Question 1 4 area pendukung dalam knlowledge areas, yaitu?
 Correct

Mark 2.50 out Select one:


 of 2.50
a. scope, communication, risk, and procurement

b. human resources, communication, risk, and cost



c. human resources, communication, risk, and time
 d. human resources, communication, risk, and
procurement 

Good work

The correct answer is: human resources, communication, risk,


and procurement

Question 2 4 Area utama dalam knowlegde areas, yaitu?


Correct

Mark 2.50 out Select one:


of 2.50
a. time, cost, human and tools

b. scope, time, cost, and tools

c. scope, time, cost, and human

d. scope, time, cost, quality 

Good work

The correct answer is: scope, time, cost, quality

Question 3 Alat yang digunakan untuk menggambarkan kebutuhan waktu,


Correct kecuali?
Mark 2.50 out
of 2.50 Select one:
a. Network diagrams

b. Project Charter 

c. Gantt charts

d. Critical path analysis

Good work

The correct answer is: Project Charter


Question 4 Apa sajakah 3 hal yang penting untuk dikelola, agar proyek
Correct dapat berhasil?
Mark 2.50 out
of 2.50 Select one:

a. Scope, Tools, Cost

 b. Scope, Time, Tools

c. Scope, Time, Cost 



d. Time, Tools, Cost

Good work

The correct answer is: Scope, Time, Cost

 Question 5 Apakah kepanjangan dari WBS?


Correct
 Mark 2.50 out Select one:
of 2.50
a. Work Bounded Structure

b. Word Breakdown Structure

 c. Work Breakdown Structure 

d. Work Breakdown Service


Good work
The correct answer is: Work Breakdown Structure

Question 6 Apakah sifat dari proyek?


Correct

Mark 2.50 out Select one:


of 2.50
a. Permanen

b. tidak langsung

c. langsung

d. Sementara 

Good work

The correct answer is: Sementara


Question 7
Correct

Mark 2.50 out


of 2.50


Gambar diatas merupakan contoh alat dalam manajemen
 proyek berupa?

 Select one:
a. Gantt Chart 
 b. Network diagram

c. Quality metric

d. Grafik

Good work

The correct answer is: Gantt Chart

Question 8

Correct

Mark 2.50 out


of 2.50

Gambar diatas merupakan?

Select one:
a. Network Diagram 

b. Grafik

c. Checklist

d. Gantt Chart

Good work

The correct answer is: Network Diagram


Question 9 Hal-hal yang harus dimiliki seorang manajer proyek, kecuali?
Correct

Mark 2.50 out Select one:


of 2.50
 a. Mampu membuat keputusan

b. Menimbulkan Konflik 
 c. Memberikan Kepercayaan

 d. Menjadi penengar yang baik


Good work
 The correct answer is: Menimbulkan Konflik


Question 10 Kemampuan yang dimiliki oleh manajer proyek, antara lain,
 Correct kecuali?
Mark 2.50 out
 of 2.50 Select one:
a. Menciptakan Konflik 

b. Mampu Beradaptasi

 c. Kemampuan Memimpin

d. Mampu Mengorganisasikan tim


Good work
The correct answer is: Menciptakan Konflik

Question 11 Manajemen risiko, manajemen harapan, kepemimpinan,


Correct keterampilan orang, dan keterampilan perencanaan adalah
Mark 2.50 out kemampuan yang dimiliki manajer proyek dalam?
of 2.50

Select one:
a. Large projects

b. High uncertainty projects 

c. Low uncertainty projects

d. Very novel projects

Good work

The correct answer is: High uncertainty projects

Question 12 Manakah yang bukan termasuk keuntungan dari manajemen


Correct proyek?
Mark 2.50 out
of 2.50 Select one:
a. Meningkatkan Kualitas

b. Meningkatkan Produktivitas

c. Meningkatkan kerjasama

d. Memperbanyak biaya 

Good work

The correct answer is: Memperbanyak biaya


Question 13 Orang yang memainkan peran penting dalam
Correct mengorganisasikan proyek dan menentukan keberhasilan
Mark 2.50 out proyek dalah?
of 2.50

Select one:
a. Sponsor

b. Manajer Proyek 
 c. Supplier

d. Team Proyek


Good work

 The correct answer is: Manajer Proyek


Question 14 Orang yang membantu organisasi mereka membuat
 Correct keputusan investasi yang bijak dengan membantu memilih
Mark 2.50 out dan menganalisis proyek dari perspektif strategis adalah?
 of 2.50

Select one:
 a. Support Staff

b. Sponsor Managers

c. Opponent of Project

d. Portfolio Managers 

Good work

The correct answer is: Portfolio Managers

Question 15 Orang yang memberikan arahan bagi manajer proyek dan


Correct yang memimpin proyek dalam program adalah?
Mark 2.50 out
of 2.50 Select one:
a. Manajer Proyek

b. Supplier

c. Manajer Program 

d. Sponsor

Good work

The correct answer is: Manajer Program

Question 16 Penerapan pengetahuan, keterampilan, alat dan teknik untuk


Correct kegiatan proyek untuk memenuhi persyaratan proyek disebut?
Mark 2.50 out
of 2.50 Select one:
a. Manajemen Proyek 

b. Manajemen Program

c. Manajemen Teamwork

d. Manajemen Sumberdaya

Good work

The correct answer is: Manajemen Proyek


Question 17 Project Budget, Net present value, project portfolio
Correct management, return on invensment merupakan contoh alat
Mark 2.50 out atau teknik yang digunakan dalam area?
of 2.50

Select one:
a. Manajemen Waktu

b. Manajemen Biaya 
 c. Manajemen Ruang Lingkup

d. Manajemen Sumber Daya



Good work

 The correct answer is: Manajemen Biaya


Question 18 Quality metris, Checklists, Fishbone Diagram, Maturity Model
 Correct merupakan alat yang digunakan dalam area?
Mark 2.50 out
 of 2.50 Select one:
a. Manajemen Waktu
 b. Manajemen Sumber Daya

 c. Manajemen Biaya

d. Manajemen Kualitas 

Good work

The correct answer is: Manajemen Kualitas

Question 19 Sekelompok proyek terkait dikelola secara terkoordinasi untuk


Correct memperoleh manfaat dan kontrol yang tidak tersedia dari
Mark 2.50 out mengelolanya secara individual disebut
of 2.50

Select one:
a. Proyek

b. Portopolio

c. Software

d. Program 

Good work

The correct answer is: Program

Question 20 Upaya sementara yang dilakukan untuk menciptakan produk,


Correct layanan, atau hasil yang unik disebut sebagai?
Mark 2.50 out
of 2.50 Select one:
a. Proyek 

b. Teknik

c. Tools

d. Program

Good work

The correct answer is: Proyek


Question 21 Dalam Hubungan knowlegde area dan Kelompok Proses,
Correct tahapan perencanaan yang terdiri dari pendefinisian aktfitas,
Mark 2.50 out pengurutan aktifitas, menyusun perkiraan pelaksanaan aktfitas
of 2.50 dan membuat jadwal proyek, masuk ke dalam area?

Select one:

a. Ruang Lingkup

 b. Waktu 

c. Kualitas

d. Biaya


Good work

The correct answer is: Waktu

 Question 22 Dokumen high level yang menyatakan dan menjelaskan


Correct adanya sebuah proyek yang berisi informasi penting yang
 Mark 2.50 out mencakup penjelasan ringkas dari sebuah proyek yang akan
of 2.50 dijalankan adalah:

Select one:
 a. Project Management Plan

b. Project Charter 

c. Work Breakdown Structure

d. Schedule

Good work

The correct answer is: Project Charter

Question 23 Empat sumber utama perubahan dalam proyek, kecuali:


Correct

Mark 2.50 out Select one:


of 2.50
a. Teknis/Teknologi

b. Biaya 

c. Lingkungan/organisasi

d. Pengguna Akhir

Good work

The correct answer is: Biaya


Question 24 Kelompok proses awal/tahapan inisiasi terdiri dari beberapa
Correct hal, kecuali:
Mark 2.50 out
of 2.50 Select one:

a. Mengurutkan pekerjaan dan membuat jadwal 

 b. Mengalokasikan dana dan sumber daya

c. Menugaskan Manajer Proyek



d. Menentukan proyek baru atau baru fase proyek yang
ada


Good work

 The correct answer is: Mengurutkan pekerjaan dan membuat


jadwal

 Question 25 Kelompok Proses Manajemen Proyek mencakup, kecuali:


Correct

 Mark 2.50 out Select one:


of 2.50
a. Pemeliharaan 
 b. Pengendalian

 c. Perencanaan

d. Pelaksanaan

Good work

The correct answer is: Pemeliharaan

Question 26 Kelompok proses/tahapan perencanaan melibatkan hal-hal


Correct dibawah ini, kecuali:
Mark 2.50 out
of 2.50 Select one:
a. Menentukan produk yang akan diproduksi dan
pekerjaan yang dibutuhkan

b. Menentukan ruang lingkup proyek

c. Mengurutkan pekerjaan dan membuat jadwal

d. Menentukan tujuan, hasil, dan kriteria keberhasilan


proyek 

Good work

The correct answer is: Menentukan tujuan, hasil, dan kriteria


keberhasilan proyek
Question 27 Keluaran/target dari proses/tahapan eksekusi adalah, kecuali:
Correct

Mark 2.50 out Select one:


of 2.50
 a. Resolusi konflik dan pemecahan masalah

b. Melakukan negosiasi dan memiliki pengaruh untuk


 memastikan staf yang tepat ditugaskan

c. Membuat Anggaran dan Penjadwalan 



d. Membangun motivasi dan bimbingan untuk
memastikan kinerja tim


Good work

 The correct answer is: Membuat Anggaran dan Penjadwalan


Question 28 Output utama dari proses/tahapan penutupan proyek, kecuali:
 Correct

Mark 2.50 out Select one:


 of 2.50
a. Produk/hasil kerja akhir

b. Kalender sumber daya



c. Perubahan Permintaan 
 d. Sertifikat Penyelesaian/Laporan

Good work

The correct answer is: Perubahan Permintaan

Question 29 Proses yang memungkinkan manajer proyek untuk


Correct memastikan bahwa interaksi dan kompetensi dalam tim sesuai
Mark 2.50 out dengan tingkat kinerja yang disyaratkan, merupakan definisi :
of 2.50

Select one:
a. Pengembangan Tim Proyek 

b. Pengelolaan Tim Proyek

c. Mengakuisisi Tim Proyek

d. Pengelolaan Harapan Stakeholder

Good work

The correct answer is: Pengembangan Tim Proyek

Question 30 Proses-proses untuk melacak, meninjau, dan mengatur


Correct kemajuan dan kinerja proyek; mengidentifikasi bidang-bidang
Mark 2.50 out yang memerlukan perubahan rencana; dan memulai
of 2.50 perubahan yang sesuai, merupakan definisi dari tahapan:

Select one:
a. Tahapan Eksekusi

b. Tahapan Inisiasi

c. Tahapan Perencanaan

d. Tahapan Monitoring dan Controling 

Good work

The correct answer is: Tahapan Monitoring dan Controling


Question 31 Proses-proses untuk menghentikan secara formal semua
Correct kegiatan proyek atau fase proyek, dan transfer produk yang
Mark 2.50 out telah selesai kepada orang lain atau untuk menutup proyek
of 2.50 yang dibatalkan merupakan defisini:

Select one:

a. Tahapan Perencanaan

 b. Tahapan Inisiasi

c. Tahapan Penutupan 

d. Tahapan Eksekusi


Good work

The correct answer is: Tahapan Penutupan

 Question 32 Proses/tahapan untuk menentukan proyek baru atau fase baru


Correct dari proyek yang ada dengan memperoleh otorisasi untuk
 Mark 2.50 out memulai proyek atau fase tersebut, disebut:
of 2.50

 Select one:
a. Tahapan Perencanaan
 b. Tahapan Inisiasi 

c. Tahapan Penutupan

d. Tahapan Pengendalian

Good work

The correct answer is: Tahapan Inisiasi

Question 33 Suatu metode pengorganisasian proyek menjadi struktur


Correct pelaporan hierarakis, digunakan untuk memecahkan tiap
Mark 2.50 out proses pekerjaan menjadi lebih detail disebut:
of 2.50

Select one:
a. Work Breakdown Structure 

b. Project Management Plan

c. Schedule Document

d. Project Charter

Good work

The correct answer is: Work Breakdown Structure


Question 34 Terdiri dari proses-proses yang dilakukan untuk membangun
Correct ruang lingkup total upaya, menentukan dan memperbaiki
Mark 2.50 out tujuan, dan mengembangkan tindakan yang diperlukan untuk
of 2.50 mencapai tujuan merupakan pemahaman dari:

Select one:

a. Tahapan Perencanaan 

 b. Tahapan Monitoring

c. Tahapan Inisiasi

d. Tahapan Eksekusi


Good work

The correct answer is: Tahapan Perencanaan

 Question 35 Terdiri dari proses-proses yang dilakukan untuk menyelesaikan


Correct pekerjaan yang didefinisikan dalam rencana manajemen
 Mark 2.50 out proyek untuk memenuhi spesifikasi proyek, merupakan
of 2.50 pengertian dari:

Select one:
 a. Tahapan Perencanaan

b. Tahapan Eksekusi 

c. Tahapan Monitoring

d. Tahapan Inisiasi

Good work

The correct answer is: Tahapan Eksekusi

Question 36 Yang bukan aktifitas utama dalam proses penutupan proyek


Correct adalah:
Mark 2.50 out
of 2.50 Select one:
a. Mengontrol perubahan proyek dan dokumen proyek 

b. Finalisasi pengadaan

c. Melaporkan kinerja tim dan pelajaran yang didapat

d. Menyimpan atau mengarsipkan informasi

Good work

The correct answer is: Mengontrol perubahan proyek dan


dokumen proyek
Question 37 Yang bukan keluaran dari tahapan monitoring adalah:
Correct

Mark 2.50 out Select one:


of 2.50
 a. Laporan kemajuan dan status

b. Jadwal 
 c. Rencana pembaruan

 d. Produk/hasil kerja


Good work
 The correct answer is: Jadwal


Question 38 Yang dibutuhkan dalam sebuat Tim proyek adalah, kecuali:
 Correct

Mark 2.50 out Select one:


 of 2.50
a. Keterbaruan

b. Ketepatan

c. Kejujuran
 d. Subjektifitas 


Good work

The correct answer is: Subjektifitas

Question 39 Yang termasuk dalam proses/tahapan eksekusi, kecuali:


Correct

Mark 2.50 out Select one:


of 2.50
a. Mengelola Harapan Stakeholder

b. Mengarahkan dan Mengelola Eksekusi Proyek

c. Membuat Work Breakdown Structure 

d. Melakukan Pengadaan

Good work

The correct answer is: Membuat Work Breakdown Structure

Question 40 Yang termasuk dalam tugas inisiasi oleh senior manajer,


Correct kecuali:
Mark 2.50 out
of 2.50 Select one:
a. Memilih manajer proyek

b. Mengidentifikasi sponsor proyek

c. Menentukan ruang lingkup, waktu, dan kendala biaya


untuk proyek

d. Membuat penjadwalan proyek 

Good work

The correct answer is: Membuat penjadwalan proyek