Professional Documents
Culture Documents
Method Statement For Surveying Works of Land Projects
Method Statement For Surveying Works of Land Projects
Method Statement For Surveying Works of Land Projects
The survey activities include are as follows but not limited to:
Initial survey to validate site/plot boundaries; permanent markers are
established and site data is collected.
Demarcation of the project area and marking of the limits and boundaries.
Set out for vertical and horizontal control of precast elements, in-situ concrete
slab, raft foundations, wall, columns, formworks, storm drainage, trenches, kerbs,
and other structures.
Setting out of grid lines and taking records of the actual ground level in
preparation for excavation
Horizontal Control & Vertical Survey Control
Transfer of datum
As-built surveys
I will be implementing the method statement for survey works with the project
located in Qatar. All of the relevant terms associated with the country’s
surveying practices are mentioned. Nonetheless, if the method statement for
other countries will be adopted be advised to check with the specific practices
intended for the country and modify the method statement accordingly.
As long as the task and conditions do not change, generic work method
statement may be used at a number of civil engineering projects.
Before the activity or any part thereof are commenced, the Contractor and the
Consultant Engineer shall together make a complete survey and take grade levels of
the site and agree with the Consultant Engineer on all particulars upon which setting
out of the works will be based, including existing plant, buildings, and services.
Moreover, a risk assessment must be conducted by the contractor prior to the start of
the concerned work.
The Contractor shall prepare shop drawings detailing all survey information and
survey levels. Such levels shall be related to the temporary benchmarks as aforesaid.
The plans shall also show the site’s permanent grid lines. After an agreement of the
drawings, they shall be signed by the Consultant Engineer and Contractor and will
form the basis of settling out.
Working “from whole to part”, the survey control point should be established on
undisturbed and permanent features such as walls, concrete foundations, curb line,
etc.
The network of closed traverses which start from and established by closed onto
different known control points is recommended as the accuracy of the survey result
can be evaluated and refined by using adjustment methods in computation.
Site control stations will be placed around the construction site in strategic locations
where they will not be disturbed by construction activities and secondary control will
be placed closer to the work area. These will be made up of monument type as:
K1. Steel Pin, in Concrete
Due to their location and proximity to work activities, they are more likely to be
disturbed and will need to be checked at regular intervals. Checks will be done on
every use by connecting to no less than two other stations.
In case of controls being disturbed, the contractor shall replace them whether on the
same position or some other positions approved by the surveyor consultant.
The project site is connected to Permanent Bench Mark (PBM) provided by the client
representative through 3rd party surveyor.
The points have been cross-checked for relative position and found to be correct.
If required, further site control would be established as necessary by closed loop
traverse.
All precise work must be linked to the four permanent marks formed around the site
via closed traverse and/or level run.
Plan Control
Static GPS observations will be used to establish a minimum of two survey stations.
Following that, the data will be post-processed to generate grid co-ordinates and
height above datum. Rather than using less accurate Real-Time Kinetic (RTK)
measurements, this would be preferable.
Closed-loop enclosed by closed traverse will be used to create additional site control
as required. With PK or Hilti nails in hard material or Perma Marks in soft material, a
minimum of two Permanent Ground Markers (PGMs) would be identified
Barriers around the Temporary Bench Mark shall be used for protection from the
moving equipment during the phase of construction.
However, it is proposed also to establish stable benchmark points which are unlikely
to move or be damaged from the time they are set to the time they are used to
establish the elevation.
The contractor will establish benchmarks at the suitable density and for spacing for
the purpose of survey and work. This initial set up of benchmark shall be checked by
the surveyor to confirm their correctness and accuracy and will provide 3 benchmarks
for each working area as required.
The key benchmarks will be protected from potential damages during construction
activities caused by work, by means of barriers e.g. steel barricade/enclosures,
barricade tapes to prevent encroachment and disturbance.
The contractor shall height all-new benchmarks using spirit leveling equipment for
the following application:
The maximum distance between level and leveling staff shall not exceed 50 meters.
All survey instruments to be used during the entire duration of project execution shall
be accurately and carefully maintained that is, preventive maintenance and calibration
schedule shall be properly and strictly observed.
The regular checking intervals of the established TMB will be done connecting to no
less than two other approved control stations.
The location of temporary benchmarks shall be agreed upon with the consultant. The
level of temporary benchmarks shall be related to the Qatar National Height Datum
(QNHD). An existing benchmark or control station related to the Qatar National
Height Datum will be indicated by the consultant for this purpose. The Contractor
shall prepare a plan detailing the location of the benchmarks and temporary
benchmarks and keep it up to date for the duration of the Contract.
The Contractor shall protect and maintain the temporary benchmarks until the project
is complete. Upon completion, the Contractor shall clear away the temporary
benchmarks to the satisfaction of the consultant.
The Contractor is responsible for checking the accuracy of the temporary benchmark.
Any re-work resulting from incorrect or inaccurate temporary benchmarks shall be
undertaken at the Contractor’s cost.
Site Grid/Zones
As may be required, the contractor shall implement a Project Site Grid-tied to the
Qatar National Grid, oriented and labeled as specified by and agreed with the
Consultant Engineer. The final survey grid shall be arbitrary but related to the
National Grid (QND95). A description of the grid system used shall be quoted on
each survey plan or upon the index plan.
Total Station
Total station shall be used to set-out locations, alignment, and plumpness of structures
(foundations, columns, walls, slabs, steel frames, etc.) based on approved setting-out
drawing coordinates and with reference to established TBMs.
This equipment shall also be employed to undertake a topographic survey and as-built
survey as required.
Automatic Levels
Automatic levels shall be used for verifying the level control station, fixed new TBM
levels, and finalize all required item levels on site.
The survey team shall ensure that they work within the confines of the existing
perimeter edge protection provided.
Setting out of foundations, steel frames, etc. is done through the coordinate method.
All points must be marked and corresponding dimensions are checked with respect to
the approved drawings.
The contractor shall establish the theoretical grid line positions at the ground floor of
the building & this grid line shall be transferred to the other floors from existing
horizontal control points the outside of the building.
The theoretical grid lines shall be marked around the perimeter of the floor slabs by
grid lines offset identified using metal pins or chalk lines applied directly to the slab. (
for finishing job).
Level datum or slab level surveys shall be transferred to all floor levels (if applicable)
and shall be marked as control datum 1 meter from SSL (Slab Surface Level).
The survey team shall verify the as-built position of the structure in relation to the
theoretical grid lines and datum levels and shall immediately notify the project team
of any discrepancy from the agreed tolerances. Any discrepancies shall be
immediately highlighted and inform the project team for rectification.
All information relative to the as-built survey of the existing structure and cast-in
items shall be recorded.
After completion of survey to a sufficient area setting out of the precast elements and
structural frames installation shall be carried out. Setting out shall be completed on all
structures and other elements basis which shall be completed generally by marking
reference to the positions via grid lines with spray paint.
The survey can be carried out from the foundation below or from the top level.
The concrete pouring of the cast-in-situ concrete slab, foundations, wall, columns,
blindings, formworks, and other structures (i.e road networks) will be controlled using
a leveling instrument possibly a laser level or conventional leveling method.
The laser plummets or the optical plummet will be used to layout control on the new
slab and plumbed to the formwork platform. Once the slab has been cast all
permanent grid points and grid lines shall be marked by the surveyor. Accuracy at all
times shall be implemented.
These marks are then used to verify and set the shutter locations. While formwork is
being moved up each level, the verticality of the lift core walls must be checked.
However, every 5 floors, including two diagonally opposite corners of lift shafts, the
frequency of results must be generated and logged.
The verticality of all shafts will be monitored from the external wall coordinate.
Calculation and worksheet will show the drawings and revision numbers of drawings
used onsite.
As far as is practical only the drawings kept in the drawings office will be used as
copies of the drawings. Surveyor’s responsibility is to make sure that the latest
revision of drawings for set out is used on site.
In addition to the as-built survey file maintained in the survey office, the surveyors
will maintain a similar file in the construction manager’s office.
Communication
‘As built’ information needs to be communicated to the project manager, construction
manager, and relevant foreman for perusal.
Any unusual results or results exceeding the specifications will be highlighted and the
project manager informed. This will be communicated to the Consultant Engineer in
the form of an RFI (Request For Information) for further disposition.
Attach with the Survey Inspection Request (IR) is the usual complimentary form of
Survey Report.
All survey data is stored in the data card onboard the instrument and transfers to and
from the computer. These data can be retrieved and viewed in two formats:
DXF format for .dwg files (Autocad files)
CSV format for .xls files
Wherein either DXF & CSV formats will be shared to Consultant Engineer /Surveyor
along with the related Survey Inspection Request (IR).
Drawings are sent by email in pdf and AutoCAD dxf or dwg format.
Responsibilities/Supervision
Project Manager
The Project Manager is responsible for managing the Construction activities and
provide general interface between Sub-contractors.
Monitor progress and site resources.
Review of the construction methodologies and ensuring the construction team and
subcontractors abide with agreed methodologies.
Implement agreed quality procedures and ensure the Construction Inspection /
Supervision Team understands the requirements.
Site Engineer
Liaising with clients and their representatives (engineers and surveyors), including
attending regular meetings to keep them informed of site progress.
Issuing daily reports.
Day-to-day job supervision of the site, including supervising and monitoring the site
labor force and the work of any subcontractors.
Planning the work and efficiently organizing the plant and site facilities in order to
meet agreed deadlines
QA/QC Manager
To support QC Engineer with the necessary information and remarks
To coordinate with the QC Engineer in reviewing all relevant documentation and
testing activities.
To be in direct contact with Project Managers and Construction Managers to obtain
and/ or provide necessary information pertaining to inspection and/ or testing.
Responsible in providing all information including shop drawings required for the
work.
Responsible for the works carried out are as per the plan agreed with the engineer and
the consultant.
Maintain all documentations required and ensure correct information is given to all
concern.
Ensure that quality inspections are regularly performed at site in accordance to
specification and standards.
QA/QC Engineer
The QA/QC Engineer is responsible to ensure work has been executed on field as per
the specification and approved method statement for surveying.
He is responsible for quality inspection as per method statement for surveying.
Safety and Health Manager
The Safety and Health Manager is responsible to ensure that all safety precautions and
procedures are in place.
He may conduct audits or inspections to ensure said compliance.
Chief Surveyor
Supervises the survey team daily activities on site.
Ensures that surveying data are collected and recorded accurately including shape,
contour location, elevation and dimension of land features.
Ensures that the survey team follows company standards and procedures for
operations and safety.
Leads the survey team making sure that the work on site is accurate.
Leads and participates in a variety of land survey operations such as boundary,
topography, leveling, design, as-built, and maintaining horizontal and vertical control
networks utilizing a full range of survey equipment.
Project Surveyor
Leads the Land surveyors during setting out and controlling the quality of site setting
out.
Prepare survey reports and maintain records.
Supervise the land surveyor for the use of equipment, preparation of sketches and
notes and electronic data collection.
Prepare reports on Surveyor’s performance.
Prepare all the necessary data (Points x, y & z value) for the Surveyor on Site.
Double checking on the orientation of the drawing received by the
Technical Department prior to start data preparation.
Survey Helper/Aide
Maintain and use Surveying equipment. Assist surveyors in taking measurements,
record measurements manually or electronically, and peg out boundaries.
Manpower Requirement
Chief Surveyor
Project Surveyor
Survey Helper/Aide
Draughtsman for production of as-built drawings (As required)
Safety Officers
Site Engineer
Equipment Requirement
A combination of modem, both electronic and conventional, survey equipment should
be used to achieve required survey accuracy. The list of survey equipment includes
(but is not limited to):
Total Station
Equipment
An electronic/optical theodolite integrated with an electronic distance meter to read
distances from the instrument to a particular point. Provides high accuracy angle
measurements and precise long-range distance measurements backed by automatic
fine pointing and fast, reliable reflector location.
Instruments will allow for internal data storage and the measurement of horizontal and
vertical position angles.
Total Station instruments will be returned to the manufacturer every 6 months for
testing and calibration.
Level instruments will be returned to the manufacturer every 6 months for testing and
calibration. In addition, an opposite two peg will be performed periodically or before
major datum transfers.
The survey team will also use a range of equipment including range poles, stadia rods,
steel bands, tape measures, bar levels, etc.
Rotating laser leveling equipment (Optional)
Laser levels (Optional)
Laser Plummets (Optional)
Measuring Tapes, Marker, Chalk, Spray Paint
Other general surveying and setting out equipment.
Accuracies
Drawings shall be delivered by email in pdf and dxf or dwg autocad format.
Maintenance guidelines:
Auto levels to be checked for collimation error on weekly basis and adjusted if
necessary by Chief Surveyor.
Total stations calibrated by authorized ISO certified dealer. Horizontal and vertical
collimation on each piece of equipment should be calibrated as well.
The contractor shall ensure that the Health and Safety Management Plan is followed
stringently.Where applicable particular site safety procedures shall be adhered to at all
times during site works.
A Daily tool box talk shall be given to all employees; this shall include a 360 Haz ID
(STARRT), findings of which shall be discussed and where practical mitigated.
All workers shall hold in their possession of identification ID cards along with
training ID Cards.
In the event of an emergency the Site Engineer shall immediately inform the the
Health, Safety & Environment (HSE) Manager providing them with all relevant
information regarding the emergency.
During the works, contractor shall ensure adequate barricading in order to restrict
access to authorized personnel only.
Ensure that the personnel deployed are trained and competent to perform the specific
task, under the supervision of competent supervisors.
Ensure all workers comply with the requirements of summer working hours.
Keep available, records of hazards on particular sites. Make sure all relevant people
are notified.
Helmets, steel capped high angle shoes, safety goggles, high visibility jackets, face
masks, overalls should be appropriate and in good condition
Supporting Documents
This method statement for survey works to be read in conjunction with the below-
referenced documents:
Contract Specification
Approved shop drawings
Project Quality Plan
Project HSE Plan
Distribution of the Approved Copy of Method Statement for
Surveying Works
Copies of this method statement for surveying will be circulated to the following for
information & action
Project Manager
Project Engineer
Chief Surveyor
Project Surveyor
Site Engineer
QA/QC Engineer
HSE Engineer
The contractor must have access to a copy of the work method statement when on site
and be able to provide it upon request.