AGENDA ALAT PENUNJANG

No Material Kebutuhan Vol Sat


1 Tool Box Penunjang 1 set
2 Pick Up Mobilitas 1 bh
3 Tenaga Kebutuhan 8 orng
4 E-Port Mobilitas 1
5 Salary 2 orang Pekerja 2 orang
6 Wearpack Safety 4 orang
7 Sepatu Safety Safety 4 orang

AGENDA KPLP
No Material Kebutuhan Vol Sat
1 Pompa Grundfos pemasangan 1 bh
Kabel MDP to SDP (NYY 4x16
2
mm) Tarikan 125 m
3 Kwh to MDP (NYY 4x16 mm) Tarikan 20 m
4 Kabel Jumper (NYY 4X16 mm) Tarikan 3 m
5 Sand Bag Dewatering 15 bh
6 Sewa Pompa Listrik Dewatering 1 bh
7
Chemical Pasang angkur 4 bh
sambungan
8
Skun 16 mm kabel 25 bh
sambungan
9
Sleeve Skun 16 mm kabel 25 bh
10 Sewa Forklift Mobilitas 1 bh
11 Box Panel 40x30x20 cm Power Utama 1 bh
12 MCCB 100 A Breaker power 1 bh
13 Pipa PVC 1,5'' safety Kabel 70 m
14 Shock pipa 1,5'' safety Kabel 10 bh
15 Elbow 1,5'' safety Kabel 8 bh
16 Pipa PVC 10'' Outlet Pompa 12 m
17 Elbow 10'' Outlet Pompa 2 bh
18 Klem pipa 1,5'' Safety Pipa 1 pack
19 Isolasi listrik Isolasi kabel 2 bh
20 Anchor M20x170 Dudukan ADC 4 bh
21 WLC Control Pompa 1 bh
22 Lem Pipa Pipa Baru 1 bh
23 Roofing Pipa Baru 1 pak
24 flange 12 inch Pipa Baru 1 bh
25 Mor Baut Pipa Baru 12 bh
26 Reducer 12 to 10 inch Pipa Baru 1 bh