Rab Pos Gate
Rab Pos Gate
60,850.00
71,050.00
99,533.87
25,800.00
90,200.00
DAFTAR BIAYA SEWA PERALATAN
Tenaga
Mandor 0.0500 O.H 110,000.00 5,500.00
Kepala Tukang 0.2000 O.H 100,000.00 20,000.00
Tukang Kayu 2.0000 O.H 90,000.00 180,000.00
Pekerja 1.0000 O.H 85,000.00 85,000.00
Jumlah Tenaga 290,500.00
Bahan
Dolken Kayu Gelam Ø 8-10/400 Cm 1.7000 Batang 21,510.00 36,567.00
Kayu Meranti 5/7 0.2100 m3 5,166,270.00 1,084,916.70
Paku Biasa 2" - 5" 0.3000 Kg 18,900.00 5,670.00
Semen Portland 0.2625 Zak 69,750.00 18,309.38
Pasir Beton 0.0300 m3 231,885.00 6,956.55
Koral Beton 0.0500 m3 220,860.00 11,043.00
Seng Gelombang 1.5000 Lembar 71,055.00 106,582.50
Seng Plat 0.2500 Lembar 45,675.00 11,418.75
Jumlah Bahan 1,281,463.88
Total ( Tenaga + Bahan) 1,571,963.88
Overhead 0.0000 0.00
H.S.P 1,571,963.88
Tenaga
Mandor 0.0750 O.H 110,000.00 8,250.00
Pekerja 0.1500 O.H 85,000.00 12,750.00
Jumlah Tenaga 21,000.00
Bahan
1 m2 Pembongkaran Paving m2
Tenaga
Mandor 0.0100 O.H 110,000.00 1,100.00
Pekerja 0.2000 O.H 85,000.00 17,000.00
Jumlah Tenaga 18,100.00
Bahan
C PEKERJAAN TANAH
1 m3 Pekerjaan Galian Tanah Biasa Sedalam 1
Meter m3
Tenaga
Mandor 0.0250 O.H 110,000.00 2,750.00
Pekerja 0.7500 O.H 85,000.00 63,750.00
Jumlah Tenaga 66,500.00
Bahan
Tenaga
Mandor 0.0450 O.H 110,000.00 4,950.00
Pekerja 0.9000 O.H 85,000.00 76,500.00
Jumlah Tenaga 81,450.00
Bahan
Tenaga
Mandor 0.0600 O.H 110,000.00 6,600.00
Pekerja 1.5000 O.H 85,000.00 127,500.00
Jumlah Tenaga 134,100.00
Bahan
Tenaga
Mandor 0.0200 O.H 110,000.00 2,200.00
Pekerja 0.4000 O.H 85,000.00 34,000.00
Jumlah Tenaga 36,200.00
Bahan
Sewa Alat Bantu Strouss Pile 0.4000 jam 10,650.00 4,260.00
Jumlah Bahan 4,260.00
Total ( Tenaga + Bahan) 40,460.00
Overhead 0.0000 0.00
H.S.P 40,460.00
Tenaga
Mandor 0.0240 O.H 110,000.00 2,640.00
Pekerja 0.4800 O.H 85,000.00 40,800.00
Jumlah Tenaga 43,440.00
Bahan
Sewa Alat Bantu Strouss Pile 0.4000 jam 10,650.00 4,260.00
Jumlah Bahan 4,260.00
Total ( Tenaga + Bahan) 47,700.00
Overhead 0.0000 0.00
H.S.P 47,700.00
Tenaga
Mandor 0.0100 O.H 110,000.00 1,100.00
Pekerja 0.3300 O.H 85,000.00 28,050.00
Jumlah Tenaga 29,150.00
Bahan
Tenaga
Mandor 0.0150 O.H 110,000.00 1,650.00
Pekerja 0.3000 O.H 85,000.00 25,500.00
Jumlah Tenaga 27,150.00
Bahan
Tenaga
Mandor 0.0200 O.H 110,000.00 2,200.00
Pekerja 0.5000 O.H 85,000.00 42,500.00
Jumlah Tenaga 44,700.00
Bahan
Tenaga
Mandor 0.0150 O.H 110,000.00 1,650.00
Pekerja 0.4000 O.H 85,000.00 34,000.00
Jumlah Tenaga 35,650.00
Bahan
D PEKERJAAN PONDASI
1 m3 Pekerjaan Pasangan Pondasi Batu Belah
15/20 Cm, Campuran (1 Pc : 3 Pp) m3
Tenaga
Mandor 0.0750 O.H 110,000.00 8,250.00
Kepala Tukang 0.0750 O.H 100,000.00 7,500.00
Tukang Batu 0.7500 O.H 90,000.00 67,500.00
Pekerja 1.5000 O.H 85,000.00 127,500.00
Jumlah Tenaga 210,750.00
Bahan
Semen Portland 5.0500 Zak 69,750.00 352,237.50
Pasir Pasang 0.4850 m3 220,275.00 106,833.38
Batu Kali Pecah 15/20 Cm 1.2000 m3 173,925.00 208,710.00
Jumlah Bahan 667,780.88
Total ( Tenaga + Bahan) 878,530.88
Overhead 0.0000 0.00
H.S.P 878,530.88
Tenaga
Mandor 0.0750 O.H 110,000.00 8,250.00
Kepala Tukang 0.0750 O.H 100,000.00 7,500.00
Tukang Batu 0.7500 O.H 90,000.00 67,500.00
Pekerja 1.5000 O.H 85,000.00 127,500.00
Jumlah Tenaga 210,750.00
Bahan
Semen Portland 4.0750 Zak 69,750.00 284,231.25
Pasir Pasang 0.5200 m3 220,275.00 114,543.00
Batu Kali Pecah 15/20 Cm 1.2000 m3 173,925.00 208,710.00
Jumlah Bahan 607,484.25
Total ( Tenaga + Bahan) 818,234.25
Overhead 0.0000 0.00
H.S.P 818,234.25
Tenaga
Mandor 0.0750 O.H 110,000.00 8,250.00
Kepala Tukang 0.0750 O.H 100,000.00 7,500.00
Tukang Batu 0.7500 O.H 90,000.00 67,500.00
Pekerja 1.5000 O.H 85,000.00 127,500.00
Jumlah Tenaga 210,750.00
Bahan
Semen Portland 3.4000 Zak 69,750.00 237,150.00
Pasir Pasang 0.5440 m3 220,275.00 119,829.60
Batu Kali Pecah 15/20 Cm 1.2000 m3 173,925.00 208,710.00
Jumlah Bahan 565,689.60
Total ( Tenaga + Bahan) 776,439.60
Overhead 0.0000 0.00
H.S.P 776,439.60
E PEKERJAAN BETON
1 m3 Pekerjaan Lantai Kerja K-100 F’C = 7,4 Mpa
m3
Slump (3-6) Cm, W/C = 0,87
Tenaga
Mandor 0.0600 O.H 110,000.00 6,600.00
Kepala Tukang 0.0200 O.H 100,000.00 2,000.00
Tukang Batu 0.2000 O.H 90,000.00 18,000.00
Pekerja 1.2000 O.H 85,000.00 102,000.00
Jumlah Tenaga 128,600.00
Bahan
Semen Portland 5.7500 Zak 69,750.00 401,062.50
Pasir Beton 0.6379 m3 231,885.00 147,919.44
Kerikil 0.7608 m3 220,860.00 168,030.29
Air Tawar 200.0000 Liter 135.00 27,000.00
Jumlah Bahan 744,012.23
Total ( Tenaga + Bahan) 872,612.23
Overhead 0.0000 0.00
H.S.P 872,612.23
Tenaga
Mandor 0.0830 O.H 110,000.00 9,130.00
Kepala Tukang 0.0280 O.H 100,000.00 2,800.00
Tukang Batu 0.2750 O.H 90,000.00 24,750.00
Pekerja 1.6500 O.H 85,000.00 140,250.00
Jumlah Tenaga 176,930.00
Bahan
Semen Portland 6.9000 Zak 69,750.00 481,275.00
Pasir Beton 0.5915 m3 231,885.00 137,159.98
Kerikil 0.7497 m3 220,860.00 165,578.74
Air Tawar 215.0000 Liter 135.00 29,025.00
Jumlah Bahan 813,038.72
Total ( Tenaga + Bahan) 989,968.72
Overhead 0.0000 0.00
H.S.P 989,968.72
Tenaga
Mandor 0.0830 O.H 110,000.00 9,130.00
Kepala Tukang 0.0280 O.H 100,000.00 2,800.00
Tukang Batu 0.2750 O.H 90,000.00 24,750.00
Pekerja 1.6500 O.H 85,000.00 140,250.00
Jumlah Tenaga 176,930.00
Bahan
Semen Portland 7.4750 Zak 69,750.00 521,381.25
Pasir Beton 0.5708 m3 231,885.00 132,359.96
Kerikil 0.7534 m3 220,860.00 166,395.92
Air Tawar 215.0000 Liter 135.00 29,025.00
Jumlah Bahan 849,162.13
Total ( Tenaga + Bahan) 1,026,092.13
Overhead 0.0000 0.00
H.S.P 1,026,092.13
Tenaga
Mandor 0.0830 O.H 110,000.00 9,130.00
Kepala Tukang 0.0280 O.H 100,000.00 2,800.00
Tukang Batu 0.2750 O.H 90,000.00 24,750.00
Pekerja 1.6500 O.H 85,000.00 140,250.00
Jumlah Tenaga 176,930.00
Bahan
Semen Portland 8.1500 Zak 69,750.00 568,462.50
Pasir Beton 0.5428 m3 231,885.00 125,867.18
Kerikil 0.7623 m3 220,860.00 168,361.58
Air Tawar 215.0000 Liter 135.00 29,025.00
Jumlah Bahan 891,716.26
Total ( Tenaga + Bahan) 1,068,646.26
Overhead 0.0000 0.00
H.S.P 1,068,646.26
Tenaga
Mandor 0.0830 O.H 110,000.00 9,130.00
Kepala Tukang 0.0280 O.H 100,000.00 2,800.00
Tukang Batu 0.2750 O.H 90,000.00 24,750.00
Pekerja 1.6500 O.H 85,000.00 140,250.00
Jumlah Tenaga 176,930.00
Bahan
Semen Portland 10.3250 Zak 69,750.00 720,168.75
Pasir Beton 0.4864 m3 231,885.00 112,788.86
Kerikil 0.7562 m3 220,860.00 167,014.33
Air Tawar 215.0000 Liter 135.00 29,025.00
Jumlah Bahan 1,028,996.95
Total ( Tenaga + Bahan) 1,205,926.95
Overhead 0.0000 0.00
H.S.P 1,205,926.95
Tenaga
Mandor 0.2650 O.H 110,000.00 29,150.00
Kepala Tukang 0.2620 O.H 100,000.00 26,200.00
Tukang Besi 1.0500 O.H 90,000.00 94,500.00
Tukang Kayu 1.3000 O.H 90,000.00 117,000.00
Tukang Batu 0.2750 O.H 90,000.00 24,750.00
Pekerja 5.3000 O.H 85,000.00 450,500.00
Jumlah Tenaga 742,100.00
Bahan
Kayu Bekisting Meranti 0.2000 m3 5,230,755.00 1,046,151.00
Paku Biasa 2" - 5" 1.5000 Kg 18,900.00 28,350.00
Minyak Bekisting 0.4000 liter 13,770.00 5,508.00
Besi Beton Polos 157.5000 Kg 11,745.00 1,849,837.50
Kawat Beton 0.0900 Roll 389,025.00 35,012.25
Semen Portland 8.4000 Zak 69,750.00 585,900.00
Pasir Beton 0.5400 m3 231,885.00 125,217.90
Kerikil 0.8100 m3 220,860.00 178,896.60
Jumlah Bahan 3,854,873.25
Total ( Tenaga + Bahan) 4,596,973.25
Overhead 0.0000 0.00
H.S.P 4,596,973.25
Tenaga
Mandor 0.2830 O.H 110,000.00 31,130.00
Kepala Tukang 0.3230 O.H 100,000.00 32,300.00
Tukang Besi 1.4000 O.H 90,000.00 126,000.00
Tukang Kayu 1.5600 O.H 90,000.00 140,400.00
Tukang Batu 0.2750 O.H 90,000.00 24,750.00
Pekerja 5.6500 O.H 85,000.00 480,250.00
Jumlah Tenaga 834,830.00
Bahan
Kayu Bekisting Meranti 0.2700 m3 5,230,755.00 1,412,303.85
Paku Biasa 2" - 5" 2.0000 Kg 18,900.00 37,800.00
Minyak Bekisting 0.6000 liter 13,770.00 8,262.00
Besi Beton Polos 210.0000 Kg 11,745.00 2,466,450.00
Kawat Beton 0.1200 Roll 389,025.00 46,683.00
Semen Portland 8.4000 Zak 69,750.00 585,900.00
Pasir Beton 0.5400 m3 231,885.00 125,217.90
Kerikil 0.8100 m3 220,860.00 178,896.60
Jumlah Bahan 4,861,513.35
Total ( Tenaga + Bahan) 5,696,343.35
Overhead 0.0000 0.00
H.S.P 5,696,343.35
Tenaga
Mandor 0.2650 O.H 110,000.00 29,150.00
Kepala Tukang 0.2620 O.H 100,000.00 26,200.00
Tukang Besi 1.0500 O.H 90,000.00 94,500.00
Tukang Kayu 1.3000 O.H 90,000.00 117,000.00
Tukang Batu 0.2750 O.H 90,000.00 24,750.00
Pekerja 5.3000 O.H 85,000.00 450,500.00
Jumlah Tenaga 742,100.00
Bahan
Kayu Bekisting Meranti 0.2400 m3 5,230,755.00 1,255,381.20
Paku Biasa 2" - 5" 3.2000 Kg 18,900.00 60,480.00
Minyak Bekisting 1.6000 liter 13,770.00 22,032.00
Besi Beton Polos 157.5000 Kg 11,745.00 1,849,837.50
Kawat Beton 0.0900 Roll 389,025.00 35,012.25
Semen Portland 8.4000 Zak 69,750.00 585,900.00
Pasir Beton 0.5400 m3 231,885.00 125,217.90
Kerikil 0.8100 m3 220,860.00 178,896.60
Kayu Meranti Balok 0.1600 m3 6,077,970.00 972,475.20
Multipleks 9 Mm 2.8000 Lembar 156,960.00 439,488.00
Dolken Kayu Gelam Dia 8-10 Cm, Pjg 4 M 24.0000 Batang 21,510.00 516,240.00
Jumlah Bahan 6,040,960.65
Total ( Tenaga + Bahan) 6,783,060.65
Overhead 0.0000 0.00
H.S.P 6,783,060.65
Tenaga
Mandor 0.0030 O.H 110,000.00 330.00
Kepala Tukang 0.0060 O.H 100,000.00 600.00
Tukang Besi 0.0200 O.H 90,000.00 1,800.00
Tukang Kayu 0.0200 O.H 90,000.00 1,800.00
Tukang Batu 0.0200 O.H 90,000.00 1,800.00
Pekerja 0.0600 O.H 85,000.00 5,100.00
Jumlah Tenaga 11,430.00
Bahan
Kayu Bekisting Meranti 0.0020 m3 5,230,755.00 10,461.51
Paku Biasa 2" - 5" 0.0100 Kg 18,900.00 189.00
Besi Beton Polos 3.0000 Kg 11,745.00 35,235.00
Kawat Beton 0.0180 Roll 389,025.00 7,002.45
Semen Portland 0.1000 Zak 69,750.00 6,975.00
Pasir Beton 0.0060 m3 231,885.00 1,391.31
Kerikil 0.0090 m3 220,860.00 1,987.74
Jumlah Bahan 63,242.01
Total ( Tenaga + Bahan) 74,672.01
Overhead 0.0000 0.00
H.S.P 74,672.01
H PEKERJAAN BEKISTING
1 m2 Pekerjaan Pasang Bekisting Untuk Pondasi m2
Tenaga
Mandor 0.0260 O.H 110,000.00 2,860.00
Kepala Tukang 0.0260 O.H 100,000.00 2,600.00
Tukang Kayu 0.2600 O.H 90,000.00 23,400.00
Pekerja 0.5200 O.H 85,000.00 44,200.00
Jumlah Tenaga 73,060.00
Bahan
Kayu Bekisting Meranti 0.0400 m3 5,230,755.00 209,230.20
Paku Biasa 2" - 5" 0.3000 Kg 18,900.00 5,670.00
Minyak Bekisting 0.1000 liter 13,770.00 1,377.00
Jumlah Bahan 216,277.20
Total ( Tenaga + Bahan) 289,337.20
Overhead 0.0000 0.00
H.S.P 289,337.20
Tenaga
Mandor 0.0165 O.H 110,000.00 1,815.00
Kepala Tukang 0.0165 O.H 100,000.00 1,650.00
Tukang Kayu 0.1650 O.H 90,000.00 14,850.00
Pekerja 0.3300 O.H 85,000.00 28,050.00
Jumlah Tenaga 46,365.00
Bahan
Kayu Bekisting Meranti 0.0200 m3 5,230,755.00 104,615.10
Paku Biasa 2" - 5" 0.2000 Kg 18,900.00 3,780.00
Minyak Bekisting 0.1000 liter 13,770.00 1,377.00
Balok Kayu Meranti 0.0090 m3 6,077,970.00 54,701.73
Multipleks 9 Mm 0.1750 Lembar 156,960.00 27,468.00
Dolken Kayu Gelam Dia 8-10 Cm, Pjg 4 M 1.0000 Batang 21,510.00 21,510.00
Jumlah Bahan 213,451.83
Total ( Tenaga + Bahan) 259,816.83
Overhead 0.0000 0.00
H.S.P 259,816.83
Tenaga
Mandor 0.0165 O.H 110,000.00 1,815.00
Kepala Tukang 0.0165 O.H 100,000.00 1,650.00
Tukang Kayu 0.1650 O.H 90,000.00 14,850.00
Pekerja 0.3300 O.H 85,000.00 28,050.00
Jumlah Tenaga 46,365.00
Bahan
Kayu Bekisting Meranti 0.0200 m3 5,230,755.00 104,615.10
Paku Biasa 2" - 5" 0.2000 Kg 18,900.00 3,780.00
Minyak Bekisting 0.1000 liter 13,770.00 1,377.00
Balok Kayu Meranti 0.0075 m3 6,077,970.00 45,584.78
Multipleks 9 Mm 0.1750 Lembar 156,960.00 27,468.00
Dolken Kayu Gelam Dia 8-10 Cm, Pjg 4 M 3.0000 Batang 21,510.00 64,530.00
Jumlah Bahan 247,354.88
Total ( Tenaga + Bahan) 293,719.88
Overhead 0.0000 0.00
H.S.P 293,719.88
Tenaga
Mandor 0.0165 O.H 110,000.00 1,815.00
Kepala Tukang 0.0165 O.H 100,000.00 1,650.00
Tukang Kayu 0.1650 O.H 90,000.00 14,850.00
Pekerja 0.3300 O.H 85,000.00 28,050.00
Jumlah Tenaga 46,365.00
Bahan
Kayu Bekisting Meranti 0.0150 m3 5,230,755.00 78,461.33
Paku Biasa 2" - 5" 0.2000 Kg 18,900.00 3,780.00
Minyak Bekisting 0.0750 liter 13,770.00 1,032.75
Balok Kayu Meranti 0.0075 m3 6,077,970.00 45,584.78
Multipleks 9 Mm 0.1750 Lembar 156,960.00 27,468.00
Dolken Kayu Gelam Dia 8-10 Cm, Pjg 4 M 1.0000 Batang 21,510.00 21,510.00
Jumlah Bahan 177,836.85
Total ( Tenaga + Bahan) 224,201.85
Overhead 0.0000 0.00
H.S.P 224,201.85
Tenaga
Mandor 0.0110 O.H 110,000.00 1,210.00
Kepala Tukang 0.0110 O.H 100,000.00 1,100.00
Tukang Kayu 0.1100 O.H 90,000.00 9,900.00
Pekerja 0.2200 O.H 85,000.00 18,700.00
Jumlah Tenaga 30,910.00
Bahan
Kayu Bekisting Meranti 0.0134 m3 5,230,755.00 70,092.12
Paku Biasa 2" - 5" 0.1334 Kg 18,900.00 2,521.26
Minyak Bekisting 0.0667 liter 13,770.00 918.46
Balok Kayu Meranti 0.0060 m3 6,077,970.00 36,467.82
Multipleks 9 Mm 0.1167 Lembar 156,960.00 18,317.23
Dolken Kayu Gelam Dia 8-10 Cm, Pjg 4 M 0.6667 Batang 21,510.00 14,340.72
Jumlah Bahan 142,657.61
Total ( Tenaga + Bahan) 173,567.61
Overhead 0.0000 0.00
H.S.P 173,567.61
Tenaga
Mandor 0.0110 O.H 110,000.00 1,210.00
Kepala Tukang 0.0110 O.H 100,000.00 1,100.00
Tukang Kayu 0.1100 O.H 90,000.00 9,900.00
Pekerja 0.2200 O.H 85,000.00 18,700.00
Jumlah Tenaga 30,910.00
Bahan
Kayu Bekisting Meranti 0.0100 m3 5,230,755.00 52,307.55
Paku Biasa 2" - 5" 0.1334 Kg 18,900.00 2,521.26
Minyak Bekisting 0.0667 liter 13,770.00 918.46
Balok Kayu Meranti 0.0067 m3 6,077,970.00 40,722.40
Multipleks 9 Mm 0.1167 Lembar 156,960.00 18,317.23
Dolken Kayu Gelam Dia 8-10 Cm, Pjg 4 M 1.0000 Batang 21,510.00 21,510.00
Jumlah Bahan 136,296.90
Total ( Tenaga + Bahan) 167,206.90
Overhead 0.0000 0.00
H.S.P 167,206.90
I PEKERJAAN DINDING
1 m2 Pekerjaan Pemasangan Batu Merah Tbl 1 m2
Bata (1 Pc : 2 Ps)
Tenaga
Mandor 0.0300 O.H 110,000.00 3,300.00
Kepala Tukang 0.0200 O.H 100,000.00 2,000.00
Tukang Batu 0.2000 O.H 90,000.00 18,000.00
Pekerja 0.6000 O.H 85,000.00 51,000.00
Jumlah Tenaga 74,300.00
Bahan
Semen Portland 1.0875 Zak 69,750.00 75,853.13
Pasir Pasang 0.0800 m3 220,275.00 17,622.00
Bata Merah Uk.5 X 11 X 22 140.0000 buah 855.00 119,700.00
Jumlah Bahan 213,175.13
Total ( Tenaga + Bahan) 287,475.13
Overhead 0.0000 0.00
H.S.P 287,475.13
Tenaga
Mandor 0.0300 O.H 110,000.00 3,300.00
Kepala Tukang 0.0200 O.H 100,000.00 2,000.00
Tukang Batu 0.2000 O.H 90,000.00 18,000.00
Pekerja 0.6000 O.H 85,000.00 51,000.00
Jumlah Tenaga 74,300.00
Bahan
Semen Portland 0.8238 Zak 69,750.00 57,460.05
Pasir Pasang 0.0910 m3 220,275.00 20,045.03
Bata Merah Uk.5 X 11 X 22 140.0000 buah 855.00 119,700.00
Jumlah Bahan 197,205.08
Total ( Tenaga + Bahan) 271,505.08
Overhead 0.0000 0.00
H.S.P 271,505.08
Tenaga
Mandor 0.0150 O.H 110,000.00 1,650.00
Kepala Tukang 0.0100 O.H 100,000.00 1,000.00
Tukang Batu 0.1000 O.H 90,000.00 9,000.00
Pekerja 0.3000 O.H 85,000.00 25,500.00
Jumlah Tenaga 37,150.00
Bahan
Semen Portland 0.3593 Zak 69,750.00 25,061.18
Pasir Pasang 0.0400 m3 220,275.00 8,811.00
Bata Merah Uk.5 X 11 X 22 70.0000 buah 855.00 59,850.00
Jumlah Bahan 93,722.18
Total ( Tenaga + Bahan) 130,872.18
Overhead 0.0000 0.00
H.S.P 130,872.18
Tenaga
Mandor 0.0300 O.H 110,000.00 3,300.00
Kepala Tukang 0.0200 O.H 100,000.00 2,000.00
Tukang Batu 0.2000 O.H 90,000.00 18,000.00
Pekerja 0.6000 O.H 85,000.00 51,000.00
Jumlah Tenaga 74,300.00
Bahan
Semen Portland 0.6638 Zak 69,750.00 46,300.05
Pasir Pasang 0.0930 m3 220,275.00 20,485.58
Bata Merah Uk.5 X 11 X 22 140.0000 buah 855.00 119,700.00
Jumlah Bahan 186,485.63
Total ( Tenaga + Bahan) 260,785.63
Overhead 0.0000 0.00
H.S.P 260,785.63
Tenaga
Mandor 0.0150 O.H 110,000.00 1,650.00
Kepala Tukang 0.0100 O.H 100,000.00 1,000.00
Tukang Batu 0.1000 O.H 90,000.00 9,000.00
Pekerja 0.3000 O.H 85,000.00 25,500.00
Jumlah Tenaga 37,150.00
Bahan
Semen Portland 0.2875 Zak 69,750.00 20,053.13
Pasir Pasang 0.0430 m3 220,275.00 9,471.83
Bata Merah Uk.5 X 11 X 22 70.0000 buah 855.00 59,850.00
Jumlah Bahan 89,374.95
Total ( Tenaga + Bahan) 126,524.95
Overhead 0.0000 0.00
H.S.P 126,524.95
Tenaga
Mandor 0.0300 O.H 110,000.00 3,300.00
Kepala Tukang 0.0200 O.H 100,000.00 2,000.00
Tukang Batu 0.2000 O.H 90,000.00 18,000.00
Pekerja 0.6000 O.H 85,000.00 51,000.00
Jumlah Tenaga 74,300.00
Bahan
Semen Portland 0.5550 Zak 69,750.00 38,711.25
Pasir Pasang 0.1020 m3 220,275.00 22,468.05
Bata Merah Uk.5 X 11 X 22 140.0000 buah 855.00 119,700.00
Jumlah Bahan 180,879.30
Total ( Tenaga + Bahan) 255,179.30
Overhead 0.0000 0.00
H.S.P 255,179.30
Tenaga
Mandor 0.0150 O.H 110,000.00 1,650.00
Kepala Tukang 0.0100 O.H 100,000.00 1,000.00
Tukang Batu 0.1000 O.H 90,000.00 9,000.00
Pekerja 0.3000 O.H 85,000.00 25,500.00
Jumlah Tenaga 37,150.00
Bahan
Semen Portland 0.2420 Zak 69,750.00 16,879.50
Pasir Pasang 0.0450 m3 220,275.00 9,912.38
Bata Merah Uk.5 X 11 X 22 70.0000 buah 855.00 59,850.00
Jumlah Bahan 86,641.88
Total ( Tenaga + Bahan) 123,791.88
Overhead 0.0000 0.00
H.S.P 123,791.88
Tenaga
Mandor 0.0300 O.H 110,000.00 3,300.00
Kepala Tukang 0.0200 O.H 100,000.00 2,000.00
Tukang Batu 0.2000 O.H 90,000.00 18,000.00
Pekerja 0.6000 O.H 85,000.00 51,000.00
Jumlah Tenaga 74,300.00
Bahan
Semen Portland 0.4625 Zak 69,750.00 32,259.38
Pasir Pasang 0.1220 m3 220,275.00 26,873.55
Bata Merah Uk.5 X 11 X 22 140.0000 buah 855.00 119,700.00
Jumlah Bahan 178,832.93
Total ( Tenaga + Bahan) 253,132.93
Overhead 0.0000 0.00
H.S.P 253,132.93
Tenaga
Mandor 0.0150 O.H 110,000.00 1,650.00
Kepala Tukang 0.0100 O.H 100,000.00 1,000.00
Tukang Batu 0.1000 O.H 90,000.00 9,000.00
Pekerja 0.3000 O.H 85,000.00 25,500.00
Jumlah Tenaga 37,150.00
Bahan
Semen Portland 0.2080 Zak 69,750.00 14,508.00
Pasir Pasang 0.0490 m3 220,275.00 10,793.48
Bata Merah Uk.5 X 11 X 22 70.0000 buah 855.00 59,850.00
Jumlah Bahan 85,151.48
Total ( Tenaga + Bahan) 122,301.48
Overhead 0.0000 0.00
H.S.P 122,301.48
J PEKERJAAN PLESTERAN
1 m2 Pekerjaan Plesteran 1 Pc : 1 Ps Tebal 15 Mm m2
Tenaga
Mandor 0.0150 O.H 110,000.00 1,650.00
Kepala Tukang 0.0150 O.H 100,000.00 1,500.00
Tukang Batu 0.1500 O.H 90,000.00 13,500.00
Pekerja 0.3000 O.H 85,000.00 25,500.00
Jumlah Tenaga 42,150.00
Bahan
Semen Portland 0.3876 Zak 69,750.00 27,035.10
Pasir Pasang 0.0160 m3 220,275.00 3,524.40
Jumlah Bahan 30,559.50
Total ( Tenaga + Bahan) 72,709.50
Overhead 0.0000 0.00
H.S.P 72,709.50
Tenaga
Mandor 0.0040 O.H 110,000.00 440.00
Kepala Tukang 0.0040 O.H 100,000.00 400.00
Tukang Batu 0.0350 O.H 90,000.00 3,150.00
Pekerja 0.0700 O.H 85,000.00 5,950.00
Jumlah Tenaga 9,940.00
Bahan
Semen Portland 0.0400 Zak 69,750.00 2,790.00
Jumlah Bahan 2,790.00
Total ( Tenaga + Bahan) 12,730.00
Overhead 0.0000 0.00
H.S.P 12,730.00
1 m2 Pekerjaan Acian m2
Tenaga
Mandor 0.0100 O.H 110,000.00 1,100.00
Kepala Tukang 0.0100 O.H 100,000.00 1,000.00
Tukang Batu 0.1000 O.H 90,000.00 9,000.00
Pekerja 0.2000 O.H 85,000.00 17,000.00
Jumlah Tenaga 28,100.00
Bahan
Semen Portland 0.0813 Zak 69,750.00 5,670.68
Jumlah Bahan 5,670.68
Total ( Tenaga + Bahan) 33,770.68
Overhead 0.0000 0.00
H.S.P 33,770.68
K PENUTUP LANTAI
1 m2 Pekerjaan Pasang Lantai Granit Ukuran
60X60 Cm m2
Tenaga
Mandor 0.0120 O.H 110,000.00 1,320.00
Kepala Tukang 0.0120 O.H 100,000.00 1,200.00
Tukang Batu 0.1200 O.H 90,000.00 10,800.00
Pekerja 0.2400 O.H 85,000.00 20,400.00
Jumlah Tenaga 33,720.00
Bahan
Ubin Granit 60X60 1.0500 m2 377,775.00 396,663.75
Semen Portland 0.2400 Zak 69,750.00 16,740.00
Pasir Pasang 0.0450 m3 220,275.00 9,912.38
Semen Warna 1.5000 Kg 13,410.00 20,115.00
Jumlah Bahan 443,431.13
Total ( Tenaga + Bahan) 477,151.13
Overhead 0.0000 0.00
H.S.P 477,151.13
Tenaga
Mandor 0.0350 O.H 110,000.00 3,850.00
Kepala Tukang 0.0350 O.H 100,000.00 3,500.00
Tukang Batu 0.3500 O.H 90,000.00 31,500.00
Pekerja 0.7000 O.H 85,000.00 59,500.00
Jumlah Tenaga 98,350.00
Bahan
Semen Portland 0.2450 Zak 69,750.00 17,088.75
Semen Warna 1.3000 Kg 13,410.00 17,433.00
Pasir Pasang 0.0450 m3 220,275.00 9,912.38
Keramik Motif 40X40 Cm 1.0608 m2 50,490.00 53,559.79
Jumlah Bahan 97,993.92
Total ( Tenaga + Bahan) 196,343.92
Overhead 0.0000 0.00
H.S.P 196,343.92
Tenaga
Mandor 0.0350 O.H 110,000.00 3,850.00
Kepala Tukang 0.0350 O.H 100,000.00 3,500.00
Tukang Batu 0.3500 O.H 90,000.00 31,500.00
Pekerja 0.7000 O.H 85,000.00 59,500.00
Jumlah Tenaga 98,350.00
Bahan
Semen Portland 0.2048 Zak 69,750.00 14,284.80
Semen Warna 0.6500 Kg 13,410.00 8,716.50
Pasir Pasang 0.0450 m3 220,275.00 9,912.38
Marmer Tulungagung; 30 X 60 Cm 1.0600 m2 377,775.00 400,441.50
Jumlah Bahan 433,355.18
Total ( Tenaga + Bahan) 531,705.18
Overhead 0.0000 0.00
H.S.P 531,705.18
L PENUTUP DINDING
1 m2 Pekerjaan Pasangan Dinding Keramik Polos m2
Uk.20X25 Cm
Tenaga
Mandor 0.0450 O.H 110,000.00 4,950.00
Kepala Tukang 0.0450 O.H 100,000.00 4,500.00
Tukang Batu 0.4500 O.H 90,000.00 40,500.00
Pekerja 0.9000 O.H 85,000.00 76,500.00
Jumlah Tenaga 126,450.00
Bahan
Semen Portland 0.2325 Zak 69,750.00 16,216.88
Semen Warna 1.9400 Kg 13,410.00 26,015.40
Pasir Pasang 0.0180 m3 220,275.00 3,964.95
Dinding Keramik 20X25 Cm (Polos) 1.0500 m2 107,730.00 113,116.50
Jumlah Bahan 159,313.73
Total ( Tenaga + Bahan) 285,763.73
Overhead 0.0000 0.00
H.S.P 285,763.73
Tenaga
Mandor 0.0450 O.H 110,000.00 4,950.00
Kepala Tukang 0.0450 O.H 100,000.00 4,500.00
Tukang Batu 0.4500 O.H 90,000.00 40,500.00
Pekerja 0.9000 O.H 85,000.00 76,500.00
Jumlah Tenaga 126,450.00
Bahan
Semen Portland 0.2325 Zak 69,750.00 16,216.88
Semen Warna 1.9400 Kg 13,410.00 26,015.40
Pasir Pasang 0.0180 m3 220,275.00 3,964.95
Dinding Keramik 20X25 Cm (Motif) 1.0500 m2 120,915.00 126,960.75
Jumlah Bahan 173,157.98
Total ( Tenaga + Bahan) 299,607.98
Overhead 0.0000 0.00
H.S.P 299,607.98
Tenaga
Mandor 0.0450 O.H 110,000.00 4,950.00
Kepala Tukang 0.0450 O.H 100,000.00 4,500.00
Tukang Batu 0.4500 O.H 90,000.00 40,500.00
Pekerja 0.9000 O.H 85,000.00 76,500.00
Jumlah Tenaga 126,450.00
Bahan
Semen Portland 0.2325 Zak 69,750.00 16,216.88
Semen Warna 1.9400 Kg 13,410.00 26,015.40
Pasir Pasang 0.0180 m3 220,275.00 3,964.95
Dinding Keramik 20X20 Cm (Motif) 1.0500 m2 50,985.00 53,534.25
Jumlah Bahan 99,731.48
Total ( Tenaga + Bahan) 226,181.48
Overhead 0.0000 0.00
H.S.P 226,181.48
Tenaga
Mandor 0.0400 O.H 110,000.00 4,400.00
Kepala Tukang 0.2400 O.H 100,000.00 24,000.00
Tukang Kayu 2.4000 O.H 90,000.00 216,000.00
Pekerja 0.8000 O.H 85,000.00 68,000.00
Jumlah Tenaga 312,400.00
Bahan
Plywood Uk. 4' X 8' X 4 Mm 1.0000 Lembar 113,715.00 113,715.00
Kayu Jati Papan 0.0256 m3 19,150,290.00 490,247.42
Paku Biasa 0.0300 kg 18,900.00 567.00
Lem Kayu 0.5000 kg 29,070.00 14,535.00
Jumlah Bahan 619,064.42
Total ( Tenaga + Bahan) 931,464.42
Overhead 0.0000 0.00
H.S.P 931,464.42
Tenaga
Mandor 0.0400 O.H 110,000.00 4,400.00
Kepala Tukang 0.2400 O.H 100,000.00 24,000.00
Tukang Kayu 2.4000 O.H 90,000.00 216,000.00
Pekerja 0.8000 O.H 85,000.00 68,000.00
Jumlah Tenaga 312,400.00
Bahan
Teakwood Uk. 4' X 8' X 4 Mm 1.0000 lembar 127,890.00 127,890.00
Kayu Jati Papan 0.0250 m3 19,150,290.00 478,757.25
Paku Biasa 0.0300 kg 18,900.00 567.00
Lem Kayu 0.3000 kg 29,070.00 8,721.00
Jumlah Bahan 615,935.25
Total ( Tenaga + Bahan) 928,335.25
Overhead 0.0000 0.00
H.S.P 928,335.25
O LISTPLANK
1 m' Pekerjaan Pasang Listplank Kayu Jati 3/20 m'
Tenaga
Mandor 0.0050 O.H 110,000.00 550.00
Kepala Tukang 0.0200 O.H 100,000.00 2,000.00
Tukang Kayu 0.2000 O.H 90,000.00 18,000.00
Pekerja 0.1000 O.H 85,000.00 8,500.00
Jumlah Tenaga 29,050.00
Bahan
Kayu Jati Papan 0.0108 m3 19,150,290.00 206,823.13
Paku Biasa 0.1000 kg 18,900.00 1,890.00
Jumlah Bahan 208,713.13
Total ( Tenaga + Bahan) 237,763.13
Overhead 0.0000 0.00
H.S.P 237,763.13
P PARTISI KAYU
1 m2 Pekerjaan Pasang Dinding Pemisah Teakwood Rangkap Rangka
Kayu Jati m2
Tenaga
Mandor 0.0080 O.H 110,000.00 880.00
Kepala Tukang 0.0450 O.H 100,000.00 4,500.00
Tukang Kayu 0.4500 O.H 90,000.00 40,500.00
Pekerja 0.1500 O.H 85,000.00 12,750.00
Jumlah Tenaga 58,630.00
Bahan
Kayu Jati Balok 0.0280 m3 19,150,290.00 536,208.12
Teakwood 4 Mm, Uk. 120 X 240 Cm 0.8600 Lembar 127,890.00 109,985.40
Paku Biasa 0.1500 kg 18,900.00 2,835.00
Lem Kayu 0.5600 kg 29,070.00 16,279.20
Jumlah Bahan 665,307.72
Total ( Tenaga + Bahan) 723,937.72
Overhead 0.0000 0.00
H.S.P 723,937.72
Tenaga
Mandor 0.0800 O.H 110,000.00 8,800.00
Kepala Tukang 0.0800 O.H 100,000.00 8,000.00
Tukang Kayu 0.0750 O.H 90,000.00 6,750.00
Pekerja 0.1500 O.H 85,000.00 12,750.00
Jumlah Tenaga 36,300.00
Bahan
Genteng Keramik Glazzur ex. Kanmuri 14.5000 Buah 11,070.00 160,515.00
Jumlah Bahan 160,515.00
Total ( Tenaga + Bahan) 196,815.00
Overhead 0.0000 0.00
H.S.P 196,815.00
Tenaga
Mandor 0.0050 O.H 110,000.00 550.00
Kepala Tukang 0.0050 O.H 100,000.00 500.00
Tukang Kayu 0.0500 O.H 90,000.00 4,500.00
Pekerja 0.1000 O.H 85,000.00 8,500.00
Jumlah Tenaga 14,050.00
Bahan
Gypsum Board Tb. 9 Mm 0.3640 Lembar 86,985.00 31,662.54
Paku Skrup 0.1100 Kg 24,390.00 2,682.90
Jumlah Bahan 34,345.44
Total ( Tenaga + Bahan) 48,395.44
Overhead 0.0000 0.00
H.S.P 48,395.44
R SANITASI
Pekerjaan Pemasangan 1 Buah Kloset Duduk Buah
Tenaga
Mandor 0.1600 O.H 110,000.00 17,600.00
Kepala Tukang 0.0010 O.H 100,000.00 100.00
Tukang Batu 1.1000 O.H 90,000.00 99,000.00
Pekerja 3.3000 O.H 85,000.00 280,500.00
Jumlah Tenaga 397,200.00
Bahan
Kloset Duduk Setara Ina Komplit 1.0000 Buah 1,453,005.00 1,453,005.00
Peralatan (6% Dari Harga Bahan) 0.0600 Set 1,453,005.00 87,180.30
Jumlah Bahan 1,540,185.30
Total ( Tenaga + Bahan) 1,937,385.30
Overhead 0.0000 0.00
H.S.P 1,937,385.30
Tenaga
Mandor 0.1600 O.H 110,000.00 17,600.00
Kepala Tukang 1.5000 O.H 100,000.00 150,000.00
Tukang Batu 1.5000 O.H 90,000.00 135,000.00
Pekerja 1.0000 O.H 85,000.00 85,000.00
Jumlah Tenaga 387,600.00
Bahan
Kloset Jongkok Porselen 1.0000 Buah 174,375.00 174,375.00
Semen Portland 0.1500 Zak 69,750.00 10,462.50
Pasir Pasang 0.0100 m3 220,275.00 2,202.75
Jumlah Bahan 187,040.25
Total ( Tenaga + Bahan) 574,640.25
Overhead 0.0000 0.00
H.S.P 574,640.25
Tenaga
Mandor 0.0130 O.H 110,000.00 1,430.00
Kepala Tukang 0.0250 O.H 100,000.00 2,500.00
Tukang Besi 0.2500 O.H 90,000.00 22,500.00
Pekerja 0.2500 O.H 85,000.00 21,250.00
Jumlah Tenaga 47,680.00
Bahan
Rangka Metal Hollow 40.40.2 Mm 0.8750 Btg 32,760.00 28,665.00
Kalsiboard 0.8600 Lembar 103,770.00 89,242.20
Accesorries 0.2500 Set 32,760.00 8,190.00
Jumlah Bahan 126,097.20
Total ( Tenaga + Bahan) 173,777.20
Overhead 0.0000 0.00
H.S.P 173,777.20
Tenaga
Mandor 0.0500 O.H 110,000.00 5,500.00
Kepala Tukang 0.0100 O.H 100,000.00 1,000.00
Tukang Besi 0.4500 O.H 90,000.00 40,500.00
Pekerja 0.2000 O.H 85,000.00 17,000.00
Jumlah Tenaga 64,000.00
Bahan
C-75 , 0.8 0.2480 Batang 93,015.00 23,067.72
C-75 , 0.6 0.3720 Batang 89,865.00 33,429.78
Baut (Screw Driver) 38.0000 Buah 1,350.00 51,300.00
Dynabolt 1.6000 Buah 11,610.00 18,576.00
Reng 0.9000 Batang 43,515.00 39,163.50
Talang Jurai 0.1240 m' 40,590.00 5,033.16
Jumlah Bahan 170,570.16
Total ( Tenaga + Bahan) 234,570.16
Overhead 0.0000 0.00
H.S.P 234,570.16
Tenaga
Mandor 0.0050 O.H 110,000.00 550.00
Kepala Tukang 0.0090 O.H 100,000.00 900.00
Tukang Kayu 0.0850 O.H 90,000.00 7,650.00
Pekerja 0.0850 O.H 85,000.00 7,225.00
Jumlah Tenaga 16,325.00
Bahan
Profil Alluminium 4.4000 m 100,305.00 441,342.00
Kaca Rayban 5 Mm 1.1000 m2 116,280.00 127,908.00
Sealant 0.2700 Tube 13,950.00 3,766.50
Jumlah Bahan 573,016.50
Total ( Tenaga + Bahan) 589,341.50
Overhead 0.0000 0.00
H.S.P 589,341.50
Tenaga
Mandor 0.0080 O.H 110,000.00 880.00
Kepala Tukang 0.0080 O.H 100,000.00 800.00
Tukang Besi 0.0750 O.H 90,000.00 6,750.00
Pekerja 0.1500 O.H 85,000.00 12,750.00
Jumlah Tenaga 21,180.00
Bahan
Besi Hollow 40.40 1.7242 Btg 188,100.00 324,322.02
Polycarbonate t. 8 mm 0.0404 m2 3,719,655.00 150,274.06
Paku payung 6.0000 bh 1,080.00 6,480.00
Jumlah Bahan 481,076.08
Total ( Tenaga + Bahan) 502,256.08
Overhead 0.0000 0.00
H.S.P 502,256.08
Tenaga
Mandor 0.0030 O.H 110,000.00 330.00
Kepala Tukang 0.0600 O.H 100,000.00 6,000.00
Tukang Kayu 0.6000 O.H 90,000.00 54,000.00
Pekerja 0.0600 O.H 85,000.00 5,100.00
Jumlah Tenaga 65,430.00
Bahan
Kunci Tanam Antik 1.0000 Buah 144,945.00 144,945.00
Jumlah Bahan 144,945.00
Total ( Tenaga + Bahan) 210,375.00
Overhead 0.0000 0.00
H.S.P 210,375.00
Tenaga
Mandor 0.0005 O.H 110,000.00 55.00
Kepala Tukang 0.0100 O.H 100,000.00 1,000.00
Tukang Kayu 0.1000 O.H 90,000.00 9,000.00
Pekerja 0.0100 O.H 85,000.00 850.00
Jumlah Tenaga 10,905.00
Bahan
Engsel Jendela Kupu-Kupu Kuningan 2.5" 1.0000 Stel 29,205.00 29,205.00
Jumlah Bahan 29,205.00
Total ( Tenaga + Bahan) 40,110.00
Overhead 0.0000 0.00
H.S.P 40,110.00
Tenaga
Mandor 0.0030 O.H 110,000.00 330.00
Kepala Tukang Cat 0.0060 O.H 100,000.00 600.00
Tukang Cat 0.0090 O.H 90,000.00 810.00
Pekerja 0.0700 O.H 85,000.00 5,950.00
Jumlah Tenaga 7,690.00
Bahan
Cat Meni Kayu 0.2000 Kg 34,785.00 6,957.00
Plamur Kayu 0.1500 Kg 32,940.00 4,941.00
Kuas 0.0100 bh 11,790.00 117.90
Pengencer 0.0300 Kg 26,685.00 800.55
Ampelas 0.2000 lembar 5,040.00 1,008.00
Cat Kayu Dasar 0.1700 Kg 69,750.00 11,857.50
Cat Kayu Penutup 2 Kali 0.2600 Kg 69,750.00 18,135.00
Jumlah Bahan 43,816.95
Total ( Tenaga + Bahan) 43,934.85
Overhead 0.0000 0.00
H.S.P 43,934.85
Tenaga
Mandor 0.0030 O.H 110,000.00 330.00
Pekerja 0.1500 O.H 85,000.00 12,750.00
Jumlah Tenaga 13,080.00
Bahan
Soda Api 0.0500 Kg 16,830.00 841.50
Jumlah Bahan 841.50
Total ( Tenaga + Bahan) 13,921.50
Overhead 0.0000 0.00
H.S.P 13,921.50
Tenaga
Mandor 0.0100 O.H 110,000.00 1,100.00
Kepala Tukang 0.0010 O.H 100,000.00 100.00
Tukang Cat 0.0070 O.H 90,000.00 630.00
Pekerja 0.0390 O.H 85,000.00 3,315.00
Jumlah Tenaga 5,145.00
Bahan
Kapur Pasang 0.0010 m3 108,135.00 108.14
Jumlah Bahan 108.14
Total ( Tenaga + Bahan) 5,253.14
Overhead 0.0000 0.00
H.S.P 5,253.14
Tenaga
Mandor 0.0030 O.H 110,000.00 330.00
Kepala Tukang Cat 0.0063 O.H 100,000.00 630.00
Tukang Cat 0.0630 O.H 90,000.00 5,670.00
Pekerja 0.0200 O.H 85,000.00 1,700.00
Jumlah Tenaga 8,330.00
Bahan
Plamur Tembok 0.1000 Kg 14,625.00 1,462.50
Cat Tembok Dasar 0.1000 Kg 27,855.00 2,785.50
Cat Tembok Penutup (5 Kg) 0.0520 Galon 127,530.00 6,631.56
Jumlah Bahan 10,879.56
Total ( Tenaga + Bahan) 19,209.56
Overhead 0.0000 0.00
H.S.P 19,209.56
Tenaga
Mandor 0.0030 O.H 110,000.00 330.00
Kepala Tukang Cat 0.0042 O.H 100,000.00 420.00
Tukang Cat 0.0420 O.H 90,000.00 3,780.00
Pekerja 0.0280 O.H 85,000.00 2,380.00
Jumlah Tenaga 6,910.00
Bahan
Cat Tembok Dasar 0.1200 Kg 27,855.00 3,342.60
Cat Tembok 0.0360 Galon 127,530.00 4,591.08
Jumlah Bahan 7,933.68
Total ( Tenaga + Bahan) 14,843.68
Overhead 0.0000 0.00
H.S.P 14,843.68
Tenaga
Mandor 0.0025 O.H 110,000.00 275.00
Kepala Tukang Cat 0.0200 O.H 100,000.00 2,000.00
Tukang Cat 0.2000 O.H 90,000.00 18,000.00
Pekerja 0.0200 O.H 85,000.00 1,700.00
Jumlah Tenaga 21,975.00
Bahan
Meni Besi 0.1000 Kg 48,825.00 4,882.50
Kuas Cat 0.0100 bh 11,790.00 117.90
Jumlah Bahan 5,000.40
Total ( Tenaga + Bahan) 26,975.40
Overhead 0.0000 0.00
H.S.P 26,975.40
Tenaga
Mandor 0.2000 O.H 110,000.00 22,000.00
Kepala Tukang Cat 0.2000 O.H 100,000.00 20,000.00
Tukang Cat 0.7000 O.H 90,000.00 63,000.00
Pekerja 0.4000 O.H 85,000.00 34,000.00
Jumlah Tenaga 139,000.00
Bahan
Cat Besi Dasar 0.3000 kg 64,350.00 19,305.00
Jumlah Bahan 19,305.00
Total ( Tenaga + Bahan) 158,305.00
Overhead 0.0000 0.00
H.S.P 158,305.00
V INSTALASI LISTRIK
Pemasangan 1 Titik Stop Kontak Titik
Tenaga
Kepala Tukang 0.0050 O.H 100,000.00 500.00
Tukang Listrik 0.5000 O.H 90,000.00 45,000.00
Pekerja 0.0500 O.H 85,000.00 4,250.00
Jumlah Tenaga 49,750.00
Bahan
Kabel Nya 1 X 2,5 Ex. Supreme 15.0000 m' 4,455.00 66,825.00
Pipa Pralon 5/8 0.2000 Batang 9,180.00 1,836.00
Stop Kontak Ex. Broco 1.0000 Buah 15,975.00 15,975.00
T Doos Pvc 1.0000 Buah 4,635.00 4,635.00
Jumlah Bahan 89,271.00
Total ( Tenaga + Bahan) 139,021.00
Overhead 0.0000 0.00
H.S.P 139,021.00
Tenaga
Mandor 0.0125 O.H 110,000.00 1,375.00
Kepala Tukang 0.0125 O.H 100,000.00 1,250.00
Tukang Batu 0.2500 O.H 90,000.00 22,500.00
Pekerja 0.5000 O.H 85,000.00 42,500.00
Jumlah Tenaga 67,625.00
Bahan
Paving Stone Abu - Abu Tebal 6 Cm (Persegi
Panjang) K-300 1.0000 m2 106,501.24 106,501.24
V ACCESSORIES
1 m2 Pekerjaan Pemasangan / Covering ACP (Aluminium Composite
Panel) m2
Tenaga
Mandor 0.0070 O.H 110,000.00 770.00
Kepala Tukang 0.0700 O.H 100,000.00 7,000.00
Tukang Besi 0.7000 O.H 90,000.00 63,000.00
Pekerja 0.3900 O.H 85,000.00 33,150.00
Jumlah Tenaga 103,920.00
Bahan
Alumunium Composite 1.1000 m2 420,500.00 462,550.00
Hollow Besi Galvanis Uk 4 x 4 x 1 mm 0.8000 Btg 115,000.00 92,000.00
Braket Siku / spigot / stiffener 0.2670 Btg 60,000.00 16,020.00
Skrup Fixer 0.0800 Buah 29,070.00 2,325.60
Paku Skrup 0.1100 Kg 21,600.00 2,376.00
Sealant 0.2500 Tube 13,950.00 3,487.50
Jumlah Bahan 570,570.00
Alat
Stager 0.0200 set 110,000.00 2,200.00
Jumlah Bahan 2,200.00
Total ( Tenaga + Bahan) 674,490.00
Overhead 0.0000 0.00
H.S.P 674,490.00