Final Rate of Switchyard Work
Final Rate of Switchyard Work
Final Rate of Switchyard Work
Name of the work: “Supply, Erection, Testing and Commissioning of (i) 220/11 KV Sub-Station at Yacharam under Kaleshwaram Lift Irrigation Scheme Nizamabad District
on Turnkey Basis”.
Plastering with CM (1:5), 12 mm thick to the even wall surfaces including cost &
conveyance of all materials, labour charges, leads, lifts , scaffolding and curing
32 -
complete as per the directions of the Engineer in charge for the finished item of work.-
Cement will be supplied by M/s Vikran
a Fire protection wall Up to 3.66 mts height Sqm 325.00 66.00 21,450.00
b Fire protection wall above 3.66 mts height Sqm 325.00 72.00 23,400.00
Supply and Spreading of 20mm size Hard Broken Granite metal in switch yard (100mm
thick) providing suitable PCC guage block of size 100x100x100mm at 2m x2m intervals ,
33 Cum 600.00 1,100.00 6,60,000.00
cost & conveyance of all materials, labour charges, leads, lifts complete as per the
directions of the Engineer in charge for the finished item of work
Supply and spreading of crusher dust in the switch yard(100mm thick) area including
Suitable antiweed treatment after completion of final levelling and grading including
34 disposal of surplus earth and filling within switch yard area including cost of all materials, Cum 600.00 900.00 5,40,000.00
all leads and lifts, labour charges complete as per the directions of the Engineer in
charge for the finished item of work..
Supply and laying of 180 GSM LDPE sheet of approved make in the switch yard including
laying the sheet neatly in between layers of crusher dust without folds to avoid the
35 vegetation and weed growth, cutting and jointing the sheet properly including cost & Sqm 6000.00 10.00 60,000.00
conveyance of all materials, all leads , labour charges for laying complete as per the
directions of the Engineer in charge for the finished item of work..
White washing two coats with whiting / Suryacem of approved quality to give an even
shade after thoroughly brushing the surface to remove all dirt and remains of loose
36 Sqm 650.00 25.00 16,250.00
powdered materials including cost of all materials, labour charges and incidental such as
scaffolding, lift charges etc., complete for finished item of work
Supply and fixing of 110 lb rail pole conforming to Indian Railway specification and fixing
on Transformer plinth including the cost of all labour, materials, equipment fixing bolts,
base plates etc. but excluding the cost of excavation, concrete, reinforcement,
37 RM 12.00 1,900.00 22,800.00
shuttering and guide angles as per specification and approved drawings (top of rail shall
flush with top of concrete) complete as approved and directed by the Engineer in -
charge at site.- Supply of Rail Pole is in Sub-Contractor's scope
60,83,500.00
WATER SUPPLY ARRANGEMENT IN EARTH PITS
Supplying and fixing CPVC pipes of SDR 13.50 pipes Medium Grade as per IS 15778 of
approved make for water supply line to toilets including cost and conveyance of pipe,
40 specials such as elbows, Tees concealing same in walls and floors by cutting 25/ 20/
15mm dia to be included grooves, packing, finishing after laying pipe in position as per
the directions of the Engineer in charge for the finished item of work.
a 28.6 mm Outer dia Pipe RM 600.00 100.00 60,000.00
b 15.90 mm Outer dia Pipe RM 125.00 65.00 8,125.00
Providing and fixing in position at all levels of the buildings Bronze Gate (GM peet) Valve
(Tata/Zenith make)as per IS-778 class- 1, Indian make heavy type for water services with
41 -
hand wheel at all elevations for following sizes including jointing complete as per the
directions of the Engineer in charge for the finished item of work.
a 20mm dia Nominal Bore No 15.00 410.00 6,150.00
Supply & Fixing of 15 mm brass body CP finish bib tap of not less than 300 grams weight
screw type (full turn) with internal / external threaded connection conforming to IS 8931
42 No 105.00 119.00 12,495.00
including cost & conveyance of all materials, labour charges, leads, lifts complete as per
the directions of the Engineer in charge for the finished item of work .
Construction of Brick masonry chamber over the cully trap or peet valves & fitted with
304.8mm X 228.6mm size CI frame & Hinged cover as including cost & conveyance of all
43 No 15.00 250.00 3,750.00
materials, labour charges complete for finished item of work as per the directions of
the Engineer-in-charge - Cement will be supplied by M/s Vikran
90,520.00
Total Rs. 61,74,020.00