Final Rate of Switchyard Work

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

VIKRAN ENGINEERING & EXIM PVT. LTD.

Name of the work: “Supply, Erection, Testing and Commissioning of (i) 220/11 KV Sub-Station at Yacharam under Kaleshwaram Lift Irrigation Scheme Nizamabad District
on Turnkey Basis”.

Final Rate Dt. 21082020

Sl.No. DESCRIPTION OF ITEM OF WORK Unit QUANTITY Unit Rate Amount

SWITCH YARD WORKS


Earthwork excavation in all types of soils (up to stone matrix)which can be excavated
with pick axe and crow bars and do not require blasting in all conditions such as dry, wet
21 and slushy etc. covering initial lead and lift etc and backfilling the foundations (after Cum 2500.00 82.00 2,05,000.00
laying foundations) with excavated earth complete as per the the directions of the
Engineer in charge for the finished item of work. .
Excavation in HDR, soft rock, F&F requiring blasting where ever necessary. The rate
includes labour charges, cost of blasting materials, tools and tackles, safety measures,
22 Cum 125.00 300.00 37,500.00
disposal of unuseful excavated material at all leads and lifts, complete for finished item
of work as per directions of the Engineer-in-charge.
Excavation in Hard rock (requiring blasting) The rate includes labour charges, cost of
blasting materials, tools and tackles, safety measures, disposal of unuseful excavted
23 Cum 375.00 450.00 1,68,750.00
material at all leads and lifts, complete for finished item of work as per directions of
the Engineer-in-charge
Excavation in Ordinary rock (HDR, soft rock ) (not requiring blastingThe rate includes
labour charges, cost of tools and tackles, disposing of unuseful excavated materail at
24 Cum 125.00 150.00 18,750.00
all leads and lifts, complete for finished item of work as per directions of the Engineer-in-
charge
Laying of Cement Concrete (1:4:8) mix using 40mm size HBG Machine crushed metal
for foundations including cost and conveyance of all materials at all leads and lifts,
25 Cum 117.00 2,900.00 3,39,300.00
ramming, consolidating, curing etc,complete. for finished item of work as per directions
of the Engineer-in-charge. - Cement will be supplied by M/s Vikran
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) (Fe
500/ 500D/550D) grade as per IS 1786-1979) of TISCO/ SAIL/ VSP/Jindal make, different
diameters for RCC works , including labour charges for straightening, cutting, bending to
required sizes and shapes, placing in position with cover blocks of approved materials
and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for
26 reinforcement work as per approved designs and drawings, including cost and -
conveyance of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and all
incidental, operational, labour charges such as cutting, bending, placing in position, tying
including sales and other taxes on all materials etc., complete for finished item of work
in all floors.( APSS No.126) - TMT Bars will be supplied by M/s Vikran
Upto 3.66m Height MT 31.00 5,500.00 1,70,500.00
RCC M- 20 Nominal mix (Cement 400 kgs ) using 20mm size graded machine crushed
hard granite metal (coarse aggregate) (20mm & 12mm (2:1)) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (screened
sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales &
27 other taxes on all materials including all operational, incidental and labour charges such -
as machine mixing, laying concrete, curing and centering, etc.,complete but excluding
cost of steel and its fabrication charges for finished item of work(Sand 0.45 cum and
Metal 0.90 cum) as directed by the Engineer in charge for finished item of work.-
Cement will be supplied by M/s Vikran
a Switch yard foundations, Cable Duct & Fire protection wall upto GL Cum 802.00 4,200.00 33,68,400.00
b Fire protection wall up to 3.66 mts height Cum 20.00 4,700.00 94,000.00
c Fire protection wall above 3.66 mts height Cum 10.00 5,000.00 50,000.00
PCC M- 20 Nominal mix (Cement 330 kgs ) using 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
28 Cum 5.00 4,200.00 21,000.00
etc., to site and including Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such as machine mixing, laying
concrete, curing and centering, etc., complete - Cement will be supplied by M/s Vikran
Brick Masonry in CM (1:6) with common burnt clay bricks of class as per Table-1 of
IS:1077-1992 Non-Modular or traditional size 23 x 11 x 7 cms of approved quality,
29 including cost & conveyance of all materials, labour charges, scaffolding leads, lifts and Cum 62.00 3,500.00 2,17,000.00
curing complete as per the directions of the Engineer in charge for the finished item of
work . - Cement will be supplied by M/s Vikran
Plastering with CM (1:5), 12 mm thick and finishing smooth to the required slope and
painting two coats of Janatha Cem including cost & conveyance of all materials, labour
31 charges, leads, lifts and curing including cost of Janatha Cem paint two coats, complete Sqm 650.00 76.00 49,400.00
as per the directions of the Engineer in charge for the finished item of work.- Cement
will be supplied by M/s Vikran
VIKRAN ENGINEERING & EXIM PVT. LTD.
Name of the work: “Supply, Erection, Testing and Commissioning of (i) 220/11 KV Sub-Station at Yacharam under Kaleshwaram Lift Irrigation Scheme Nizamabad District
on Turnkey Basis”.

Final Rate Dt. 21082020

Sl.No. DESCRIPTION OF ITEM OF WORK Unit QUANTITY Unit Rate Amount

Plastering with CM (1:5), 12 mm thick to the even wall surfaces including cost &
conveyance of all materials, labour charges, leads, lifts , scaffolding and curing
32 -
complete as per the directions of the Engineer in charge for the finished item of work.-
Cement will be supplied by M/s Vikran
a Fire protection wall Up to 3.66 mts height Sqm 325.00 66.00 21,450.00
b Fire protection wall above 3.66 mts height Sqm 325.00 72.00 23,400.00
Supply and Spreading of 20mm size Hard Broken Granite metal in switch yard (100mm
thick) providing suitable PCC guage block of size 100x100x100mm at 2m x2m intervals ,
33 Cum 600.00 1,100.00 6,60,000.00
cost & conveyance of all materials, labour charges, leads, lifts complete as per the
directions of the Engineer in charge for the finished item of work
Supply and spreading of crusher dust in the switch yard(100mm thick) area including
Suitable antiweed treatment after completion of final levelling and grading including
34 disposal of surplus earth and filling within switch yard area including cost of all materials, Cum 600.00 900.00 5,40,000.00
all leads and lifts, labour charges complete as per the directions of the Engineer in
charge for the finished item of work..
Supply and laying of 180 GSM LDPE sheet of approved make in the switch yard including
laying the sheet neatly in between layers of crusher dust without folds to avoid the
35 vegetation and weed growth, cutting and jointing the sheet properly including cost & Sqm 6000.00 10.00 60,000.00
conveyance of all materials, all leads , labour charges for laying complete as per the
directions of the Engineer in charge for the finished item of work..
White washing two coats with whiting / Suryacem of approved quality to give an even
shade after thoroughly brushing the surface to remove all dirt and remains of loose
36 Sqm 650.00 25.00 16,250.00
powdered materials including cost of all materials, labour charges and incidental such as
scaffolding, lift charges etc., complete for finished item of work
Supply and fixing of 110 lb rail pole conforming to Indian Railway specification and fixing
on Transformer plinth including the cost of all labour, materials, equipment fixing bolts,
base plates etc. but excluding the cost of excavation, concrete, reinforcement,
37 RM 12.00 1,900.00 22,800.00
shuttering and guide angles as per specification and approved drawings (top of rail shall
flush with top of concrete) complete as approved and directed by the Engineer in -
charge at site.- Supply of Rail Pole is in Sub-Contractor's scope
60,83,500.00
WATER SUPPLY ARRANGEMENT IN EARTH PITS
Supplying and fixing CPVC pipes of SDR 13.50 pipes Medium Grade as per IS 15778 of
approved make for water supply line to toilets including cost and conveyance of pipe,
40 specials such as elbows, Tees concealing same in walls and floors by cutting 25/ 20/
15mm dia to be included grooves, packing, finishing after laying pipe in position as per
the directions of the Engineer in charge for the finished item of work.
a 28.6 mm Outer dia Pipe RM 600.00 100.00 60,000.00
b 15.90 mm Outer dia Pipe RM 125.00 65.00 8,125.00
Providing and fixing in position at all levels of the buildings Bronze Gate (GM peet) Valve
(Tata/Zenith make)as per IS-778 class- 1, Indian make heavy type for water services with
41 -
hand wheel at all elevations for following sizes including jointing complete as per the
directions of the Engineer in charge for the finished item of work.
a 20mm dia Nominal Bore No 15.00 410.00 6,150.00

Supply & Fixing of 15 mm brass body CP finish bib tap of not less than 300 grams weight
screw type (full turn) with internal / external threaded connection conforming to IS 8931
42 No 105.00 119.00 12,495.00
including cost & conveyance of all materials, labour charges, leads, lifts complete as per
the directions of the Engineer in charge for the finished item of work .

Construction of Brick masonry chamber over the cully trap or peet valves & fitted with
304.8mm X 228.6mm size CI frame & Hinged cover as including cost & conveyance of all
43 No 15.00 250.00 3,750.00
materials, labour charges complete for finished item of work as per the directions of
the Engineer-in-charge - Cement will be supplied by M/s Vikran
90,520.00
Total Rs. 61,74,020.00

You might also like