Chiller Satus in Chiller Plant-A & Emergency Plan: Standby
Chiller Satus in Chiller Plant-A & Emergency Plan: Standby
Operation Operation
1 Chiller # 3 Operation Operation Operation (CP # 3 Shifted from Operation Operation GEDAC Operation Control Module from
Chiller-B CP # 10) Chiller # 1 to 3
Operation Operation
AFC Valve repaied by Inma
2 Chiller # 6 Operation Operation Operation Operation Operation GEDAC Operation team;
(CP # 3 Shifted from
Soft Starter Module has been
Chiller-B CP # 14)
changed from CP# 23 to 6
standby
Chiller # 18 Standby Standby Standby Standby Standby Standby YORK/SBG Standby ( Change Intercooler I/P
4
transducer from Chiller #
1 to 18)
CT Motor
5 Chiller # 4 Standby Standby Standby Standby Standby Red phase GEA/SIEMENS Standby Standby
RTD Short
6 Chiller # 05 Standby Standby Standby Standby Standby Standby INMA Standby Standby
Cannot Run
Cannot Run
11 Chiller # 17 Standby Cannot Run Standby Standby Standby ASEM Morex/SBG Cannot Run Supplier ASEM MOREX
Condenser Pump
Shall repair the Pump
Major Leakage
Cannot Run
Cannot Run
12 Chiller # 24 Standby Cannot Run Standby Standby Standby ASEM Morex/SBG Cannot Run Supplier ASEM MOREX
Condenser Pump
Shall repair the Pump
Major Leakage
Cannot Run
Cannot Run Supplier ASEM MOREX
Condenser Pump 1.Supplier ASEM
York spare MOREX Shall repair Shall repair the Pump
Major Leakage
parts(transducer, Cannot Run the Pum
ABCD/ASEM
Proximity sensor,I/P CP Soft starter 2.Waiting for YORK Waiting for Spare Parts
16 Chiller # 1 Cannot Run CP Soft starter Standby Standby MOREX/YORK/ Cannot Run
transducer) control Module chiller Spares. Gulf Abram/GEDAC delivery by YORK
Module Overload 3.Waiting for delivery
panel cpu Overload Fault Fault & GEDAC shall supply
of Flow meter 6oo
mm
Module
600 mm Flow Meter