Professional Documents
Culture Documents
BRT Prefesibility Study Final Thesis Report
BRT Prefesibility Study Final Thesis Report
Master’s Thesis
Prefeasibility Study of Bus Rapid Transit
System in Kathmandu City
Author
Kesha Shrestha
Date of Submission
Second Supervisor:
Hiermit erkläre ich, dass ich die vorliegende Arbeit selbständig verfasst und keine anderen als
die angegebenen Hilfsmittel verwendet habe.
Author’s Statement
I hereby certify that I have prepared this Master’s Thesis independently, and that only those
sources, aids and advisors that are duly noted herein have been used and / or consulted.
Date: 21.11.2013
Signature: ______________________
On the completion of my thesis, I would like to express my sincere gratitude to all the people
who have made supported me during this rigorous and challenging task.
First and foremost I would like to thank my thesis supervisors Prof. Dr.-Ing. Markus
Friedrich from Institute for Transport Planning and Traffic Control and Prof. Dr. Frank C.
Englmann from Institute of Economics and Law for accepting my thesis proposal. My
sincere gratitude goes to AOR Dipl.-Ing Manfred Wacker from Department from Transport
Planning and Traffic Engineering and Dr. Marion Aschmann from Institute of Economics
and Law for their continuous guidance and encouragement during the period. I thank them
for their effort in guiding and training me throughout the research and analysis period. They
have helped me to shape my thesis in this form.
I would also like to thank Ms Elke Schneider, course director of MIP for her administration
and proper coordination to complete the course work in time. I would also like to thank all
my Professors and faculty members for their support throughout my stay at University of
Stuttgart.
I am very thankful to all my colleagues and friends for their valuable suggestion and
interaction during my study period. Finally, I would like to grab this opportunity to express
my heartfelt gratitude to my beloved parents and sister for their moral support and
encouragement.
Water Body 1.90 2.90 0.70 1.10 2.80 4.33 2.40 3.71
Forest Cover 9.00 13.90 5.70 8.80 1.90 2.93 1.50 2.32
Open Field 4.50 7.00 1.50 2.32 0.50 0.78 0.40 0.62
Cultivated Land 38.40 59.35 39.10 60.43 31.90 49.30 17.30 26.74
The change in the population and land use pattern signifies the necessity of better
infrastructure and planning to supplement them. Among the various components, transport
sector planning is also key component. The current traffic condition of the city is quite
alarming. The road infrastructure has not increased in the past decades while the number of
private vehicles have amplified. This has resulted in the traffic congestions, reduced vehicle
speed, capacity reduction and emissions. The government has failed to intervene to improve
the traffic condition. The public transport is mainly operated by private sector with smaller
vehicles in operations. In absence of proper coordination, the traffic condition in the city is
deteriorating. The demand and supply of public transport is imbalanced. There is less supply
than demand of means of public transport. Hence, the vehicles are overcrowded most of the
time. The government has opted for some measures in the past but not much success has been
achieved.
In this scenario, to cope with the demanding traffic condition, the prefeasibility study of bus
rapid transit system for the city is quite significant. The thesis deals with the current traffic
conditions, estimates the future traffic demand, case study of the existing bus rapid transit
system in other cities, recommends suitable designs for the case specific and finally financial
and economic analysis of the system.
1.2 Objectives:
The main objectives of the study are listed below:
Literature Review: This covers up the detail study of BRT system and its features. There are
many successful cases of BRTs to cater the increasing traffic demand in the world. Hence,
the study will also cover the case study of the existing successful BRTs in other cities. It also
covers up the detail study of the existing transportation condition in Kathmandu. The study of
measures adopted till now and the causes of failure.
Data Collection and Preparation: The related data about the traffic condition are collected
from governmental and non-governmental organisation during the research. The data from
traffic related projects are the main source of data reference.. Adequate and reliable data
availability is the major challenge for the research. The internet is the major source for the
international scenario.
Data Analysis and Planning: The data are analysed to get the information about the demand
and current situation. Based on the demand analysis, suitable corridor will be selected. As
suggested in Bus Rapid Transit Guide (Wright & Hook, 2007), the corridor is selected so as
to maximize the number of beneficiaries, minimize the negative impacts on general traffic,
and minimize operational cost and environmental impacts. The corridor selection is followed
by the infrastructure planning. The elements of BRTs required and suitable for Kathmandu
are identified. The proper cross section of road for BRTs are suggested along with the
necessary steps to be followed to implement BRTs properly. The required number of bus
lines, bus station, bus frequency and number of buses are also planned.
Financial and Economic Evaluation: The BRTs system thus planned are evaluated on the
basis of financial and economic aspects. In order to carry on the evaluation, the tentative cost
for investment are calculated. This will cover the cost for infrastructure (such as modification
of the existing road structure, bus stations, and workshop areas), Cost of vehicles,
Operational cost such as cost of fuels, staff and administrative cost. The estimate of revenues
that will be collected are done so as to carry on cost benefit analysis. The social benefits will
also be considered for the economic analysis. Finally the sensitivity analysis of the project
will be carried on with the change in its critical parameter.
Limitations: The key limitations during the study is the availability of the data. In the
developing cities like Kathmandu it is hard to get the adequate and reliable data. The study
report on the current traffic condition is difficult to collect. Hence, the forecasting of the
future demand is quite challenging. In this condition appropriate assumptions has to be made
for further analysis. Since, there has not been study for BRT in past, hence the local rates for
Figure 2: Road Classification within Kathmandu City Source: (JICA, 2012:Ap 3-4)
Figure 4: Comparison between Travel Modes in 1991 and 2011 in Kathmandu valley
Source: (JICA, 2012:6-11)
Walking covers a large share in the modal share, however the walking environment needs
improvement. The sidewalks are usually narrow, badly paved, having difficulty to cross
crowds and pedestrians are obliged to give way to vehicles in the city core. The condition is
worse for physically disabled people due to lack of facilities for wheel chairs (KSUT, 2010).
The decrease in the share of bicycle clearly indicates the lower facilities for cycling.
Currently bicycle lanes are being constructed in certain area in the city but still requires a lot
of effort to make it substantial.
Buses 14
Taxis 7000
These are the vehicles plying within the valley only, while additional 925 buses , 114 mini
buses and 22 micro buses with extend their operating services outside Kathmandu Valley.
(KSUT, 2010). In addition to normal buses , there are also 16 buses under Sajha yatayat with
seat capacity of 54 running within the city since March 2013. (Yatayat, 2013)
1 Although 860 gas tempos are registered with DOTM, only 430 are operating. (KSUTa, 2010:10)
2.4.1.b Microbuses
They have the seats between 6 – 14 passengers. They are also major means of public
transport which is clear from the number of vehicles plying as shown in the table above.
These are all run by private sectors and hence there is a high competition. There are also two
type of microbuses depending of the fuel used. Some have 800 cc petrol engines whil eothers
have been converteed to run on LPG i.e using domestic cooking gas cylinders. (KSUTa,
2010:10)
2.4.1.c Tempos
Tempos are three wheelers having seat capacity up to 11 seats. There are also two types
depending upon fuel used. LPG and battery operated tempos, popularly known as Safa
tempos (meaning clean tempos). (KSUTa, 2010:10-11)
As mentioned earlier there are around 430 gas tempos running in the Valley. They run on
LPG gas and the way these gas cylinders are connected to engines are regarded as unsafe.
Hence there are some proposals from members of transport industry to ban these tempos for
environmental and safety reasons. The association representing Safa tempo owners, CLEAN,
are willing to convert them to run on batteries. It is technically feasible but the licensing
regulations do not permit the change (KSUTa, 2010:10-11)
There is also a high number of Safa tempos plying in the city with a total of 603 numbers.
These were first introduced in Nepal under a Danish program subsidizing the services until
they were established. (KSUTa, 2010:10-11). These vehicles ply exclusively in five routes
with additional 11 routes shared with other vehicles. The major problem with these types of
vehicles has been loadshedding which mounted upto 16 hours a day in 2009. Currently there
is loadshedding of around 7 hours a day which is quite managable.
2.5 Parking:
Both on street parking and off street parking are available in Kathmandu. According to the
information gathered during the inventory survey and interviews done in the central area of
Kathmandu for KSUT project, shows that there are inadequate numbers of parking lots for
cars and motorcycles. Furthermore the charges are also low, which resulted in the full
occupancy most of the time (KSUT, 2010:74). The parking fee was first introduced in
Kathmandu Metropolitan areas since April 1995 on 17 sectors (Jha, 2001). The parking lots
are ususally within the city area. The parking lots are usually managed by some commercial
complexes, banks etc as private parking, while few are managed by KMC and LMC.
To cope with the increasing demand for parking government has to find places nearby for
parking. However, according to KSUT report very little government land is available in
appropriate places and land in appropriate locations is privately owned and therefore too
expensive to be utilized for a relatively low revenue yield compared to commercial uses.
(KSUT, 2010:74)
Figure 5: Trends in the number of traffic accidents in Kathmandu valley Source: (Dhakal, 2006)
Bus Rapid Transit system, an economical and efficient form of mass transit for growing
cities. It was first introduced in Curitiba around 1974 for 24km long system. Ever since the
launch of BRT system the popularity is growing from Latin America to North America,
Europe and Asia. First BRT system in Asia was launched in 15 January 2004, the
TransJakarta busway along 12.9 km long corridor through the city centre. BRT corridors
were installed in Seoul on 1st July 2004 (Matsumoto, 2006). It is also operated in various
other cities of Asia such as in Beijing, Ahmedabad and Delhi (India), Bangkok etc.
3.1 Definition
BRT system is described in bus rapid transit guidebook as a bus based transit system of high
quality delivering fast, comfortable and cost effective urban mobility. These services are
delivered by the provision of segregated right of way infrastructure, rapid and frequent
operations and excellence marketing and customer service (Wright & Hook, 2007: 11).
In the meantime, BRT system has been defined in Levinson, et al., 2003 as “a flexible, rubber
tired rapid transit mode that combines stations, vehicles, services, running ways and
intelligent Transportation System (ITS) elements into an integrated system with a strong
positive identity that evokes a unique image.”
BRT is “high quality, customer oriented
transit that delivers fast, comfortable and cost
effective urban mobility”. (Wright &
Fjellstrom, 2003)
BRT system is also known with various
names such as High Capacity Bus Systems,
High Quality Bus Systems, Metro Bus,
Surface Bus, Express Bus Systems and
Busway Systems (Wright & Hook, 2007).
The performance of BRT system is similar to
modern rail based transit system but at an
economical price. It might be in the range of 4
to 20 times less than light rail system and
around 10 to 100 times less than a metro
system. The relation between the cost and
various mass transit system is shown in the
Figure 7 and Figure 8
Figure 7: Passenger Capacity and capital cost per mass transit
options (Source: (Wright & Hook, 2007:72)
2. Operations:
The operation of BRT system will be characterised by frequent and rapid service between
major origins and destination. The boarding and alighting from the vehicle will be rapid.
The service will be sufficient for passengers demand along the corridor. The fare
collection and fare verification will be done pre board. In most of the cases the fare
integration between routes, corridors and feeder services will be done. (Wright & Hook,
2007:12)
4. Technology:
BRT system is characterised by low-emission (Euro III
or higher) and low noise vehicle technologies as shown
in Figure 12. The fare collection is done automatically
with fare verification technology installed in the system.
The system management is done through a centralised
control centre with the utilisation of Intelligent Figure 12: High technology vehicle
Transportation systems (ITS) such as automatic vehicle on Eindhoven BRT corridor :
location. There is a signal priority or grade separation at Source: APTS
Figure 17: Phase I of TransMilenio of 40 km of exclusive busway in Left and expected total system is
expected consist of 380 km by 2015. (Source: TransMilenio SA)
The successful implementation of the TransMilenio shows that BRT system can be an
effective, efficient and comapartively cheap solution to light rail system for Mass transit. The
system can be implemented in a short span of time making it more suitable for urgent
requirements. Furthermore, it has also been observed in the case of TransMilenio that it can
be self sustained if effective planning and operation is undertaken. It has to be noted that
effective palnning is a key to the success of the project. The invovement of stakeholders from
the start of the project seems to have a positive impact in the project as well.
4.1 Routes
For the corridor selection in the case, the primary routes defined by Kathmandu Sustainable
Urban Transport has been taken for considerations.The current situation of urban bus network
has been explained earlier in chapter 2. The Kathmandu Sustainable Urban Transport Project
has proposed that the urban bus network should be redesigned with the hierarchy of routes to
simplify the complex network. The routes will be operated by the most appropriate type of
vehicle. The proposed hierarchy of the routes are as follows:
1) Primary Routes
2) Secondary Routes and Tertiary Routes
1) Primary Routes: These routes will include the main roads which are capable of
accommodating the full sized buses. These will operate mostly across the city centre,
from one terminal on the outskirts of the urban area to another. In addition it will not
terminate in the centre. Terminal points should be as mentioned in the outskirts of the
city near to Ring Road or to some distance outside from it (KSUT, 2010:17-18). The
primary routes are shown in the Figure 18.
Based upon the above criteria there are four corridors which are selected for Primary
routes in KSUT project where BRT may be implemented. The details of the criteria
for the corridors has been shown in Appendix III. From the available information
based on the criteria three routes seems to be appropriate for BRT system
implementation. They are Ring Road, Narayan Gopal Chowk to Ekantakuna and
Kalanki to Koteshwor. However, in this study, two of them have been taken for
further studies based upon there characteristics. Both the corridor selected pass
through the city core and their improvement will affect the city as a whole. In case of
Ring Road , there is Improvement project of Kathmandu Ring Road (DOR, 2012)
ongoing for its expansion to eight lanes, so implementation of BRT system may not
2. Kalanki – Koteshwor
It runs through the east west direction of the city nearly dividing the city in two parts within
Ring Road. As mentioned in the working paper it is the heaviest trafficked section around
128,000 passenger trips per day. The traffic displays opposite directional flows in the
morning and evening. (Ingham, 2012) The existing public transport consists of mini buses,
microbuses and tempos. (Ingham, 2012) The quality as in other parts of the city is quite low,
with no proper time tables and no fixed bus stops. The increasing passenger demand has
urged for a better and improved public transport. Hence it is recommended for mass transit
option to maximise the person moving capability of the transport system. (Ingham, 2012).
Thus, it has been selected as BRT corridor for further study.
In order to predict the future demand of the passenger growth, JICA survey report has been
referred. According to the JICA survey report (JICA, 2012), if the ongoing major road
development projects such as expansion of Ring Road to four lane roads, expansion of
Arniko Highway inside the Ring Road to six lanes road, expansion of Tribhuvan Highway
outside the Ring Road to four lanes, all narrow roads would be improved to have a capacity
of at least 2 lanes, and all roads with bad surface condition would be improved to have fair
condition at least are to be completed, then the ratio of person trips/day within the ring road
for 2022/2011 will be 1.61 (JICA, 2012:8-14). Hence for this study also passenger volume /
day in 2022 is estimated with an increase by 1.61 in 2022 as shown Table 8.
Figure 20: A Typical Roadway configuration for BRT. (Wright & Hook, 2007:157)
2. Fixed guideways:
Normally 3.5 meters of road width is required for vehicles plying and 3.0 meters at
station but it can be squeezed to 2.7 meters with aid of a guidance mechanism. (Wright &
Hook, 2007:168) It physically restrains the vehicle with the guidance mechanism
reducing the required width. They have already been implemented in Adelaide, Bradford,
Leeds, Essen and Nagoya. The BRT lane using mechanical guidance to reduce road
width is shown in Figure 22. With the use of fixed guideway, around 0.9 meters of lane
width can be reduced. In addition, it can help to increase the operating speeds and ensures
Figure 22: Nagoya's elevated BRT line using a mechanical guidance system
to reduce the required roadway width (Source: Lloyd Wright)
3. Elongated stations:
Normally the median station requires a width of 3.0 meters while separated station
requires 2.5 meters each.
In addition single station
serves both the direction
hence it is more
convenient for
passengers to change
direction if necessary.
The separated station
will require additional
infrastructure for
pedestrians passing. In
addition, building two Figure 23: Standard BRT configuration (Wright & Hook, 2007)
stations will cost more
than one station. Hence median station is preferable than separated one. (Wright & Hook,
2007:170)
Furthermore the width of station is function of the projected peak passenger volume. In
case of median station two vehicles might stop at the same time, requiring larger space at
the station. Hence to meet this requirements, station itself can be elongated to offset the
placement of the station doors for each direction. This will also result in the reduction of
the station width from 3m to 2.5 m as shown in Figure 23 and Figure 24 (Wright &
Bi articulated 24 240-270
Articulated 18.5 120-170
Standard 12 60-80
Mini - bus 6 25-35
The size of the vehicle is the key factor for the determining the number of vehicles required.
When the vehicle chosen is small then the number of vehicles required will be high.
However, the frequency will be high and headway will be less, giving an advantage to
passengers of less waiting time. However, it will also be reflected in the higher cost of
operation. (Wright & Hook, 2007) Giving consideration to all the factors, in this case
articulated bus with capacity of 160 passengers has been chosen for BRT vehicle.
There are two other factor that influence the vehicle fleet size, they are peak passenger
demand at critical point along corridor and total travel time to complete a cycle as reflected in
the Equation 1 (Wright & Hook, 2007:256).
Equation 1: Total Operational Fleet for a Corridor (Wright & Hook, 2007:256)
Ft
Operational fleet size for corridor (Fo)
Contingency value (Cv)
Total Fleet Size ( Ft)
The calculation of the fleet size required for the two corridors are shown in
Table 12 and Table 13 below.
Table 12: Calculation of Fleet Size required for Corridor I
Description Values Units
Demand on critical link (D) 3100 pphpd
2
Travel time for a complete cycle (Tc) 72.6 minutes
Vehicle capacity (Cb) (passengers/vehicle) 160 passengers
Assuming the contingency value of 10 percent, the total fleet required for the corridor will be:
2The speed of 26km/hr has been assumed and dwell time of 15 secs for each stations has been assumed along
with 10 minutes of layover time.
3
The speed of 26km/hr has been assumed and dwell time of 15 secs for each stations has been assumed along
with 10 minutes of layover time.
Figure 26: Illustrative comparison between trunk-feeder and direct services. (Source: Wright &
Hook, 2007:217)
The type of the system to be chosen also depends upon the demand estimated as shown in the
Table 14. For the demand in between 2000 to 8000 pphpd, segregated median busway used by
direct services can be implemented. Since we have demand of around 4000 pphdp, direct
services seems to be sufficient in our case.
2000 to 8000 Segregated median busway used by direct services reducing the need to
transfer
8000 to 15000 Segregated median busway used by trunk services requiring transfers but
benefitting from fast boarding and operating speeds. Transit priority at
intersections
6.1 Runways:
Table 17: Recommended minimum lane widths
BRT guideline suggest that the construction of the per direction
runway will take more than fifty percent of the total
cost of the infrastructure. Hence proper
considerations should be given for the design of the
runway (Wright & Hook, 2007:346). The required
right of way for the system is taken with reference to
the recommended minimum lane widths that was
actually used in Quito BRT system as shown in the
Table 17 (Wright & Hook, 2007:351). The required
right of way with segment wise break up has been
shown below for the normal and the bus station is
given in the table below. Since elongated bus station
is considered, the width has been adjusted to 2.5 m
from 3m.
Sidewalk 3 3
Mixed Traffic 3.5 3.5
Bus lane 3 3
Island 1 2.5
Bus lane 3 3
Mixed traffic 3.5 3.5
Sidewalk 3 3
Bicycle lane 0 0
Total 20 21.5
As shown in Table 18 that the required right of way for normal section and section at bus
station is 20m and 21.5 m respectively. The separate bicycle lane hasn’t been considered. It is
Figure 27: BRT Cross Section at Normal Section 20m (Dimensions are in meters)
Figure 28: BRT Cross Section at Bus Station 21.5m, (Dimensions are in meters)
6.2 Stations
The stations width has already been recommended with the width of 2.5 meters. The station
here chosen is an elongated one in order to cope with the existing road condition. The station
has also to do a lot with the usability, comfort and attractiveness. The attractiveness of the
station also plays a vital role in the success of the overall system. There exists various kinds
of aesthetically sound stations like station used in other BRT systems are tubed stations that
are used in Curitiba, simple yet modern station used in Brisbane as shown in Figure 30 and
Figure 31. They have also created an iconic identity for the city itself (Wright & Hook,
2007:360-366). The simple yet functional type of station should be built in the case too.
Figure 31: Station at Brisbane. (Queensland Figure 30: Modern tubed Curitiba's station (URBS and
Transport) Municipality of Curitiba)
Figure 33: Schematic showing the simple transfer from a trunk vehicle (on left) to a feeder
vehicle on right. ( Source: Steer Davles Gleave)
In addition to the transfer it also provides the facility of parking of the vehicles in order to
provide space for vehicle services. Likewise, depots are the area which provides the facility
to park the vehicles, vehicle services and repair. The additional facilities such as the
employee services and administrative support is also provided. (Wright & Hook, 2007:378-
384). It is usually the case that the terminals and depots are nearby. As in the case of Bogota
as shown Figure 34. The space required for the depot depends upon the vehicle fleet
basically.
Figure 34: Terminals and depots adjacent to each other in Bogota. (Source: Oscar Diaz and
PPQ)
The depots should have sufficient space for accommodating the space required for the
administrative areas, refueling areas, vehicle cleaning and washing areas, major and minor
repair area, BRT vehicle parking area as well as the area for some private vehicle as well.
(Wright & Hook, 2007:390). In our case we require two termials and two depots for each
Figure 35: BRT corridors, terminals, depots, control centre and Intermediate
Parking
Figure 37: Stations along feeder lines (Source: Llyold Figure 36: Kathmandu Bhaktapur Road (Source:
Wright) http://www.jica.go.jp/nepal/english/activities/transpor
tation.html)
Traffic Police
Traffic police can also be involved in the project for the proper execution of the segregated
bus lanes. It is primary concern of the BRT system to have exclusive busways. It has been
seen in the past that no proper traffic rules have been followed, hence it is necessary to force
people to use the designated lanes only. They will help to ensure the priority of BRT vehicles
at the intersections as well.
7.4 Conclusion
As already been stated BRT system is quite a challenging task, hence it requires the support
of various organisations at different time. The core operation and management team can be
from the coordination of various governmental organisations with the coordination from the
non-governmental organisation such as Sajha yatayat cooperative. They have the experience
to operate the public transport. The experience of TransMilenio shows that public private
partnership can be one of the suitable solutions. The governmental organisation can
participate in the investment of the infrastructure and non-governmental organisations and
others can involve in the operation undertaking the cost of fleets and other operational
charges. Apart from the investment, the coordination of various governmental organisation is
also necessary for the implementation and smooth running of the project as main executing
and managing authorities. Hence, a separate committee can be formed which overlooks the
project involving all the concerned governmental and non-governmental organisation.
Table 20: Detailed Cost Breakdown of per km costs for Bogota's TransMilenio BRT System
4
The rate of asphalt has been taken from rates used in KSUT project for asphalt pavement (KSUT, 2010, p. 121). Since, the width of our lane is 22m, it leads to the value of
440,000 per km.
5
The cost of 3meter wide station has been taken form Hyderabad BRT system estimates (ITDP, 2005, p. 79). The cost of station is estimated to be around 130,000 US$.
Since the cost in India and Nepal are quite similar, the reference has been taken.
Enter km of improved
Pedestrian access to station areas footpaths
Improvements to pedestrian
access ways 35,000 US$ per km 12.2 $427,000.00
Boarding bridge between bus and
station Enter no. of km of busway
Boarding bridge for each bus
doorway (half paid by city) 2,000 US$ per bus 12.2 $51,240.00
Control center (including
software) Enter no. of control centers
6The cost of control centre has been adjusted from the cost provided in the BRT cost calculator as the scale of the project is reduced than assumed in cost calculator. Hence it
has been adjusted for 12.2km, as the cost for 50km system and 12.2 km system will vary.
7The cost for terminals and depots has also been changed based upon the total kilometres of the BRT system and vehicles required. As the BRT system is only 12.2 km not
50 km as shown in BRT cost calculator sample, the cost will definitely be reduced.
8
The rate has been taken from KSUT project, as it estimates 20,000 US$ per toilets. (KSUT, 2010, p. 119)
9
It has been taken from the BRT calculator rates itself for rough estimation.
10The rate of asphalt has been taken from rates used in KSUT project for asphalt pavement (KSUT, 2010, p. 121). Since, the width of our lane is 22m, it leads to the value of
440,000US$ per km.
11
The cost of 3meter wide station has been taken form Hyderabad BRT system estimates (ITDP, 2005, p. 79). The cost of station is estimated to be around 130,000 US$.
Since the cost in India and Nepal are quite similar, the reference has been taken.
12 The cost of control center has been adjusted from the cost provided in the BRT cost calculator as the scale of the project is reduced than shown. Hence it has been adjusted
for 12.2km, as the cost for 50km system and 12.2 km system will vary.
13
The cost for terminals and depots has also been changed based upon the total kilometres of the BRT system and vehicles required. As the BRT system is only 7.7 km not
50 km as shown in BRT cost calculator sample, the cost will definitely be reduced.
Property acquisition15
Enter no. of terminals or
depots
Terminal site in peripheral US$ per
area 1,000,000 terminal 2.0 $2,000,000.00
US$ per
Depot site in peripheral area 770,000 depot 2.0 $1,540,000.00
Sub-total $13,480,550.00
Contingency
10% contingency US$ $1,348,055.00
Total $14,828,605.00
Cost per kilometer
(including planning costs) $1,925,792.86
14 The rate has been taken from KSUT project, as it estimates 20,000 US$ per toilets. (KSUT, 2010, p. 119)
15
It has been taken from the BRT calculator rates itself for rough estimation.
Hence for the calculation of the operating cost, the cost has been calculated based on the
above two tables. For fixed operational cost and finance charges, it has been referred to Table
24 and for Variable Operating cost it has been referred to Table 25. Since,
The detail of the operational cost calculated as per the local rates is shown in Table
26.
Table 26: Operational Cost
Value
Per
Item Measurement Units vehicle Remarks
Depreciation USD
Number of vehicles
Vehicle Depreciation % of value of vehicle / year 10% 1,050,000 required is 50
Finance charges
Effective annual interest rate
Cost of capital on invested capital 14% 4,722,747
5,772,747
Fixed Operating
costs
Diver and Conductor
salaries Employees / vehicle 4.6816 776,565
Salaries of
mechanics Employees / vehicle 0.38 60,719
Salaries of
administrative In an average salary
personnel and is assumed to be NRs
supervisors Employees / vehicle 0.32 51,132 20000/month.17
16 Additionally 2 is added per unit considering the units for conductors as well. As it has not been included in
the rate previously.
17
The minimum rate in Government is around NRs 12,000 per month and for driver, additional benefits will
also be there which will increase the salary up to NRs 20,000 per month.
The total operational cost, Infrastructure cost and cost of vehicle is shown in Table 27.
Table 27: Summary of Cost
Corridor Corridor 1 Corridor 2 Total
Length 12.2 km 7.7 km
Total Infrastructure Cost 18,905,304 14,828,605 33,733,909
Vehicle Number 26 24 50
Vehicle Cost 19 5,460,000 5,040,000 10,500,000
Assuming the construction will be completed in 2 years
Capital cost/year 9,452,652 7,414,303 16,866,955
18Number of trips is assumed to be 7 per day and 300 days per year with adjustment for off peak and vacations.
Cost of fuel is assumed to be 3.87 USD per gallons of diesel as per rate in 2013 from Nepal Oil Corporation
19
The vehicle cost has been estimated to be 210,000 US$/vehicle as per rates in BRT Guide. (Wright & Hook,
2007, p. 441)
`Year 1 2 3 4 5 6 7 8 9 10
Total
operating
Revenues 15,529,374 16,330,128 17,130,882 17,931,636 18,732,390 19,533,144 20,333,897 21,134,651
Total Inflows - - 15,529,374 16,330,128 17,130,882 17,931,636 18,732,390 19,533,144 20,333,897 21,134,651
Total
operating
costs and
Capital Costs 2,361,374 4,722,747 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838
Infrastructure
Costs 16,866,955 16,866,955
The reduction in accident due to BRT system is also a benefit. However, it hasn’t been
considered for analysis due to insufficient data. Nevertheless, it will have a positive impact and
will be considered as benefit from the system. Similarly increased safety and reduction in
accidents is also benefit of the system and will have positive impact in overall outcome of the
project. Table 30 shows the variable and unit of benefits from BRT system to be evaluated.
Time spent during travelling is an expense and an important factor for calculating the benefits of
BRT. To calculate the gross average hourly wage rate for Nepal, gross national income per
capita for 2012 is taken as reference which equals to 1500 USD from World Bank (Word bank,
2013).
So deducting the non-working days and assuming 7 working hours a day, resulting wage rate
was 0.96 USD/hour20. This leads to the value of 0.02 USD/mins. For the value of working time
savings and non-working time savings has been calculated as suggested in transport notes by
World Bank (The World Bank, 2005, p. 10) i.e 30% of the price of working trips.
As suggested in KSUT project report, 5 minutes saving is not so much of importance (KSUT,
2010, p. 144). But if it is done for collectively for all passengers then it might be of some
importance. Hence, in this case time saved up to 5 minutes during travel has been neglected.
20The working days have been calculated by deducting the public holidays as published in February for
the year 2013/014 (Nepalnews, 2013)
Since the BRT system come into operations from 2015 AD only, its benefit will also be calculated
from there forth. The total number of passengers per day and annually is shown in the Table 33.
Nepal 707
Euro area 36,550.20
Ratio 0.019
This gives a value of CO2 per MT as 0.86 $ in 2015 instead of 32.5 Euro per MT as derived from
the Table 35.
The Table 38 shows the savings due to decrease in CO2 emission after the application of BRT
system.
Tempos21 130,000 1460.00 38.30 100.00 30.00 30.00 12.0 21,960 1,100 10 9 0.4
Microbus22 1,440,000 6390.00 44.46 156.35 32.00 68.75 12.0 21,960 1,100 10 14 2.0
Mini Bus23 959,470 7695.27 44.46 156.35 32.00 128.13 12.0 21,960 1,100 12 24 5.0
Articulated
Buses24 14,950,000 11892.00 44.46 156.35 32.00 128.13 12.0 21,960 880 15 160 18.5
21The input data related to cost for tempo has been taken from KSUT report for year 2009. For annual km driven it is assumed that the vehicles are plying in BRT
corridor for 6 trip a days and 300 days per year in 12.2km. The annual working hour is derived by assuming average speed of 20 km/hr.
22
The input data related to cost for Micro bus has been taken from KSUT report for year 2009. For annual km driven it is assumed that the vehicles are plying in
BRT corridor for 6 trip a days and 300 days per year in 12.2km. The annual working hour is derived by assuming average speed of 20 km/hr.
23
The input data related to cost for Mini bus has been taken from KSUT report for year 2009. For annual km driven it is assumed that the vehicles are plying in BRT
corridor for 6 trip a days and 300 days per year in 12.2km. The annual working hour is derived by assuming average speed of 20 km/hr.
24
The input data has been taken for year 2009 in case of cost. For annual km driven it is assumed that the vehicles are plying in BRT corridor for 6 trip a days and
300 days per year in 12.2km. The annual working hour is derived by assuming average speed of 26 km/hr.
Year VOC without BRT in US$ VOC with BRT in US$ Difference in US$
Time saving 810,291 852,072 893,854 935,636 977,417 1,019,199 1,060,981 1,102,762
Total Inflows - - 16,738,789 17,587,628 18,436,469 19,285,313 20,134,158 20,983,006 21,831,856 22,680,709
Total operating
and Capital
costs 2,361,374 4,722,747 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838
Infrastructure
Costs 16,866,955 16,866,955
Total Outflows 19,228,328 21,589,702 20,012,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838 9,512,838
Net Cash flow - 19,228,328 - 21,589,702 -3,274,049 8,074,790 8,923,631 9,772,475 10,621,320 11,470,168 12,319,018 13,167,871
Hence, even though with the present consideration, it might seems that the project is not
feasible but on the broader perspective, and analysing the project with other benefits, the
project can be feasible for sure.
The sensitivity analysis of the change in demand shows that, the project is sensitive with
passenger demand estimates for sure. If the demand is less than projected then the revenues
generated will be less, and will surely effect the benefits from the project. Even though the
operating cost will be reduced but the infrastructure cost that has been invested will remain the
same. This will have a negative impact on the overall benefit of the project which will make the
project infeasible.
However, if the demand is increased by 10 % then it seems that the project will be more
beneficial, as the revenues collection will be more resulting in the positive result. However, it
can also effect the headway. The current headways are 3 minutes and 2.4 minutes in Corridor I
and Corridor II respectively. Hence if the demand is increased by 10% then the headway will be
decreased to 2.7 minutes and 2.2 minutes during peak hours. However, it is above 2 minutes and
seems to be quite practical.
10.7 Conclusions
The prefeasibility analysis of the BRT system for two selected corridors for Kathmandu city
suggests that technically it is possible to implement BRT system with the forecasted passenger
volume. However, based on financial and economic analysis the project seems to be infeasible or
unprofitable. The analysis shows that the BRT system can resolve the increasing traffic demand
in those corridors. During the analysis, various assumptions have been made, which has
influenced in the result of financial and economic analysis. The following points highlights the
key points of the study:
1) BRT system can be implemented in the selected corridors as its estimated traffic demand
is more than 2000 pphpd.
2) BRT system with articulated bus with on board ticketing with conductor and level
platform at bus station is enough for the projected demand.
3) The system will have a headway of 3min and 2.4 min in Corridor II and Corridor I at
peak hour for 2022 AD.
4) Elongated stations, terminals, depots and control centre are required the BRT
infrastructure required.
5) The BRT system need to address the problem which will arise while replacing the present
transport operators.
6) Since the BRT system requires a segregated lane for BRT vehicles strong traffic rules
implementation is necessary.
7) The operation and management of the project can be done by public private partnership.
The government can invest in infrastructure and operation can be handled by private
partners. However, there should be proper coordination between the organisations.
8) The financial analysis shows that the system is not feasible as the internal rate of return is
less than that of discount rate. It might require government subsidy to sustain. However,
there might be various considerations that have been taken might have played the role.
9) In case of economic analysis, there are various benefits that will occur after BRT system
implementation that has not been considered. The economic analysis done on the base of
three benefits shows that the project is unprofitable.
10) The sensitivity analysis done with change in passenger volume shows that the increase by
10 % will make it profitable economically.
Existing
Passenger Transport Roadway
Road Name Directional Split Economic Linkages Operators in
Volume / day Linkages Geometry
corridor
Ring Road 27.3 106,000 North of Non-directional. Balaju Industrial Estate Extensive linkages Generally 2 8 Minibus &
km Kalanki to Airport and road lanes with Microbus
based terminals as limited operators run the
follows: portions 4 whole route.
98,000 at Balaju This is a circular Patan Industrial Estate · Kalanki lanes. Many operators
107000 between route requiring Swayambunath & · Sitapalia use portions of the
Sinamangal & separate services per Pashupati temples route. Ave 5-6
Tinkune direction microbus and
92000 Manahara Commercial hubs at · Shwayambunath minibus routes on
Bridge Kalanki, Gongabu, any section.
73000 between Maharajganj, Chabahil · Gongabu
Ekantakuna & & Koteshwor · New Bus Park
Balkhu
· Samakhusi
· Chapal Karhana
· Sinamangal
· Koteshwor
· Gwarko
· Satdobato
· Bagdole
· Balkhu
Hence the required number of Vehicles in absence and presence of BRT is as follows:
Table 46: Vehicles Projection with and without BRT system
It has been assumed that the Fuel consumption for BRT vehicle is 18.6litre/100 km. (Wright &
Hook, 2007, p. 580)
Similar Calculation were done for other years too shown in Table 49.