Professional Documents
Culture Documents
Methodology For Erection of Precast I-Girders Aakar Abhinav Consultants Pvt. LTD
Methodology For Erection of Precast I-Girders Aakar Abhinav Consultants Pvt. LTD
Name Of Project FOUR-LANNING OF RAJKOT-MORBI ROAD SH-24
CONTENTS
1 Scope 2
2 Documentati 2
on
3 Working Method 3
Page 1 of 4
Rev Date Prepared By Reviewed By Approved by
SI
Description
No.
Transportation & Erection of Pre-Cast
1 Scope
Girders and Deck Slab over it
2 Documentation RFI
Manpower Required :
Section Engineer
Site Supervisor
Operators
Workmen-Rigger, Khalasi, Helpers, etc.
Equipment required :
Safety Precautions :
Page 2 of 4
Work Procedure :
The casting yard for the girder shall be properly leveled and compacted.
The base of girder shall be prepared with leveled PCC M-15 grade of concrete.
Pouring M-45 grade of concrete as per detailed design drawing shall be done with
Cocrete pump.
Pedestal of M35 grade will be casted with plan dimensions as per detailed design
drawing.
Elastomeric Bearing and Elastomeric Pad shall be placed over pedestal as per
Girder will be shifted to the site of erection from the precast yard by Trailor.
At site, it will be lifted with the help of 2 Nos. 100MT Cranes and placed on the
After placing the girder, it is to be supported from both sides by using structural
All the girders are to be erected and should be connected at the top with each
End diaphragm & intermediate diaphragm will be casted as per the drawing.
Bracket will be fixed in the cantilever portion of slab and shuttering will be laid and
Page 3 of 4
Bridge shall be opened to traffic after connecting to the approaches.
Page 4 of 4