Professional Documents
Culture Documents
AP-T262-19 Performance Requirements For Bitumen Sprayers
AP-T262-19 Performance Requirements For Bitumen Sprayers
AP-T262-19 Performance Requirements For Bitumen Sprayers
AP-T262-19
Prepared by Publisher
Keywords © Austroads 2019 | This work is copyright. Apart from any use
as permitted under the Copyright Act 1968, no part may be
Sprayed seal, sprayer calibration, bitumen, binder, application rate,
reproduced by any process without the prior written
calibration, sprayer nozzle.
permission of Austroads.
Acknowledgements
ISBN 978-1-925854-38-1
The 2014 edition of this technical report was prepared by
Austroads Project No. TT1820 Walter Holtrop and Steve Patrick and project managed by
John Esnouf.
Austroads Publication No. AP-T262-19
Sprayer calibration project working group: Helen Atalla, NATA;
Publication date September 2019
Dave Caban, RMS NSW; Robert Busutti, VicRoads; Craig
Pages 13 Phillips, MRWA; John Spathonis, TMR Queensland; Steve
Patrick, ARRB.
This report has been prepared for Austroads as part of its work to promote improved Australian and New Zealand transport outcomes by
providing expert technical input on road and road transport issues.
Individual road agencies will determine their response to this report following consideration of their legislative or administrative
arrangements, available funding, as well as local circumstances and priorities.
Austroads believes this publication to be correct at the time of printing and does not accept responsibility for any consequences arising from
the use of information herein. Readers should rely on their own skill and judgement to apply information to particular issues.
Performance Requirements for Bitumen Sprayers
Summary
Austroads works towards uniformity of practice in design, construction and user aspects of roads and bridges
and with this purpose in view, publishes guides and general procedures. A significant factor contributing to
the establishment of Australia’s large network of surfaced roads has been the successful application of
sprayed sealing technology, including the selection of treatments, design of the treatments and application
procedures. For a consistent and high quality of sprayed sealing work to be undertaken, and for sprayed
sealing to remain a viable surfacing option in the face of increasing traffic levels, particularly the increase in
the volume and size of heavy vehicles, the achievement of well-defined and controlled application rates of
bitumen and aggregate is a most important factor. Through a number of Austroads projects, the research
outcomes have been incorporated into other Austroads documents which address the selection and design
of sprayed seal treatments. This document sets out the performance requirements expected of bitumen
sprayers operating in Australia to ensure accurate control of bituminous binder application rates. The ability
to spray bitumen at the prescribed design rate of application depends on the design, manufacture and
maintenance of the bitumen sprayer, appropriate calibration methods, operating procedures, skills and
competency of the operator.
The performance requirements presented in this document apply to purpose-built mechanical bitumen
sprayers for the application of hot and/or cold bituminous materials commonly used in sprayed sealing, but
do not apply to spraying equipment used exclusively for hand sprayed work or where the pressure source is
compressed air in conjunction with a pressurised tank.
Contents
Summary ......................................................................................................................................................... i
Scope .............................................................................................................................................................. 1
1. Sprayer Calibration Certificates ........................................................................................................... 2
2. Legal, Safety, Noise and Environmental Requirements .................................................................... 3
3. Performance Requirements .................................................................................................................. 4
3.1 Spraying Bituminous Materials ......................................................................................................... 4
3.1.1 Type of Bituminous Materials .............................................................................................. 4
3.1.2 Rates of Application............................................................................................................. 4
3.1.3 Maintaining Uniform Rate of Application ............................................................................. 4
3.1.4 Temperature Range ............................................................................................................ 4
3.2 Spray Distribution ............................................................................................................................. 5
3.2.1 Uniform Transverse Distribution .......................................................................................... 5
3.2.2 Variable Transverse Distribution ......................................................................................... 5
3.2.3 Effective Width of Spray ...................................................................................................... 5
3.2.4 Overspray ............................................................................................................................ 6
3.2.5 Longitudinal Distribution ...................................................................................................... 6
3.2.6 Modifications and Repairs to Sprayers................................................................................ 6
3.3 Spray Cut-in and Cut-off Distances .................................................................................................. 7
4. Design and Construction Requirements ............................................................................................. 8
4.1 Sprayer Tanks .................................................................................................................................. 8
4.2 Loading, Mixing, Sampling and Spraying ......................................................................................... 8
4.3 Heating System ................................................................................................................................ 8
4.4 Circulating System ........................................................................................................................... 9
4.5 Bitumen Delivery System ................................................................................................................. 9
4.6 Speed Control System ................................................................................................................... 10
4.7 Instruments and Controls ............................................................................................................... 10
References ................................................................................................................................................... 12
Tables
Figures
Scope
This document sets out the performance requirements expected of bitumen sprayers operating on public
roads in Australia. It does not include the design and manufacture of the prime mover, tank and associated
equipment or operating procedures as it is considered to be the responsibility of the manufacturer, owner
and operator.
Bitumen sprayers are required to spray bituminous materials with a range of additives such as polymers,
cutters, rubber and water. These bituminous materials are also referred to as binders because of their role in
strongly binding the stone aggregates to the pavement. For simplicity and to avoid confusion these
bituminous materials/binders will generally be referred to as bitumen throughout this document.
The requirements apply to bitumen sprayers fitted with a bitumen pump and spray bar system for the
application of hot and/or cold bituminous materials used in sprayed sealing. This includes sprayers fitted with
one of the following circulating type spray bar systems:
• single spray bar fitted with a single row of nozzles
• dual spray bars fitted with a single row of nozzles in each bar
• telescopic spray bar fitted with a single row of nozzles
• telescopic spray bars fitted with two rows of nozzles
• single bar with two (or more) rows of nozzles.
The nozzles used in spray bars shall be approved by the manufacturer for use with hot and cold bitumen
products. The nozzles shall deliver a designated fluid flow and appropriate spray pattern shape without the
need to create high working pressures. These requirements do not apply to spraying equipment used
exclusively for hand sprayed work. Sprayers will not be approved where the fluid flow is created by utilising a
pressure source such as compressed air in conjunction with a pressurised tank.
Other types of bitumen sprayers, spray bar systems and spraying nozzles may be acceptable provided they
can meet the appropriate commonwealth and state legal requirements and regulations and comply with
Australian Standard AS 2809.5 Road tank vehicles for dangerous goods – tankers for bitumen-based
products, associated standards, Australian Code for the Transport of Dangerous Goods by Road & Rail and
pass the Austroads sprayer calibration test methods.
Note — where reference is made to a standard or other document, the current version of that document shall
apply.
New sprayers, those previously issued with a certificate and overseas sprayers must all comply with the
above requirements. Where sprayers are introduced into Australia from overseas, they must hold an
Australian certificate as detailed above, regardless of holding any overseas calibration certificates. Road
agencies may suspend or withdrawn at any time sprayer calibration certificates should the bitumen sprayer
prove unable to comply with the requirements of Section 4 and 5 of this document, either as a result of
defects, adjustments or alterations. Re-calibration or field audit testing may be required before a bitumen
sprayer is again accepted for use in sprayed sealing works.
A road agency may consider allowing the use of bitumen sprayers with novel designs or equipment which do
not meet the specific requirements of this document but are able to meet all appropriate legal requirements
and produce satisfactory performance when tested in accordance with AGPT/T530 to AGTP/T536. Sprayer
calibration certificates are valid for a period of 12 months from the date of issue.
A list of accredited testing organisations for bitumen sprayer calibration are listed on the NATA web site.
Calibrated bitumen sprayers are listed on the Australian Asphalt Pavement Association website
https://www.aapa.asn.au/ showing the registered owner, sprayer identification number, issuing organisation,
certificate number and expiry date.
There is further information on the recommended safe and practical procedures to use in the handling and
transfer of hot bitumen and bitumen-based products in AAPA Guide 7: Safe Use of Bitumen Hoses (AAPA
2011).
3. Performance Requirements
Rates of application are given as sprayed product on the road surface in litres per square metre (L/m²) as at
the time of spraying. The finished design application rate used by pavement engineers must factor in the
later loss of volume by cooling and the evaporation of the additives such as cutter or water. Bitumen
sprayers shall be able to spray any rate of application required within the ranges shown below inclusive, up
to the maximum effective width of spray for which the sprayer has been tested and issued with a certificate.
Bitumen sprayers shall be capable of spraying on ascending grades of up to 10% whilst fully loaded and be
able to maintain the uniform rate of application of material as specified in Section 4.1.2.
Bitumen sprayers shall be able to comply with Section 4.1.1 within the range of temperatures recommended
by the bituminous materials supplier, with a maximum temperature of 200 °C.
Uniformity of the transverse distribution shall be tested in accordance with any one of the following three test
methods:
• AGPT/T532 Transverse Distribution by Fixed Pit Facility (Austroads 2018b), or
• AGPT/T533 Transverse Distribution by Field Mat (Austroads 2018c), or
• AGPT/T534 Transverse Distribution by Portable Trough (Austroads 2018d).
This type of sprayer is typically fitted with two separate spray bars, either of the same or different widths,
which can be operated individually or combined to provide a variable transverse spraying distribution. Guide
to Pavement Technology Part 4K: Selection and Design of Sprayed Seals (Austroads 2018g) recommends
that the variation of different design application rates is not more than 0.5 L/m². If the sprayer is required to
provide both uniform transverse distribution and variable transverse distribution it must also be tested as
specified in Section 4.2.1 for uniform distribution.
The effective width of spray shall be the width within which the rate of application of the material complies
with the requirements in Section 4.2.1, and is illustrated diagrammatically in Figure 4.1. The range of
acceptable effective widths is shown in Table 4.2.
Any spray bars longer than the normal permitted legal truck width of 2.5m shall be capable of conforming to
the cross fall/shape of the surface being sprayed, aiming to provide conforming heights between the face of
the spraying nozzles and pavement surface. For example, if spraying the full width over a two-lane, two-way
road, the bar must be within the required tolerance at both the edges and over the crown of the road, and all
areas in between. These heights must be within the tolerance range as per the nozzle manufacturer’s
specification.
3.2.4 Overspray
There shall be no appreciable spray application of bituminous material beyond a 100 mm strip on each side
of the width of spray (Figure 4.1).
The rate of application of bituminous material along the length of the sprayer run shall be within ±2.5% during
continuous discharge. Requirements for distance measurement and road speed measurement are given in
Road Speed and Distance Calibration, AGPT/T535 (Austroads 2018e).
It is a requirement that where a sprayer which holds a current certificate has been modified and that
modification may effect the sprayer’s performance, then that sprayer must be retested to ensure continued
compliance with the appropriate Austroads test method. When this occurs the sprayer’s calibration certificate
is withdrawn and a new certificate is issued.
Such changes may include but are not restricted to the following occurrences:
• Bitumen pump — where an existing bitumen pump is replaced like for like or where there is a change to
the make and model of the pump then the sprayer must be retested to comply with AGPT/T531.
• Pump RPM measuring system — where changes have been made to the pump speed measuring system
and these changes could affect the accuracy of measurement, then the sprayer must be retested to
comply with AGPT/T531.
• Other changes in the spraying circuit — where a new spraybar has been fitted or where a spraybar has
been straightened following damage or where valves and pipework are replaced and where these
changes could effect the accuracy of transverse distribution then the sprayer must be retested to comply
with either one of the three transverse distribution tests AGPT/T532, T533 or T534.
• Changes to road speed instruments — where changes have been made to the road speed or distance
measuring system and these changes could effect the accuracy of measurement, then the sprayer must
be retested to comply with AGPT/T535.
• Changes to other circuits — where changes are made to other bitumen circuits (e.g. bitumen loading
circuit) and these circuits do not impact on the bitumen flow or pressure during spraying operations then
the sprayer is not required to be retested.
• raise the temperature of the bituminous material at the designated rate. The maximum heating rate shall
not exceed 20 0C per hour. The heating rates assume that the material is being circulated, and all
equipment is of adequate capacity and in good working order.
• adjust the amount of heat generated by the burner so as not to exceed the maximum heating rate
designated for the specific product being heated.
For product-specific heating rates and maximum heating temperatures, refer to Section 7 of Austroads
Bituminous Materials Safety Guide (Austroads 2015).
The safe heating level for each burner must be indicated on the dipstick (or other accepted measuring
device). In addition, the minimum safe heating level for each burner shall be clearly indicated on an engraved
aluminium, brass or stainless steel plate. This plate must be located in a conspicuous position on the outside
of the tank adjacent to the burners.
For all new designs, or extensively modified bitumen sprayers of hot bituminous materials the mixing
efficiency information shall be provided by the manufacturer of the bitumen sprayer. The mixing efficiency will
be determined by cutting back Class 170 bitumen from AS 2008 Bitumen for pavements with various
concentrations of cutter oil, complying with AS 3568 Oils for reducing the viscosity of residual bitumen for
pavements and testing in accordance with Table 5.1 below.
C 170 bitumen Kerosene concentration Minimum mixing time Pump or mixing system
(% by volume) (% by volume) (minutes) setting
97 3
93 7
Manufacturer to provide time
90 10 required to meet the
Provided by manufacturer
85 15 requirements in the following
paragraph
80 20
75 25
Mixing efficiency shall be such that when a set concentration of kerosene is added to the C170 bitumen, with
the bitumen tank filled to 75% capacity, the resultant mixture ratio as specified in Table 5.1 must not vary by
more than ± 20% from the specified concentration. The properties, sampling requirements and referenced
testing methods for cutback bitumen is provided in AS 2157 Cutback Bitumen.
Change in sprayer forward speed Change in total output for width of bar
(%) (%)
–10 –8 to –12
–5 –4 to –6
+5 +4 to +6
+10 +8 to +12
Instruments and controls shall be located such that they are clearly visible and legible to the operator, clearly
marked, provide a steady reading and are lag free.
Prior to the sprayer being presented for annual calibration, load cells and flow meters (if fitted) shall be
calibrated or the performance validated by a laboratory accredited by NATA for those specific items.
Accredited NATA laboratories or accredited testing organisations for sprayer calibration can verify the
accuracy of thermometers and temperature measuring devices by comparison against a calibrated reference
temperature measuring device.
Instruments may be analogue, digital or visual display units but need to comply with the following
requirements:
• Bituminous materials discharge — the instrument shall cover the full operating range, which includes the
10% extra as required in Section 5.5.
• Sprayer forward speed — the sprayer speed shall be controlled to ensure a uniform application rate for
the length of the sprayer run. The road speed indicator shall provide sprayer speed data in m/min, for a
range of at least 50 to 430 m/min to cover the range of rates of application required in Section 4.1.2.
• The sprayer forward speed indicator shall be accurate to ±2.5%.
• Distance sprayed — the distance sprayed shall be recorded to enable correct calculation of the actual
rate of application achieved. The distance sprayed shall be recorded in metres with a repeatability of
0.2% and shall be accurate to ±2.5%, in accordance with AGPT/T535 (Austroads 2018e). The distance
recorder may be part of the sprayer forward speed instrument or a separate instrument.
• Temperature indicator — the temperature of the bituminous material, both when in the tank, or in the
spraying system, shall be measured accurately to provide correct information for calculations for volume
correction and ensure the materials are within the specified spraying temperature range at time of
spraying. This requires a minimum of two temperature indicators to be fitted, accurate to ±4 °C over the
full range of 10 °C to 230 °C.
• Quantity of bituminous materials — the quantity of material in the sprayer tank shall be measured to
provide correct information to calculate actual rates of application achieved. The quantity may be
measured using the volume, mass or flow rate of the material in the tank.
• Dipsticks — dipsticks when used shall be suspended from the top of the tank, in square tubing, solid
rectangular or ‘T section’. The dipstick shall be located at the mid point of the longitudinal axis of the tank.
The maximum scale intervals and maximum permissible error of dipsticks must be in accordance with the
National Instrument Test Procedure for Vehicle Tanks NITP9.
• The safe heating level for all burners shall be indicated on the dipstick as well as on the tank adjacent to
the burners as per Section 5.3. The dipstick shall be marked with the tank serial number.
• Load cells — where load cells are used, the maximum permissible error shall be in accordance with
Class A of NMI R 60 Metrological Regulation for Load Cells (National Measurement Institute 2004a).
• Flow meters — where flow meters are used, the maximum permissible error shall be in accordance with
NMI R 105 Direct Mass Flow Measuring Systems for Quantities of Liquids (National Measurement
Institute 2004b).
References
Australian Asphalt Pavement Association 2011, AAPA guide to the safe use of bitumen hoses, AAPA, no. 7,
AAPA, Kew, Vic.
Austroads 2011, Performance requirements for bitumen sprayers, AP-T181-11, Austroads, Sydney, NSW.
Austroads 2015, Bituminous materials safety guide, AP-G41-15, Austroads, Sydney, NSW.
Austroads 2018a, Calibration of bitumen sprayers part 1: volumetric calibration of bitumen pumps,
AGPT/T531, Austroads, Sydney, NSW.
Austroads 2018b, Calibration of bitumen sprayers part 2: transverse distribution by fixed pit facility,
AGPT/T532, Austroads, Sydney, NSW.
Austroads 2018c, Calibration of bitumen sprayers: part 3: transverse distribution by field mat, AGPT/T533,
Austroads, Sydney, NSW.
Austroads 2018d, Calibration of bitumen sprayers part 4: transverse distribution by portable trough,
AGPT/T534, Austroads, Sydney, NSW.
Austroads 2018e, Calibration of bitumen sprayers part 5: road speed and distance calibration, AGPT/T535,
Austroads, Sydney, NSW.
Austroads 2018f, Calibration of bitumen sprayers part 6: viscosity of calibration fluid, AGPT/T536, Austroads,
Sydney, NSW.
Austroads 2018g, Guide to pavement technology part 4k: selection and design of sprayed seals, Austroads,
Sydney, NSW
Austroads 2019a, Specification framework for polymer modified binders and multigrade bitumens,
AGPT/T190, Austroads, Sydney, NSW.
Austroads 2019b, Calibration of bitumen sprayers: general introduction and list of methods, AGPT/T530,
Austroads, Sydney, NSW.
National Measurement Institute 2004a, Metrological regulation for load cells, NMI R 60, NMI, Lindfield, NSW.
National Measurement Institute 2004b, Direct mass flow measuring systems for quantities of liquids, NMI R
105, NMI, Lindfield, NSW.
Australian Code for the Transport of Dangerous Goods by Road & Rail.
Standards Australia
AS 2809.1-2008, Road tank vehicles for dangerous goods: general requirements for all road tank vehicles.
AS 2809.5-2001, Road tank vehicles for dangerous goods: tankers for bitumen-based products.
AS 3568-1999, Oils for reducing the viscosity of residual bitumen for pavements.