24 / 7 SCHEDULED OF ELECTRICAL OPERATION 2022

S/N Description Equipment's Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 24/7 WEEKLY OPERATION OF ELECTRICAL MV/LV CHILLER BUILDING All RUNNING EQUIPMENT RECORED DATA                               

ELECTRICAL PREVENTIVE MAINTENANCE SCHEDULED 2022


Description Equipment's WEEK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

2 MONTHLY PM FOR AIR COMPRESSOR ELECTRICAL AIR COMPRESSOR #1  


3 MONTHLY PM FOR AIR COMPRESSOR ELECTRICAL AIR COMPRESSOR # 2  
4 GROUND FLOOR ELECTRICAL ROOM # 1 & 2  
YEARLY MV 13.8KV SWITCHGEAR MAINTENANCE
GROUND FLOOR ELECTRICAL ROOM # 3 & 4  
INCLUDED OUT GOING CABLES
GROUND FLOOR ELECTRICAL ROOM # 9 & 10  
GROUND FLOORELECTRICAL ROOM # 11 & 12  
ELECTRICAL ROOM BASEMENT A-C AREA B-02  
ELECTRICAL ROOM BASEMENT U-W AREA B-01 & B-04  
5 G. F ELECTRICAL ROOM # 1 & 2 BATTERY CHARGER # 1 & 2            
MONTHLY MAINTENANCE FOR BATTERY BANK AND
G. F ELECTRICAL ROOM # 3 & 4 BATTERY CHARGER # 1 & 2            
CHARGER INCLUDED CABLES
G. F ELECTRICAL ROOM # 9 & 10 BATTERY CHARGER # 1 & 2            
G. F E. ROOM # 11 & 12 BATTERY CHARGER # 1 & 2            
B. F E. ROOM U-W AREA BATTERY CHARGER # B-01, 02 & 04            
B.F E. ROOM A-C AREA BATTERY CHARGER # B-01, 02 & 03            
6 ELECTRICAL ROOM BASEMENT 'A-C' AREA MCC # 1 & 2  
1/2 YEARLY LV MCC 400V SWITCHGEAR
ELECTRICAL ROOM BASEMENT 'A-C' AREA MCC # 3 & 4  
MAINTENANCE WITH CABLES
ELECTRICAL ROOM BASEMENT 'A-C' AREA MCC # 5 & 6  
ELECTRICAL ROOM BASEMENT 'A-C' AREA MCC # 7 & 8  
ELECTRICAL ROOM BASEMENT 'U-W' AREA MCC # 17 & 18  
ELECTRICAL ROOM BASEMENT 'U-W' AREA MCC # 19 & 20  
ELECTRICAL ROOM BASEMENT 'U-W' AREA MCC # 21 & 22  
ELECTRICAL ROOM BASEMENT 'U-W' AREA MCC # 23 & 24  
ELECTRICAL ROOM BASEMENT 'U-W' AREA EMDB  
ELECTRICAL ROOM BASEMENT PUMP AREA MCC # 33  
7 GROUND FLOOR ELECTRICAL ROOM # 1 TR # 1 & 2  
1/2 YEARLY MV/LV TRANSFORMER MAINTENANCE
GROUND FLOOR ELECTRICAL ROOM # 2 TR # 3 & 4  
WITH CABLES
GROUND FLOOR ELECTRICAL ROOM # 3 TR # 5 & 6  
GROUND FLOOR ELECTRICAL ROOM # 4 TR # 7 & 8  
GROUND FLOOR ELECTRICAL ROOM # 9 TR # 17 & 18  
GROUND FLOOR ELECTRICAL ROOM # 10 TR # 19 & 20  
GROUND FLOORELECTRICAL ROOM # 11 TR # 21 & 22  
GROUND FLOOR ELECTRICAL ROOM # 12 TR # 23 & 24  
BASEMENT 'U-W' AREA ELECTRICAL ROOM TR # 1 & 2  
8 BASEMENT 'A-C' AREA ELECTRICAL ROOM TR # 1 TO VFD #1  
1/2 YEARLY MV/MV 13.8 TO 2.8KV VFD Transformer
BASEMENT 'A-C' AREA ELECTRICAL ROOM TR # 2 TO VFD #2  
MAINTENANCE WITH CABLES
BASEMENT 'A-C' AREA ELECTRICAL ROOM TR # 3 TO VFD #3  
BASEMENT 'A-C' AREA ELECTRICAL ROOM TR # 4 TO VFD #4  
BASEMENT 'U-W' AREA ELECTRICAL ROOM TR # 5 TO VFD #5  
BASEMENT 'U-W' AREA ELECTRICAL ROOM TR # 6 TO VFD #6  
BASEMENT 'U-W' AREA ELECTRICAL ROOM TR # 7 TO VFD #7  
BASEMENT 'U-W' AREA ELECTRICAL ROOM TR # 8 TO VFD #8  

9 1/2 YEARLY MCC 400V SWITCHGEAR MAINTENANCE ELECTRICAL ROOM GROUND FLOOR FEED PUMP AREA MCC  

GENERATOR BUILDING
10 YEARLY MV 13.8KV SWITCHGEAR MAINTENANCE GROUND FLOOR ELECTRICAL ROOM # 1 & 2 

11 1/2 YEARLY MV/LV TRANSFORMER MAINTENANCE GROUND FLOOR TR # 1, 2, 3 & 4  

12 YEARLY MV 13.8KV SWITCHGEAR MAINTENANCE GROUND FLOOR ELECTRICAL ROOM # 3 (52 Cubical)  

Name: Eng. Syed Shoaib Saleemuddin Name: Eng. Haytham Said Name: Eng. Yousef Al-Otaibi

Signature:……...…………...……………….....………………..…………………………………… Signature:……………………………...………….………..……..……………………………… Signature:………………………..…………...…………………....……..……………………………………


24 / 7 OPERATION SCHEDULED FOR MECHANICAL EQUIPMENT 2022
S/N Description Equipment's Day's 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
24/7 WEEKLY OPERATION OF
1 MECHANICAL EQUIPMENT CHILLER All RUNNING EQUIPMENT DATA RECOREDING                               
BUILDING 'A'

PREVENTIVE MAINTENANCE SCHEDULED FOR MECHANICAL EQUIPMENT 2022

Description Equipment's Week's 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

2 1/2 YEARLY PM FOR AIR COMPRESSOR MECHANICAL MAINTENANCE AIR COMPRESSOR # 1  

3 1/2 YEARLY PM FOR AIR COMPRESSOR MECHANICAL MAINTENANCE AIR COMPRESSOR # 2  

MONTHLY MAINTENANCE FOR ALL BASEMENT FLOOR PUMP AREA CLEANING OF ALL CONDENSER
4 PUMPS # 01 TO 16
         
PROCESS PUMPS
BASEMENT FLOOR PUMP AREA CLEANING OF ALL PRIMARY
         
PUMPS # 01 TO 16
BASEMENT FLOOR PUMP AREA CLEANING OF ALL SECONDARY
         
PUMPS # 01 TO 08
BASEMENT FLOOR PUMP AREA CLEANING OF ALL CUC HVAC
         
PUMPS # 14 TO 17
MONTHLY MAINTANENCE FOR ALL FEED BASEMENT FLOOR UNDERGROUND WATER TANK AREA
5 CLEANING # 01 TO 04
         
PUMPS
1/4 YEARLY MAINTENANCE FOR ALL BASEMENT FLOOR PUMP AREA PM OF CONDENSER PUMPS No.
6 01 To 08
   
PROCESS PUMPS
BASEMENT FLOOR PUMP AREA PM OF CONDENSER PUMPS No.
   
17 To 24
BASEMENT FLOOR PUMP AREA PM OF PRIMARY PUMPS No. 01
   
To 08
BASEMENT FLOOR PUMP AREA PM OF PRIMARY PUMPS No. 17
   
To 24
BASEMENT FLOOR PUMP AREA PM OF SECONDARY PUMPSNo. 01
   
To 08
BASEMENT FLOOR PUMP AREA PM OF ALL CUC HVAC PUMPS    

BASEMENT FLOOR PUMP AREA PM OF ALL FEED WATER PUMPS    

1/2 YEARLY MAINTENANCE FOR COOLING ROOF TOP CHILLER 'A' AREA PM COOLING TOWER FAN AND GEAR
7 BOX # 1 & 3
 
TOWER
ROOF TOP CHILLER 'A' AREA PM COOLING TOWER FAN AND GEAR
 
BOX# 2 & 4
ROOF TOP CHILLER 'A' AREA PM COOLING TOWER FAN AND GEAR
 
BOX # 6 & 8
ROOF TOP CHILLER 'A' AREA PM COOLING TOWER FAN AND GEAR
 
BOX # 17 & 19
ROOF TOP CHILLER 'A' AREA PM COOLING TOWER FAN AND GEAR
 
BOX # 21 & 23
ROOF TOP CHILLER 'A' AREA PM COOLING TOWER FAN AND GEAR
 
BOX # 18 & 20
ROOF TOP CHILLER 'A' AREA PM COOLING TOWER FAN AND GEAR
 
BOX # 22 & 24
1/2 YEARLY MAINTENANCE FOR COOLING ROOF TOP CHILLER 'A' AREA PM OF COOLING TOWER AIR INTAKE
8 LOUVERS
             
TOWER AIR INTAKE LOUVERS

9 MONTHLY MAINTENANCE OF AHU'S 16 AHU'S IN CHILLER BUILDING           

07 AHU'S IN GENERATOR BUILDING, 05 AHU'S IN SERVICES


MONTHLY MAINTENANCE OF AHU'S           
BUILDING AND 01 AHU IN MAKE-UP WATER PUMP ROOM
03 FCU'S IN SERVICES BUILDING AND 01 FCU IN MAKE-UP WATER
MONTHLY MAINTENANCE OF FCU'S           
PUMPS ELECTRICAL ROOM
1/2 YEARLY REPLACEMENT OF BAG ALL AHU'S  
FILTERS

Name: Eng. Syed Shoaib Saleemuddin Name: Eng. Haytham Said Name: Eng. Yousef Al-Otaibi

Signature:………………..……………........………………..……………...………………………… Signature:……………………………...……………..…..………….………………………… Signature:………………….…..…………...………………..……………………………………