Professional Documents
Culture Documents
Operation & Maintenance Guide For Dry Ash Evacuation & Transportation System - Operation
Operation & Maintenance Guide For Dry Ash Evacuation & Transportation System - Operation
Operation & Maintenance Guide For Dry Ash Evacuation & Transportation System - Operation
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
In Thermal Power Plants, Coal is burnt to generate power. Coal used in thermal power
plants of NTPC are having a very high ash content, generally in the range of 35 to 45%. The
large amount of ash that is produced every day needs to be transported reliably, economically
and in an environment-friendly manner. Around 80% of ash that is generated, the major
portion, is carried by flue gases and referred as fly ash.
Dry fly Ash Evacuation System (DAES) were introduced in 90s with the aim of reducing
the water requirement in handling of fly ash. With the development of avenues for utilization
of fly ash in cement, ash brick and FAB industries, second round of development in DAES
system took place and NTPC started handling fly ash in completely dry form and started
storing in fly ash silos from where user industries were offered dry fly ash for end use. Till
then many of the plants were installed for the partial use of dry ash due to low demand of fly
ash from the user industries. However, with changes in environmental norms in the country
regarding the restriction in use of land to store waste material and water consumption, and
reduction of environmental hazards due to coal ash, 100% utilization of power plant ash has
been enforced. Accordingly, NTPC started installing DAES system for the 100% of fly ash since
last decade.
In Vallur thermal power plant, ash is removed at four different locations such as Bottom
Ash hopper, Economizer hoppers, Air Pre Heater hoppers and ESP hoppers. Ash is transported
from BAH, ECO and APH hoppers through slurry system and ESP hoppers through dry/wet
evacuation system. Fly ash carried along with the flue gas from the boiler is collected
continuously in ESP hoppers. This ash is continuously removed by vacuum extraction system
in wet mode or dry mode by running vacuum pumps.
In Wet mode, fly ash from ESP hoppers is taken to collector tanks by vacuum pumps. Fly
ash is mixed with FAHP water in wetting head to form fly ash slurry in collector tank. Fly ash
slurry from each collector tank is disposed in fly ash slurry trench which connects to ash slurry
sump. From there ash slurry is transported to ash dyke by Ash Slurry Disposal Pumps.
In Dry mode, fly ash from ESP Hoppers can be collected in Buffer hopper in the dry form
by vacuum pumps. Ash from buffer hopper is then transported to main silo through pressure
conveying lines by Transport Air Compressor.
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
3. SCOPE
This LMI deals with operation aspects of ESP hopper evacuation as well as pressure
conveying by dry evacuation system (DAES). The purpose of this LMI is to provide operation
personnel with instructions for safe and effective operation of system components associated
with fly ash evacuation and transport.
Note: In the occurrence of excess ash buildup in ESP hoppers, action to be taken as per
LMI/OGN/OPN/SYST/032/OPRN/024
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
5. GENERAL INSTRUCTIONS
5.1 To maintain DAES shift operation document, Operator has to fill Shift Log Book (Soft
Copy may be used) as per Annexure-1
5.2 Based on the walk-down check-lists (Annexure-2), the operation engineer will issue
work orders to the maintenance department for the repair of identified defects.
5.3 A change-over schedule register is to be maintained and the equipment change-over
is to be followed as per the schedule.
5.4 The Shift-Charge-Engineer shall maintain the following documentation.
a) PTW Register indicating the equipment for which the PTW is issued and
cancelled in the shift.
b) Equipment availability.
c) Log-book indicating the operating hours, forced outages and critical points
requiring attention.
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
6.1 During start up, Dry Ash Evacuation System (DAES) should not be started when only
oil firing is in service as it can lead to oil deposition and thereby choking the buffer
hopper bag filter. For changeover to dry mode, after lightup, ensure at least three
cycle of evacuation of all hoppers is completed in wet mode after cutting out oil
firing.
6.2 The rate of evacuation is lower in dry mode, when compared to wet mode. Hence
while changing over from wet to dry, ensure all first three hoppers in the
corresponding ESP Pass had been emptied at least once in last 6 hrs.
6.3 Water entering buffer hopper may choke bag filter, hence for starting the system in
wet mode, always ensure FAHP manual valve in the collecting tower closed and
water pressure is zero to avoid any possibility of water entering Buffer Hopper.
6.4 After starting/changeover an ESP pass to dry mode, all branch line vacuums, shut off
vacuum(SOV) and Open Breaker Vacuum(OBV) for the ESP Pass are to be checked
and recorded in shift log.
6.5 The SOV, OBV and line vacuums for all ESP passes must be checked and recorded in
shift log during every shift beginning.
6.6 For dry mode operation ensure following parameters are achieved,
SOV > 400mmHG
Line vacuum 170 to 200mmHg
OBV 15 to 35mmHg
In the event of a deviation in any of the above parameters, evacuation system to be
checked for air ingress, vac. pump belt condition, seal water, header valve passing,
tower valves passing etc. And it shall be informed to AHP MM.
6.7 The Vacuum Setpoints for dry mode operation are advised to be set as follows:
VS1 140mmHG (Hopper no load vacuum for MHV open)
VS2 80mmHg (Hopper empty vacuum for MHV close)
VS3 350mmHg (MHV intermittent close for controlling phase density)
These settings are tentative and may be modified.
6.8 Ensure sufficient instrument air pressure (5ksc) for proper purging of BH bag filter.
6.9 Buffer Hopper Filter DP must be maintained below 50mmWc. If DP>50mmWc, check
BH PJT, ash level and ALV operation for any defects and take appropriate action.
6.10 In the event of BH ash level Hi, evacuation may be stopped (if not stopped in auto)
and BH is to be emptied. BH fluidizing, ALV and equalizer valves operation is to be
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
Fluctuation in dry shut off Malfunctioning of air lock vessel valves such as
LDV , UDG and three way valves
Line vacuum high Air intake opening at the end of header may be
fully closed or opening may not be sufficient
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
Line vacuum equal to shut off Header valve may be closed condition
vacuum
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
ALV not conveying ash Fluidizing air may be closed condition/ choked
condition
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
8. REVIEW
The CEO, NTECL shall review this document on a 2 yearly basis or as necessary.
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
DA
SHIFT GROUP
TE
UNI UNI UNI ASH WATER MAKE BLOW ASH WTR
SEA WTR
T1 T2 T3 UP DOWN R/C
LOAD SOURCE
ASP A B C D E
COAL DY
KE
EQUPMEN PT CURRE
I/S S/B PR REMARKS
T W NT
ASP
FAHP
BAHP
BALP
FWP
LP SEAL WTR P/P
HP SEAL WTR P/P
IAC-
1A/1B/2A/2B/3A
/3B
DRAIN SUMP P/P
AWRS - DEWATERING
AWRS PUMPS
PUMP AVAILABILITY-
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
UNDER VOLTAGE(U/V)
ALI-TRIP
TRIP
OFF
CERM/EERM NOT
AVAILABLE
ESP UAF -FAN
ESP-UAF PUMP I/S
/ PR.
UNIT1 UNIT2 UNIT3
VAC.P/P PT PT AV PT
STATUS I/S AVL I/S AVL I/S
W W L W
SILO 1/2/3
LEVEL
EQPT UNIT1 UNIT2 UNIT3
TAC(A/B/ I/S AVL PTW I/S AVL PTW I/S AVL PTW
C)
BH i/s
ALV i/s
CONVEYIN 1A 1B 2A 2B 3A 3B
G LINE
1X 1Y 1Y 1Z 2X 2Y 2Y 2Z 3X 3Y 3Y 3Z
FLUIDIZIN
G
BLOWER
I/S /OIL
LVL
TAC(TEMP W.T DE NDE DE W. DE ND DE W. DE ND DE
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
SILO
SILO PT
I/S AVL AERATION A B C D
EQUIPMENTS W
BLOWER
DUST
CONDITIONER OIL LEVEL
P/P
WASH WATER HEATER
P/P TEMP
AERATION
FILTER DP
BLOWER
DRAIN P/P PRESSURE
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
B/C-
1
I/C
-
I/C- B/C
B/C I/C- SEC 3S
B/C1 3S B
-2 2SA -2
A
B/C-
2
UNIT#1 ASH EXTRACTION UNIT#2 ASH UNIT#3 ASH EXTRACTION
MCC EXTRACTION MCC MCC
SECTION- SECTION
SECTION-1 SECTION-2 SECTION-2 SECTION-2
1 -1
I/C- I/C-
I/C- I/C- I/C-
I/C-1UA 2U 3U
1UB 2UB 3UB
A A
B/C B/C B/C B/C B/C B/C
ESP
EVACUATI UNIT1 UNIT2 UNIT3
ON
PASS A B C D A B C D A B C D
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
SHIFT ACTIVITY
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
OPERATION & MAINTENANCE GUIDE FOR DRY ASH EVACUATION & TRANSPORTATION
SYSTEM
OPERATION & MAINTENANCE GUIDE FOR DRY ASH EVACUATION & TRANSPORTATION
SYSTEM
H6 H6 H6 H6
H7 H7 H7 H7
H8 H8 H8 H8
H9 H9 H9 H9
H10 H10 H10 H10
H1 H1 H1 H1
H2 H2 H2 H2
H3 H3 H3 H3
H4 H4 H4 H4
H5 H5 H5 H5
3 3 3 3
H6 H6 H6 H6
H7 H7 H7 H7
H8 H8 H8 H8
H9 H9 H9 H9
H10 H10 H10 H10
H1 H1 H1 H1
H2 H2 H2 H2
H3 H3 H3 H3
H4 H4 H4 H4
H5 H5 H5 H5
4 4 4
4 H6 H6 H6 H6
H7 H7 H7 H7
H8 H8 H8 H8
H9 H9 H9 H9
H10 H10 H10 H10
NO OF CYCLE NO OF CYCLE NO OF CYCLE NO OF CYCLE
OPERATION & MAINTENANCE GUIDE FOR DRY ASH EVACUATION & TRANSPORTATION
SYSTEM
NAME Signature
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
2. Aeration Blower
- Suction filter differential pressure. -Ok/not OK
- Outlet temp. of air/Heater working or not. -Ok/not OK
- Oil level OK. -Ok/not OK
- Abnormal vibration if any. -YES/NO
- Bearing temperature. -Ok/not OK
- Leakage of air if any. -YES/NO
3. Buffer hopper
- Instrument air pressure at pulse jet station. OK(5.4ksc)/not OK
- Sequence of operation of pulse jet system. -Ok/not OK
- Air ingress sound or indication at any place. -YES/NO
- Ash leakage marks at any place. -YES/NO
- Instrument air leakage if any. -YES/NO
- Branch line coupling ingress. -YES/NO
- Any instrument loose. -YES/NO
- All valves are operating with sequence -YES/NO
- Fluidizing Line charged and ALV Temp. is OK -YES/NO
- ALV Fluidizing Line valve Auto operation -YES/NO
(Fluidizing line Pressure variation during ALV discharge valve operation to be checked
in local pressure guage. No variation indicates Fluidizing line chokage/Valve not
operating)
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020
7. ASH Silo
- Ash leakage if any. -YES/NO
- Water ingress point if any. -YES/NO
- Air leakage if any. -YES/NO
- Instrument air pressure at pulse jet station within limit -YES/NO
- Sequence of operation of pulse jet system at running Silo. -Ok/not OK
- Pr. Drop of pulse jet within limit -YES/NO
- Silo vent fan abnormal sound if any. -YES/NO
- SVF Belt Condition -
- SVF/Bearing Housing Vibration within limit. -Ok/not OK
- Dust from Vent fan discharge -YES/NO
- Silo vent fan abnormal sound if any. -YES/NO
VALLUR LMI/OGN/OPN/SYST/00
REV0/DATE:NOV2020