NATIONAL WATER SUPPLY & DRAINAGE BOARD
POLGAHAWELA, POTHUHERA AND ALAWWA.
INTERGRATED WATER SUPPLY PROJECT
Tel 037 2243930/ 037 2243931 Fea 0372243931
Mabie 110 $0017 (001 284209 Femail ppp
[My No: PDVPPAIWSP/Desigw/2021/213, ovioro2t
‘The Project Diretor
[Mis Vatech Wabag Lid
Dear Sir,
gahawela, Pothulera and Alawwa Integrated Water Supply Project,
(Contract No: SP-NWP/POLGAHAWELA/W/DB/2011/01
Subject: Comments on Submision of RIO room at Denagamuva Reservoir (G2)~ Rev 2
Reference: WAB(SL/10PI04SG/PD/20216149 dated 20" September 2021
“This refers tothe above letter no 4
The submited drawing has not boon checked and singed by te chartered Engineer. Please comply with
clause 8.1.6.6 nf eonteset agreement volume L
However, please findoue comments on your above submission and incorporate in next submission.
“Menton the N-E coordinate on the structure to ensue the location
Incorporate the foundation dowelling det with his drawing too.
Mention the typeof backfilling material surrounding the strveture
Provide cleardetal of gap filling under the ground floor slab
Provide the guard wal ontop ofthe rot as other RIO room at Kandegedara and Boyagane,
Proposed asphalt road access ot clear inthe key plan ad detailed also isnot available
Provide sunshade For door and windows,
‘Opening at the ground floor need vo mentioned clearly with dimension.
Foundation detail is not clear. Provide clear details. ie, what is under PB 3 & 4 (400 height) &
‘whether haveany dowelling oF not
Project Dee
Polgahawela, Pothubera and Alawwa Integrated Water Supply Projet
‘No 301, Kuruegala Road, Bandawa Plgatawela10, Since this structure is situate onthe ground raft slab of Denagamuwa reservoir, confer the loud
‘ofthis structure was consider inthe aft slab design.
11. Provide sunshade & ledge beam reinforcement details.
Thanking you.
ofan
Bog G.M Thilakarathne
‘Project Director (PPAIWSP)
Pres Diver
Polgahawela,Pothbera and Alnww Iterated Water Supply Project
'No 301, Kuranyala Road, Bass, Plgshawela