Professional Documents
Culture Documents
Lec-19, Ch-14 & 15, Network Level & Project Level Management M& R Work Planning
Lec-19, Ch-14 & 15, Network Level & Project Level Management M& R Work Planning
4
Introduction
5
M&R Categories
6
M&R Categories
1. Localized Safety
– Localized safety M&R is defined as the localized
distress repair needed to keep the pavement
operational in a safe condition.
2. Localized preventive
– Localized preventive M&R is defined as distress
maintenance activities performed with the primary
objective of slowing the rate of deterioration.
– These activities include crack sealing and patching.
7
M&R Categories
3. Global preventive
– Global preventive M&R is defined as activities
applied to entire pavement sections with the primary
objective of slowing the rate of deterioration.
– These activities are primarily for asphalt surfaced
pavements, e.g. surface treatments.
8
M&R Categories
4. Major M&R
– Major M&R is defined as activities applied to the
entire pavement section to correct or improve
existing structural or functional requirements.
– Major M&R includes recon-struction and structural
overlays.
– The PCI value after major M&R is assumed to be
100.
9
One Year M&R Assignment
One Year M&R Assignment
19
20
One Year M&R Assignment
27
28
Multi Year M&R Assignment
Based on Minimum PCI Method
31
32
Based on Critical PCI
33
Based on Critical PCI
Critical PCI
– A critical PCI is defined as the PCI value at which
the rate of PCI loss increases with time or the cost
of applying localized preventive maintenance
increases significantly.
– Figure 10-12 depicts an example deterioration curve
of the usual range of the critical PCI, which is 55 to
70.
35
36
Based on Critical PCI
41
42
Based on Critical PCI
46
47
Based on Critical PCI
Runways
Taxiways
apron
49
Based on Critical PCI
50
Based on Critical PCI
Prioritization Scheme
– The prioritization scheme emphasizes budget
optimization.
– This is achieved by giving the highest priority to
preventive M&R.
– The exception is localized safety, which should be
performed only when the PCI is below critical and
there are no funds available to perform major M&R.
51
Based on Critical PCI
54
Project Level Management
Project Level Management