder engagement risks requirements development and
reality be recognised by all parties when
Finally, the risk here is insufficient, optimising the project scope. requirements management are well
untimely, ineffective, and/or recognised, there are unfortunately too
The scope of any project can be many examples where this approach
unconstructive stakeholder engagement
summarised in terms of: is not followed. Rather than adopting
that negatively influences project
outcomes. Many major re-signalling 1) The geographic area and complexity a true business case-driven approach
projects are not stand-alone projects, of the project. to requirements development, focused
but rather are just one component 2) The performance/functionality on the desired project outputs, all too
of a highly integrated transportation to be provided. often clients and their consultants will
system upgrade programme, comprising 3) The operating and regulatory develop procurement specifications by
multiple projects, collectively focused environment in which the work is building on specifications from prior
on satisfying specific long-term to be undertaken. similar projects (without consideration
business needs. of any lessons-learned from those
4) The procurement/
projects), supplemented by a wish-list of
For example, the system upgrade delivery model adopted.
additional client-specific requirements
programme could include not only the Complexity of rail network drawn from various, and often numerous,
re-signalling project, but also new train project stakeholders.
The complexity of the rail network to
procurement, major control centre
be signalled/re-signalled is typically a With this approach, it is inevitable
upgrades, trackwork upgrades, network
given, with little opportunity to reduce that specification requirements, and
electrification upgrades, maintenance
the complexity of the rail network as part resulting system architectures, will
and storage facility upgrades, etc.
of the signalling project. Indeed, there become increasingly complex, with no
Successfully implementing such an
are often changes to the rail network improvement in specification quality.
upgrade programme has been described
being implemented in parallel with the The volume (number of pages) of typical
as akin to solving a huge logistical puzzle.
project, with changes to track alignment, system procurement specifications is
The number of internal and external new tracks being added, changes within certainly increasing, not only in terms of
stakeholders that can influence a interlockings areas, etc. technical requirements (what the project
project may be very large. Stakeholders must deliver), but also in terms of process
The project may also be implemented in
include not only signalling and requirements (how the project must
parallel with new train procurements and
telecoms professionals, but engineering be delivered and contract-deliverable
other system upgrades. The complexity
professionals from other disciplines documentation).
of the rail network (including legacy
responsible for enabling works
equipment the project is required to The specification requirements must
and interfacing systems, operators,
interface to) is however a major factor in also be balanced against the capabilities
maintainers, procurement and contract
influencing the implementation strategy of currently available, and service-
managers, funding agencies, regulatory
and migration plan for the project which proven, products such that the level of

International Technical Committee Topic 57 Published in IRSE News | Issue 244 | May 2018 3
product adaptation and new product engagement, prior to contract award, to constrains on ‘how’ the project is to be
development is clearly understood flush out unrealistic expectations. delivered can also result in schedule/
early in the project life cycle and cost overruns if not factored into the
When over-specifying the project
appropriately reflected in the project implementation schedule early in the
requirements occurs, at the functional
schedule and cost. project life cycle.
and detailed design levels as well as at
When developing specification the engineering process level, there Procurement/delivery model
requirements, the challenge is balancing is a resulting risk that demonstrating Delivering complex projects typically
long-term needs with short-term wants. compliance with thousands of individual involves multiple entities (the client,
The long-term needs relate to the requirements during project execution suppliers, installers, consultants, etc.)
business goals that justified the project (the ‘paper project’) can take on a higher all linked through multiple contracts,
in the first place i.e. they are something priority than delivering the fundamental where each entity takes on specific
that must be delivered, and include business objectives. responsibilities with respect to
not only functional requirements but project delivery.
Major projects also often represent
also the overall system performance
fundamental changes to operating and There is a danger in attempting to place
requirements (the project ‘outputs’),
maintenance practices, specifically when all the project delivery risks with a single
including safety integrity requirements. If
there are major changes to signalling entity, especially if that entity is not in
this requires product adaptation or new
technology. A lack of attention by a position to manage all of those risks.
product development, then so be it, but
the client to organisational transition This approach will inevitably lead to
this must be factored into the project
planning, and operating and maintenance project failure.
schedule and cost.
readiness can also be a factor in
The short-term wants on the other project failures. A preferred approach is to fully
hand relate to preferences of the various understand all of the project delivery
stakeholders; things they would like to Operating and regulatory risks, and place each risk with the entity
have but that don’t necessarily relate environment that is in the best position to manage
directly to the business goals. This is The operating and regulatory it. A consequence of this approach,
where the problem of over-specification environment can also be major schedule however, is that the method of working
and unnecessary product adaptation and cost drivers on complex signalling between the various entities becomes
can occur. There is an argument, projects. On ‘brownfield’ re-signalling critical, which in turn requires a
however, that clients should not hold projects, for example, the operating contracting strategy that encourages a
back on including such requirements, environment and the need to maintain collaborative and co-located ‘one team’
and should use such requirements to operations during project implementation approach to project delivery, with shared
encourage innovation and attracting new inevitably results in constraints on track milestones and processes, rather than a
players into the market; relying on the access and access to rail vehicles. confrontational ‘blame-based’ approach.
industry to push back if the requirements A contracting strategy that recognises
If these constraints are not fully
are unrealistic. that successfully project completion
understood early in the project life cycle,
In a competitive procurement and balanced against project delivery should take precedence over total
environment, however, there is a real needs, schedule and cost overruns contract compliance i.e. the contract
danger that suppliers will promise more become inevitable. It is particularly should support, not constrain, successful
than they can realistically deliver, with the important that contracting agencies project delivery. Again, a prerequisite of
philosophy that at the end of the day it is recognise their role in mitigating this risk. such a collaborative delivery model is that
better to have an unsatisfied client than the project schedule and cost is realistic
Regulatory requirements, and other given the project scope.
no client at all. This risk can be mitigated,
process-based requirements that impose
at least in part, though early contractor

Conclusion
In summary, while there can be many 2) Encouraging early engagement 5) Placing project delivery risks with
reasons for signalling project failures, this between the client and prospective the entities in the best position to
article concludes that one of the primary suppliers to build confidence that manage the risks.
factors is a lack of consistency between there is a common understanding of 6) Adopting a co-located ‘one team’
contracted project scope, project both the technical requirements and method of working.
schedule and project cost, when all of the delivery process requirements
7) Simplifying ‘process’ requirements
the project delivery risks are considered. (including migration planning), and
and ensuring that the process
to flush out unrealistic expectations,
One solution is to simply acknowledge requirements contribute to, rather
prior to contract award.
up-front that complex projects will than constrain, project success.
indeed cost more and take longer to 3) Minimising and simplifying, where
8) Maximising access to track
implement than desired. The preferred possible, external interfaces to legacy
and trains (short-term pain for
solution is to remove, as much as equipment with the contracting
long-term gain); and
possible, the unnecessary complexities agency acknowledging their role in
mitigating system integration risks. 9) Showing a willingness to change
in the project scope that contribute to
legacy operating and maintenance
project delivery risks, by: 4) Minimising, where possible, product
practices, consistent with
1) Focusing more on project output adaptation/new development and
characteristics of the new system.
requirements and business case where this is required ensuring there
objectives, and less on ever is an allowance for the adaptation/
increasing detailed technical and development in the project
process requirements. schedule and cost.

4 Published in IRSE News | Issue 244 | May 2018 International Technical Committee Topic 57

You might also like