Professional Documents
Culture Documents
Evaluation of Technical Losses On Electric Distribution Systems
Evaluation of Technical Losses On Electric Distribution Systems
1989
J. J. Grainger T. J. Kendrew
North Carolina State University, USA Electric Power Research Institute, USA
I
0.07 : for residential
FI,= 0.09 : small commercial (c400kW)
0.1 7 : large commercial
Service Losses
v Lg. Commercial
.......................
OH
-____
UG
--__
Since commercial customers are served directly from the wire size 5OOMCM 750MCM
transformer, losses on the secondary system were length 12.2111 12.2111
calculated for residential customers only. The difficulties loss factor FlS= 0.1 8
caused by the many different varieties of designs and
parameters were circumvented by the following direct The loss factors were calculated from independent load
approach: survey data. The coincidence factors used in the secondary
line calculations were also applied to the calculation of
energy and demand losses in the service drops.
the root-mean-square (RMS) load was found for each
major size of transformer using the formula
PISTRIBUTIO-FS: WMM4EY
RMS load = dx(load)2/no. of transformers (14)
The methodology described above permitted calculation of
to yield the following results (all in kVA): demand and energy losses in each segment of the
physically-existing distribution system with the following
Transformer RMS load RMS load results:
Size (overhead) (underground)
______-_____--__
--------------- ---------------
25 20.8 19.5
37 37.1 30.0
50 50.3 39.3
75 68.7 55.3
100 92.8 86.0
491
Energy Losses On the system tested distribution transformer no-load
Percent Percent demand losses exceeded load-variable demand losses
Segment of sales of calculated losses
___--_-__-_-- ___________ ____________________------- by a factor of three.
Substation:
No load
Load
::::} 0.66 17.1
The per-unit daily load profile of each day of the year
can be clustered with other similar profiles. A year can
be represented statistically by between four and six
typical days.
Primary:
The per-unit daily load profile shape of weekends was
3$ fdrs 0’70} 0.74 19.0 not unique and could be represented with statistical
l4&2$ 0.04 significance in losses analysis by one of the typical
wee k-days.
Distribution Transformer:
no-load
load
}:::A 2.14 55.1 In a manner similar to that used for the significant days,
certain substation transformers could be clustered by
considering the twelve monthly peak loadings.
Secondary: 0.1 3 3.4
In spite of considerable effort in modeling the system in
Services: extreme detail 13.22% of total distribution losses were
res. 0.085
sm. comm. 0.079
lg. comm. 0.046 i 0.21
-____------
3.88
5.4
_____--__
100
undetermined. This figure is thought to be a
combination of errors in modeling, elements not
calculated, measurement inaccuracies, typical input
data versus actual, or perhaps power theft.
Services: 0.23
Gf?p.eratio n
Log ...
-
Figure 1. Cascade connection of two components.
Substation Groups
r
1 I I I
-
Consumptlon kWh
493