Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

Page 1 of 5

PUMP INSTALLATION AND OPERATIONS

Considerable attention must be paid to proper pump installation to ensure trouble


free operation.

The following factors must be taken into consideration: 

INSTALLATION OF PUMP:

  The pumps should be accessible for inspection and maintenance and


should include valves on both suction and discharge lines. they should be
removed from areas that are subjected to flooding, water leakage, and
corrosion; they should be located as close as possible to the source of supply
and headroom should be provided for lifting the rotor and casing. If
the pumps must be located in areas of high humidity, the motors must be
designed for this purpose. 
  The pump is provided with a steel baseplate to which the pump and motor
are attached. This baseplate must be bolted securely to the foundation. In
most cases, larger bases are grouted into place, but this may not be required
on smaller units if the foundation is rigid and the baseplate can be bolted
down securely. 
  The piping should run to a pump as directly as possible, avoiding sharp
bends. Entrance to the pump should be provided with long-radius ells or
bends to reduce inlet friction to a minimum, and the suction piping should
run straight into the pump. 
Page 2 of 5

  Piping must be supported to take the strain from the pump and provide
for expansion and contraction to avoid pump misalignment. Expansion
joints or loops should be used when hot liquids are being handled. 

  The suction piping should be large enough to minimize the friction losses.
Short suction lines are recommended but are not always possible. In order to
avoid problems experienced with long intake pipes and high suction lifts, an
individual suction line should be provided for each pump. If this is
impractical, the suction-header size should be approximately 50 percent
larger than the pump connection and should be reduced at the pump flange.
The use of tees or right-angle fittings should be avoided, and long radius ells
or bends should be used instead. 
  The suction header should be sloped upward from the reservoir to the
pump, and high spots in the header, where air might collect, should be
avoided. The suction end should be flared, and the suction inlet should be
well below the low-water level to eliminate the possibility of air
entrainment. The suction should not be located close to the point of makeup
or returning water, since eddy currents may interfere with pump operation.
When supplying two or more pumps from a long intake header, a tapering
header with Y branches to the pump suction should be used. For pumps
operating under high suction lift, stuffing boxes should be sealed, using
water taken from the discharge header or from a separate source of supply. 
  The suction lift should be limited to 10 to 15 ft., since only clean cold
water can be raised this amount without experiencing operating
difficulties. For hot water, it is necessary to bring the water to the pump
under a positive head. The velocity should be low, and a suction head of 10
Page 3 of 5

to 20 ft. is desirable. When starting up new boiler-feed water or high-


temperature-water circulating pumps, a strainer is frequently installed to
prevent foreign material from getting into the pumps (and lines) or clogging
the suction intake. 
  The strainers can be removed when the system is cleaned. All strainers
should be inspected periodically. 
  A pump that has its suction line below the pump centerline requires
priming that is, the air must be evacuated from the pump suction before
water will enter the pump and fill the piping and casing. Priming may be
accomplished by filling the suction piping with water from some other
source. When water is ejected in a steady stream, it may be assumed that the
pump is full of water, and the pump may be started, after which the
discharge valve may be opened slowly. If a vacuum pump is used, it should
preferably be a wet vacuum pump, since water may damage a dry vacuum
pump. 
  To ensure successful operation of a pump, it should be set on a foundation
that is substantial and rigid enough to permit the pump to absorb vibration.
Good foundations are usually made of concrete. Before the concrete is
poured, the foundation bolts are secured. 
  To prevent the bed plate from springing out of line, the pump must be
aligned carefully. Pumps that come already mounted on a bedplate should be
leveled before they are placed in operation. Pumps that are to be set on a
rough foundation should be set approximately in location and leveled with
shims before the bedplate is grouted in position. Commercial grouting is
readily available with recommended curing periods. Next, check suction and
discharge flanges to determine if they are level. 
Page 4 of 5

  After suction and discharge flanges have been bolted up, the alignment
should be checked again. If connecting of piping has caused misalignment,
repeat the procedure followed previously. 
  Check pump and motor rotation and insert bolts in flanges and connect
up. A short time after the pump has been in operation, the alignment should
be checked again. After it is certain that all is satisfactory, the unit can be
doweled. The doweling is done with tapered pins usually provided with the
pump. Dowel pins are located in the feet of the pump and driver, as well as
in the bedplate. 
OPERATION OF PUMPS:

  Before operation, after all piping has been connected and after the baseplate
has been bolted in place, the pump and motor should be aligned with a dial
indicator to ensure that operation is free from vibration. Any misalignment
will cause vibration that could lead to bearing and mechanical seal failure. 
  When the alignment is being checked, and with the coupling
disconnected, the direction of rotation should be checked. This check also
can be made with the coupling connected. however, the pump must be filled
with liquid to prevent running the packing or seal dry. A mechanical seal can
fail in a short period of time if it is run dry. 
  Before placing the pump in operation, make certain that bearings are
lubricated. Rotate the motor by hand to make certain everything is free.
Prime the pump and fill the pump full of liquid, and with suction valve open
and discharge valve closed, start the pump, noting suction and discharge
pressures. (All pumps should be fitted with pressure gauges on both the
suction and discharge sides.) After running the pump this way for a minute
Page 5 of 5

or two with the air vent open, close vent valves and open the discharge valve
slowly. 
  Observe gauges closely, and if anything unusual occurs or pressures seem
unusual, stop the pump and check it thoroughly. 
  Start and stop the pump several times and observe performance. If all
looks satisfactory, continue to operate for 1h to 1 hour, meanwhile observing
bearing temperatures and watching gauges, lubrication, and general actions
of the pump and motor for overheating. Then shut the pump down, recheck
alignment, tighten all bolts, and give the entire installation a careful check.
Place the pump again in operation. 

 observe the packing gland, gland seals, lubrication, and overheating.


Never run a pump for an extended period of time with the discharge
valve closed unless the vents are open or the pump is equipped with a
bypass to permit some water to circulate through the pump at all times. 

You might also like