RFX 

2131800021 B

RFX#21B SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF GRE WATER TRANSMISSION PIPELINE & 
ASSOCIATED WORKS AT VARIOUS LOCATIONS IN THE EMIRATE OF DUBAI
Additional Works ‐  GRE pipeline  at MUSHRIF  
BASED ON ASSUMPTION THAT VALVES AND FLOW METER WILL BE GIVEN ON LOAN BASIS FROM DEWA

2.9 KM ADDITIONAL 1200MM DIA WATER LINE NEAR MUSHRIF RESERVIOR (THROUGH ACADMIC CITY ROAD)
Activity ID Activity Name Duration Start Finish
PROTECTION OF 1200MM DIA WATER LINE NEAR MUSHRIF RESERVIOR (THROUGH ACADMIC CITY ROAD)
  NOC
    A2010 DESIGN NOC (TO BE ISSUED BY DEWA) 1 01‐Oct‐21 02‐Oct‐21
    A2020 INFORMATION NOC 7 01‐Oct‐21 08‐Oct‐21
    A2030 TRIAL PIT NOC 7 01‐Oct‐21 08‐Oct‐21
  TRIAL PIT WORKS
    A2040 TRIAL PIT WORKS 20 08‐Oct‐21 28‐Oct‐21
    A2050 VERIFICATION OF TRIAL PIT WORKS 10 28‐Oct‐21 07‐Nov‐21
    A2060 DEMARCATION 7 05‐Oct‐21 12‐Oct‐21
    A2070 SETTING OUT 20 08‐Oct‐21 28‐Oct‐21
    A2080 INITIAL SURVEY 20 08‐Oct‐21 28‐Oct‐21
    A2090 CONSTRUCTION NOC (Approval from All Authorities) 25 07‐Nov‐21 02‐Dec‐21
    A2100 NDRC NOC (MICRO TUNNELING) (Approval from All Authorities) 21 02‐Dec‐21 23‐Dec‐21
    A2110 NDRC NOC (THRUST BORING) (Approval from All Authorities) 21 23‐Dec‐21 13‐Jan‐22
    A2120 NDM NOC (AS REQUIRED) (Approval from All Authorities) 21 13‐Jan‐22 03‐Feb‐22
  ENGINEERING
    SHOP DRAWING
    A2130 SUBMISSION OF SHOP DRAWING 21 07‐Nov‐21 28‐Nov‐21
    A2140 APPROVAL OF SHOP DRAWING 21 07‐Nov‐21 28‐Nov‐21
  PROCUREMENT
    A2150 GRE PIPE 1200mm DIA 21 07‐Nov‐21 28‐Nov‐21
    A2160 GRE SELF RESTRAINED PIPE 1200mm DIA  21 28‐Nov‐21 19‐Dec‐21
    A2170 GRE & SELF RESTRAINED FITTINGS 21 28‐Nov‐21 19‐Dec‐21
    A2180 STEEL SLEEVE  21 28‐Nov‐21 19‐Dec‐21
    A2190 VALVES (MOTORIZED BUTTERFLY VALVE, AIR VALVE & WASH OUT VALVE, FLOW METER, TMBV) ON LOAN BASIS FROM DEW 21 28‐Nov‐21 19‐Dec‐21
    A2200 SCADA MATERIAL 73 28‐Nov‐21 09‐Feb‐22
  CONSTRUCTION ( TO START AFTER RECEIVING ALL NOC & PERMITS and APPROVAL OF ALL DRAWINGS)
    PIPELAYING WORKS ( 2900 MTRS)
    A2200 EXCAVATION FOR POTABLE WATER LINE 90 02‐Dec‐21 02‐Mar‐22
    A2210 PIPELAYING WORKS 90 05‐Dec‐21 05‐Mar‐22
    A2220 BACKFILLING FOR POTABLE WATER LINE 90 08‐Dec‐21 08‐Mar‐22
    A2230 CCTV TESTING 60 07‐Jan‐22 08‐Mar‐22
    A2240 PRESSURE TESTING 3, 9 & 10 BAR (USING PRESSURE GAUGE) 60 06‐Feb‐22 07‐Apr‐22
    CROSSINGS
    A2250 BOREHOLES 10 23‐Oct‐21 02‐Nov‐21
    A2260 PRE‐DRIVE LEVELS 7 23‐Oct‐21 30‐Oct‐21
    A2270 POST‐DRIVE LEVELS 7 28‐Jan‐22 04‐Feb‐22
          NDRC WORK (MICRO TUNNELING)
    A2280 EXCAVATION FOR DRIVING PIT/RECIEVING PIT 14 23‐Dec‐21 06‐Jan‐22
    A2290 BLINDING FOR DRIVING PIT 4 06‐Jan‐22 10‐Jan‐22
    A2300 JACKING/THRUST WALL 4 10‐Jan‐22 14‐Jan‐22
    A2310 MICROTUNNELING WORK 14 14‐Jan‐22 28‐Jan‐22
    A2320 CLOSING OF NOZZLE HOLES 4 28‐Jan‐22 01‐Feb‐22
    A2330 INITIAL TESTING 7 01‐Feb‐22 08‐Feb‐22
    A2340 FINAL TESTING 7 08‐Feb‐22 15‐Feb‐22
          NDRC WORK (THURST BORING)
    A2350 EXCAVATION FOR DRIVING PIT/RECIEVING PIT 14 13‐Jan‐22 27‐Jan‐22
    A2360 BLINDING FOR DRIVING PIT 4 27‐Jan‐22 31‐Jan‐22
    A2370 JACKING/THRUST WALL 4 31‐Jan‐22 04‐Feb‐22
    A2380 AUGER / MANUAL BORING WORKS 14 04‐Feb‐22 18‐Feb‐22
    A2390 CASING INSTALATION 4 18‐Feb‐22 22‐Feb‐22
    A2400 SLEEVE INSTALLATION 7 22‐Feb‐22 01‐Mar‐22
    A2410 FINAL TESTING 7 01‐Mar‐22 08‐Mar‐22
          HDD WORK
    A2420 SETTING OUT FOR HDD 3 13‐Jan‐22 16‐Jan‐22
    A2430 WELDING OF HDPE PIPE 2 27‐Jan‐22 29‐Jan‐22
    A2440 HDD & HDPE PIPELAYING 2 31‐Jan‐22 02‐Feb‐22
    A2450 MANDRILL TEST FOR HDD 1 04‐Feb‐22 05‐Feb‐22
    A2460          NDM (AS REQUIRED) 7 18‐Feb‐22 25‐Feb‐22
    CHAMBER WORKS (20 NOS)
    A2460 EXCAVATION OF CHAMBER 90 03‐Dec‐21 03‐Mar‐22
    A2470 BLINDING & SCREED FOR CHAMBER WORK 90 05‐Dec‐21 05‐Mar‐22
    A2480 SHUTTERING & REBAR WORK FOR BASE 90 07‐Dec‐21 07‐Mar‐22
    A2490 CONCRETE CASTING FOR BASE 90 09‐Dec‐21 09‐Mar‐22
    A2500 SCAFFOLDING WORK FOR WALLS 90 11‐Dec‐21 11‐Mar‐22
    A2510 SHUTTERING & REBAR WORK FOR WALLS 90 13‐Dec‐21 13‐Mar‐22
    A2520 CONCRETE CASTING FOR WALL 90 15‐Dec‐21 15‐Mar‐22
    A2530 EXTERNAL WATERPROOFING OF CHAMBER 90 17‐Dec‐21 17‐Mar‐22
    A2540 INSTALLATION OF VALVE AND FITTINGS 90 19‐Dec‐21 19‐Mar‐22
    A2550 INSTALLATION OF COVER SLAB 90 21‐Dec‐21 21‐Mar‐22
    A2560 EXTERNAL PROTECTION & BACKFILLING 90 23‐Dec‐21 23‐Mar‐22
    SCADA WORKS
    A2570 HDPE PIPE FOR CABLE PULLING 90 03‐Dec‐21 03‐Mar‐22
    A2580 CABLE PULLING 10 03‐Mar‐22 13‐Mar‐22
    A2590 INSTALLATION OF PULL BOXES 30 03‐Dec‐21 02‐Jan‐22
    A2600 INSTALLATION OF RTU FOUNDATION 30 15‐Mar‐21 14‐Apr‐21
    A2610 INSTALLATION OF PANELS 7 15‐Mar‐21 22‐Mar‐21
    A2620 POWER AND SIGNAL CABLE TERMINATION 30 03‐Dec‐21 02‐Jan‐22
    A2630 PERMANENT POWER FOR RTU 30 03‐Dec‐21 02‐Jan‐22
    A2640 CONNECTION TO EXISTING NETWORK 7 23‐Mar‐22 30‐Mar‐22
    A2650 COMMISSIONING OF RTU BY DEWA 7 30‐Mar‐22 06‐Apr‐22
FLUSHING AND DISINFECTION
    A2650 FILLING OF WATER (FLUSHING) 7 23‐Mar‐22 30‐Mar‐22
    A2660 DOSING & SAMPLING OF WATER (CHLORINATION) 3 30‐Mar‐22 02‐Apr‐22
    A2670 APPROVAL OF SAMPLE (CHLORINATION) 3 02‐Apr‐22 05‐Apr‐22
    A2680 FLUSHING OF WATER & FILLING OF LINE FOR BACTERIAL TEST 2 05‐Apr‐22 07‐Apr‐22
    A2690 BACTERIAL TEST SAMPLE 1 07‐Apr‐22 08‐Apr‐22
    A2700 TEST RESULT 1 08‐Apr‐22 09‐Apr‐22
  SHUTDOWN
    A2710 SHUTDOWN WORK 7 09‐Apr‐22 16‐Apr‐22
  RELIABILITY RUN PERIOD
    A2720 RELIABILITY RUN PERIOD 60 16‐Apr‐22 15‐Jun‐22