Professional Documents
Culture Documents
Project Dashboard
Project Dashboard
Project Dashboard
xlsx
-0.42
-0.70
-0.57
CPI
Months
-0.78
4
$50 $63 -1.00 -1.00 -1.00 -1.00
$40 $25 $25 -1.07
$10 $10 $20 $20 $0 -1.18
S-Curve
$13,000,000 $12,440,000
$12,000,000
85%
85%
$11,000,000 $10,595,000 $11,758,884
$10,000,000 $9,680,000
$9,000,000 $9,150,000
$8,000,000
$7,000,000
$6,000,000
$5,000,000
$4,000,000
$3,000,000
$2,000,000
$1,000,000 78%
78%
$0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Planned Value (PV) Earned Value (EV) Actual Cost (AC) Actual Time Forescast
Dashboard 1/6
MONTHLY PROGRESS REPORT USING EARNED VALUE MANAGEMENT
PLANNED SCHEDULE
CONSTRUCTION TASKS PLANNED DURATION SCHEDULE OF VALUE May-19 Jun-19 Jul-19 Aug-19 Sep-19
1 2 3 4 5
General Conditions 3.00 $130,000 $43,333.33 $43,333.33 $43,333.33
Long Lead Procurement 3.00 $250,000 $83,333.33 $83,333.33 $83,333.33
Mobilize on Site 1.00 $80,000 $80,000.00
Site Grading and Utilities 1.00 $650,000 $650,000.00
Foundations 2.00 $590,000 $295,000.00 $295,000.00
Steel Erection 2.00 $1,800,000 $900,000.00
Form and Pour Concrete - Floors and Roof 3.00 $1,250,000
Carpentry Work 1.00 $350,000
Masonry Work 3.00 $1,250,000
Roofing 1.00 $800,000
Window wall and store front closures 3.00 $1,350,000
Building Finishes 2.00 $900,000
Elevators 1.00 $550,000
Plumbing 2.00 $750,000
Electrical 4.00 $600,000
HVAC 5.00 $900,000
Final Clean-up and Occupancy 2.00 $130,000
Complete Final Inspections/Punch list/Handover 1.00 $110,000
$12,440,000 $123,333 $776,667 $421,667 $378,333 $900,000
ACTUAL SCHEDULE
CONSTRUCTION TASKS ACTUAL DURATION Actual % Complete
1 2 3 4 5
General Conditions 3.00 100% $43,333.33 $43,333.33 $43,333.33
Long Lead Procurement 3.00 100% $83,333.33 $83,333.33 $83,333.33
Mobilize on Site 1.00 100% $80,000.00
Site Grading and Utilities* 2.00 100% $325,000.00 $325,000.00
Foundations 2.00 100% $295,000.00 $295,000.00
Steel Erection 2.00 100%
Form and Pour Concrete - Floors and Roof 3.00 100%
Carpentry Work 1.00 100%
Masonry Work** 4.00 100%
Roofing 1.00 100%
Window wall and store front closures 1.00 80%
Building Finishes 0.00 0%
Elevators 1.00 100%
Plumbing 0.00 0%
Electrical 2.00 60%
HVAC 3.00 60%
Final Clean-up and Occupancy 0.00 0%
Complete Final Inspections/Punch list/Handover 0.00 0%
$9,680,000 $123,333 $451,667 $451,667 $378,333 $295,000
*DELAY CAUSED BY ADVERSE WEATHER.
**DELAY CAUSED BY A LABOUR STRIKE.
ACTUAL COST
CONSTRUCTION TASKS ACTUAL DURATION ACTUAL COST
1 2 3 4 5
General Conditions 3.00 $100,000 $33,333.33 $33,333.33 $33,333.33
Long Lead Procurement 3.00 $250,000 $83,333.33 $83,333.33 $83,333.33
Mobilize on Site 1.00 $50,000 $50,000.00
Site Grading and Utilities* 2.00 $650,000 $325,000.00 $325,000.00
Foundations 2.00 $550,000 $275,000.00 $275,000.00
Steel Erection 2.00 $1,750,000
Form and Pour Concrete - Floors and Roof 3.00 $1,250,000
Carpentry Work 1.00 $450,000
Masonry Work** 4.00 $1,050,000
Roofing 1.00 $650,000
Window wall and store front closures 1.00 $1,000,000
Building Finishes 0.00 $0
Elevators 1.00 $650,000
Plumbing 0.00 $0
Electrical 2.00 $250,000
HVAC 3.00 $500,000
Final Clean-up and Occupancy 0.00 $0
Complete Final Inspections/Punch list/Handover 0.00 $0
$9,150,000 $83,333 $441,667 $441,667 $358,333 $275,000
EVM Analysis
MONTH 1 2 3 4 5
Planned Value (PV) $123,333 $900,000 $1,321,667 $1,700,000 $2,600,000
Earned Value (EV) $123,333 $575,000 $1,026,667 $1,405,000 $1,700,000
Actual Cost (AC) $83,333 $525,000 $966,667 $1,325,000 $1,600,000
Variance Analysis
Cost Variance (CV) = EV – AC $40,000.00 $50,000.00 $60,000.00 $80,000.00 $100,000.00
Schedule Variance (SV) = EV – PV $0.00 ($325,000.00) ($295,000.00) ($295,000.00) ($900,000.00)
12/14/2021 2
MONTHS
Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
6 7 8 9 10 11 12 13 14 15 16
$900,000.00
$416,666.67 $416,666.67 $416,666.67
$350,000.00
$416,666.67 $416,666.67 $416,666.67
$800,000.00
$450,000.00 $450,000.00 $450,000.00
$450,000.00 $450,000.00
$550,000.00
$375,000.00 $375,000.00
$150,000.00 $150,000.00 $150,000.00 $150,000.00
$180,000.00 $180,000.00 $180,000.00 $180,000.00 $180,000.00
$65,000.00 $65,000.00
$110,000.00
$900,000 $416,667 $833,333 $1,563,333 $1,096,667 $1,580,000 $1,605,000 $1,605,000 $65,000 $65,000 $110,000
MONTHS
6 7 8 9 10 11 12 13 14 15 16
$900,000.00 $900,000.00
$416,666.67 $416,666.67 $416,666.67
$350,000.00
$312,500.00 $312,500.00 $312,500.00 $312,500.00
$800,000.00
$1,080,000.00
$550,000.00
$180,000.00 $180,000.00
$180,000.00 $180,000.00 $180,000.00
MONTHS
6 7 8 9 10 11 12 13 14 15 16
$875,000.00 $875,000.00
$416,666.67 $416,666.67 $416,666.67
$450,000.00
$262,500.00 $262,500.00 $262,500.00 $262,500.00
$650,000.00
$1,000,000.00
$650,000.00
$125,000.00 $125,000.00
$166,666.67 $166,666.67 $166,666.67
CUMULATIVE VALUE
6 7 8 9 10 11 12 13 14 15 16
$3,500,000 $3,916,667 $4,750,000 $6,313,333 $7,410,000 $8,990,000 $10,595,000 $12,200,000 $12,265,000 $12,330,000 $12,440,000
$2,600,000 $3,500,000 $3,916,667 $4,645,833 $5,555,000 $7,127,500 $9,680,000
$2,475,000 $3,350,000 $3,766,667 $4,445,833 $5,291,667 $6,945,833 $9,150,000
12/14/2021 3
S-Curve
$13,000,000
$12,000,000
$11,000,000
$10,595,000
$10,000,000
$9
$9,000,000 $9
$8,000,000
$7,000,000
$6,000,000
$5,000,000
$4,000,000
$3,000,000
$2,000,000
$1,000,000
$0
May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20
0.9
$10,595,000 0.8
$9,680,000
$9,150,000 0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
eb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20