Professional Documents
Culture Documents
BOM - Abutazil Residence
BOM - Abutazil Residence
BOM - Abutazil Residence
LOCATION :
OWNER :
SUBJECT : BILL OF MATERIALS
DATE : JULY 3, 2021
Item # DESCRIPTION
A GENERAL REQUIREMENTS:
a Mobilization/Demobilization
b Demolition
c Temporary facilities
d Permits and Licenses (Fees by Owner,Legworks by
Contractor)
e As-built plans
f Overhead and Supervision
SUB-TOTAL
II RE-BARS:
2.1 Column footing 2.47 1.58 0.62 1.5 1.5 0.35 6 10
16mm Ø - Round Bar
2.2 Footing Tie beam 2.47 1.58 0.62 1
16mm Ø - Round Bar 48.0902 5 1
10mm Ø - Round Bar 48.0902 288.541 1
2.3 Columns 2.47 1.58 0.62 C1 7.5 6 10 1
16mm Ø - Round Bar
10mm Ø - Round Bar C1 0.25 0.4 75 1 500
2.4 Beams 2.47 1.58 0.62
16mm Ø - Round Bar B1 95.4167 5 1 1
10mm Ø - Round Bar B1 0.25 0.4 95.4167 477.084 1 1
2.5 Wall footing 1.58 0.62 0.4
III FORMWORKS:
3.1 Staging & Scaffoldings
2x2 Plank Woods (Cocolumber)
#4 Common Wire Nails
3.2 Footing Tie beam 1
Lumber
Plywood
#2 1/2 Common Wire Nails
#1 Finishing Nails
3.3 Columns 1
Lumber
Plywood
#2 1/2 Common Wire Nails
#1 Finishing Nails
3.4 Beams 1
Lumber
Plywood
#2 1/2 Common Wire Nails
#1 Finishing Nails
SUB-TOTAL
V MASONRY WORKS:
5.1 6" CHB Wall 82.7226 3 1
Cement 34.4677 1 1
Screened Sand
5.2 4" CHB Wall 33.6379 3 1
Cement
Screened Sand
5.3 Plain cement plaster
2 faced plastering
Cement
Screened Sand
SUB-TOTAL
VI PLUMBING WORKS:
6.1 Water line
19mm diameter PPR pipe
12mm diameter PPR Pipe
6.2 Sewer line & Drainage line
100mm diameter PVC pipe
75mm diameter PVC pipe
Catch basins
Septic tank
6.3 Fixtures:
Water closet
Lavatory
Sink
Shower
Water meter
Clean out
Floor drain
Faucet
Fittings & consumables
SUB-TOTAL
SUB-TOTAL
IX FINISHING WORKS:
9.1 60 x 60cm Ceramic Tiles
40 x 40cm Ceramic Tiles
30 x 30cm Ceramic Tiles
9.2 Gypsum Board Ceiling
9mm thk fiber cement board board on
19mmx50mm Double Furring spaced @0.60 m o.c.
b.w. and carrying channel
12mm thk fiber cement board board on
19mmx50mm Double Furring spaced @0.60 m o.c.
b.w. and carrying channel
9.3 Semi-gloss latex paint
9.4 QDE paint on ceiling
9.5 Consumables
SUB-TOTAL
X ROOF FRAME:
10.1 Base plate
10.2 1/4 x 2" x 2" Double Angle bar
10.3 1/4 x 1 1/2" x 1 1/2" Angle bar
10.4 2" x 4" C - Purlins
10.5 Consumables (welding rod etc.)
SUB-TOTAL
XI ROOF SHEETS:
11.1 Pre-painted G.I. long span roof
11.2 G.I. gutter
11.3 Spandrel Ceiling
11.4 Ridge roll
11.5 Insulation
11.6 Flashings
11.7 Consumables
SUB-TOTAL
84.81756 -
55.4714 -
-
1548.6 1,548.60 kgs 90.00 5.00 139,374.00 7,743.00 147,117.00
0 -
268 536.00 kgs 90.00 5.00 48,240.00 2,680.00 50,920.00
-
-
1.00 lot 6,000.00 - 6,000.00 - 6,000.00
-
-
-
- 618,803.68 37,370.40 656,174.08
-
-
224.40 Bd.ft. 48.00 8.00 10,771.20 1,795.20 12,566.40
43.00 pcs -
31.00 kgs -
48.0902 48.09 m2 285.00 180.00 13,705.71 8,656.24 22,361.94
133.00 pcs
19.00 Sheets
4.63 Kgs -
1.80 Kgs -
47.52 47.52 m2 285.00 180.00 13,543.20 8,553.60 22,096.80
134.00 pcs
18.00 Sheets
4.10 Kgs -
1.70 Kgs -
142.56 142.56 m2 285.00 200.00 40,629.60 28,512.00 69,141.60
378.00 pcs
54.00 Sheets
12.30 Kgs -
5.10 Kgs -
- 78,649.71 47,517.04 126,166.74
-
-
7.875 10.58 m3 3,000.00 650.00 31,725.00 6,873.75 38,598.75
2.7 71.00 bag - 650.00
4.00 m3
7.90 m3
3.847216 3.85 m3 3,000.00 650.00 11,541.65 2,500.69 14,042.34
0 35.00 bag - 650.00
2.00 m3 - 650.00
3.90 m3 - 650.00
7.5 11.10 m3 3,000.00 650.00 33,300.00 7,215.00 40,515.00
0 101.00 bag - 650.00
3.6 5.60 m3 - 650.00
0 11.10 m3 - 650.00
13.95 m3 3,000.00 650.00 41,837.47 9,064.79 50,902.26
9.54167 127.00 bag - 650.00
3.78003375 7.10 m3 - 650.00
0.62412 14.10 m3 - 650.00
3.5788 3.58 m3 3,000.00 650.00 10,736.40 2,326.22 13,062.62
33.00 bag
1.78 m3 - 650.00
3.60 m3 - 650.00
0 15.60 m3 3,000.00 650.00 46,800.00 10,140.00 56,940.00
117.00 bag
7.80 m3
15.60 m3 - 650.00
0 7.80 m3 3,000.00 650.00 23,400.00 5,070.00 28,470.00
59.00 bag
3.90 m3
7.80 m3
2.62 m3 3,000.00 650.00 7,860.00 1,703.00 9,563.00
24.00 bag
1.40 m3
2.70 m3
207,200.52 44,893.45 252,093.97
76.00 bags
4.30 m3
460,259.04 138,077.71 598,336.75
-
- 150,000.00 52,500.00 202,500.00
-
-
90.00 m2 750.00 180.00 67,500.00 16,200.00 83,700.00
15.00 m2 300.00 180.00 4,500.00 2,700.00 7,200.00
10.00 m2 240.00 180.00 2,400.00 1,800.00 4,200.00
-
80.00 m2 450.00 100.00 36,000.00 8,000.00 44,000.00
A GENERAL REQUIREMENTS:
a Mobilization/Demobilization
b Demolition
c Temporary facilities
d Permits and Licenses (Fees by Owner,Legworks by
Contractor)
e As-built plans
f Overhead and Supervision
SUB-TOTAL
II RE-BARS:
2.1 Column footing 2.47 1.58 0.62 1.5 1.5 0.35 6 10
16mm Ø - Round Bar
2.2 Footing Tie beam 2.47 1.58 0.62 1
16mm Ø - Round Bar 48.0902 5 1
10mm Ø - Round Bar 48.0902 288.541 1
2.3 Columns 2.47 1.58 0.62 C1 7.5 6 10 1
16mm Ø - Round Bar
10mm Ø - Round Bar C1 0.25 0.4 75 1 500
2.4 Beams 2.47 1.58 0.62
16mm Ø - Round Bar B1 95.4167 5 1 1
10mm Ø - Round Bar B1 0.25 0.4 95.4167 477.084 1 1
2.5 Wall footing 1.58 0.62 0.4
III FORMWORKS:
3.1 Staging & Scaffoldings
2x2 Plank Woods (Cocolumber)
#4 Common Wire Nails
3.2 Footing Tie beam 1
Lumber
Plywood
#2 1/2 Common Wire Nails
#1 Finishing Nails
3.3 Columns 1
Lumber
Plywood
#2 1/2 Common Wire Nails
#1 Finishing Nails
3.4 Beams 1
Lumber
Plywood
#2 1/2 Common Wire Nails
#1 Finishing Nails
SUB-TOTAL
V MASONRY WORKS:
5.1 6" CHB Wall 82.7226 3 1
Cement 34.4677 1 1
Screened Sand
5.2 4" CHB Wall 33.6379 3 1
Cement
Screened Sand
5.3 Plain cement plaster
2 faced plastering
Cement
Screened Sand
SUB-TOTAL
VI PLUMBING WORKS:
6.1 Water line
19mm diameter PPR pipe
12mm diameter PPR Pipe
6.2 Sewer line & Drainage line
100mm diameter PVC pipe
75mm diameter PVC pipe
Catch basins
Septic tank
6.3 Fixtures:
Water closet
Lavatory
Sink
Shower
Water meter
Clean out
Floor drain
Faucet
Fittings & consumables
SUB-TOTAL
SUB-TOTAL
IX FINISHING WORKS:
9.1 60 x 60cm Ceramic Tiles
40 x 40cm Ceramic Tiles
30 x 30cm Ceramic Tiles
9.2 Gypsum Board Ceiling
9mm thk fiber cement board board on
19mmx50mm Double Furring spaced @0.60 m o.c.
b.w. and carrying channel
12mm thk fiber cement board board on
19mmx50mm Double Furring spaced @0.60 m o.c.
b.w. and carrying channel
9.3 Semi-gloss latex paint
9.4 QDE paint on ceiling
9.5 Consumables
SUB-TOTAL
X ROOF FRAME:
10.1 Base plate
10.2 1/4 x 2" x 2" Double Angle bar
10.3 1/4 x 1 1/2" x 1 1/2" Angle bar
10.4 2" x 4" C - Purlins
10.5 Consumables (welding rod etc.)
SUB-TOTAL
XI ROOF SHEETS:
11.1 Pre-painted G.I. long span roof
11.2 G.I. gutter
11.3 Spandrel Ceiling
11.4 Ridge roll
11.5 Insulation
11.6 Flashings
11.7 Consumables
SUB-TOTAL
84.81756
55.4714
0
268 536.00 kgs 30.00 5.00 16,080.00 2,680.00 18,760.00
117.00 bag
7.80 m3
15.60 m3
0 7.80 m3 3,000.00 1,350.00 23,400.00 10,530.00 33,930.00
59.00 bag
3.90 m3
7.80 m3
2.62 m3 3,000.00 1,350.00 7,860.00 3,537.00 11,397.00
24.00 bag
1.40 m3
2.70 m3
235,400.52 105,930.23 341,330.75
76.00 bags
4.30 m3
153,419.68 138,077.71 291,497.39
50.00 l.m. 50.00 120.00 2,500.00 6,000.00 8,500.00
20.00 l.m. 50.00 120.00 1,000.00 2,400.00 3,400.00
-
- 50,000.00 17,500.00 67,500.00
-
-
90.00 m2 250.00 180.00 22,500.00 16,200.00 38,700.00
15.00 m2 100.00 180.00 1,500.00 2,700.00 4,200.00
10.00 m2 80.00 180.00 800.00 1,800.00 2,600.00
-
80.00 m2 150.00 100.00 12,000.00 8,000.00 20,000.00
I EARTHWORKS:
II RE-BARS:
2.1 Column footing 712.90 kgs 30.00 5.00 21,386.88 3,564.48 24,951.36
16mm Ø - Round Bar
2.2 Footing Tie beam 712.31 kgs 30.00 5.00 21,369.18 3,561.53 24,930.71
16mm Ø - Round Bar
10mm Ø - Round Bar
2.3 Columns 1,957.38 kgs 30.00 6.00 58,721.52 11,744.30 70,465.82
16mm Ø - Round Bar
10mm Ø - Round Bar
2.4 Beams 1,737.54 kgs 30.00 6.00 52,126.26 10,425.25 62,551.51
16mm Ø - Round Bar
10mm Ø - Round Bar
2.5 Wall footing 229.56 kgs 30.00 5.00 6,886.66 1,147.78 8,034.43
III FORMWORKS:
3.1 Staging & Scaffoldings 500.00 Bd.ft. 16.00 8.00 8,000.00 4,000.00 12,000.00
2x2 Plank Woods (Cocolumber)
Wood Nails
3.2 Footing Tie beam 51.28 m2 95.00 180.00 4,871.79 9,230.76 14,102.55
Wood Nails
3/4 Marine Plywood
3.3 Columns 162.00 m2 95.00 180.00 15,390.00 29,160.00 44,550.00
Wood Nails
3/4 Marine Plywood
3.4 Beams 83.49 m2 95.00 200.00 7,931.55 16,698.00 24,629.55
Wood Nails
3/4 Marine Plywood
SUB-TOTAL 36,193.34 59,088.76 95,282.10
V MASONRY WORKS:
5.1 6" CHB Wall 235.20 m2 250.00 120.00 58,800.00 28,224.00 87,024.00
5.2 4" CHB Wall 105.00 m2 250.00 120.00 26,250.00 12,600.00 38,850.00
5.3 Plain cement plaster 680.40 m2 75.00 120.00 51,030.00 81,648.00 132,678.00
2 faced plastering
SUB-TOTAL 136,080.00 122,472.00 258,552.00
VI PLUMBING WORKS:
6.1 Water line
19mm diameter PPR pipe 50.00 l.m. 150.00 120.00 7,500.00 6,000.00 13,500.00
12mm diameter PPR Pipe 20.00 l.m. 126.00 120.00 2,520.00 2,400.00 4,920.00
6.2 Sewer line & Drainage line
100mm diameter PVC pipe 50.00 l.m. 170.00 110.00 8,500.00 5,500.00 14,000.00
75mm diameter PVC pipe 10.00 l.m. 120.00 100.00 1,200.00 1,000.00 2,200.00
Catch basins 6.00 set 850.00 750.00 5,100.00 4,500.00 9,600.00
Septic tank 1.00 lot 9,000.00 5,000.00 9,000.00 5,000.00 14,000.00
6.3 Fixtures:
Water closet 2.00 set 4,500.00 500.00 9,000.00 1,000.00 10,000.00
Lavatory 2.00 set 3,500.00 500.00 7,000.00 1,000.00 8,000.00
Sink 2.00 set 2,500.00 750.00 500.00 1,500.00 2,000.00
Shower 2.00 set 5,000.00 500.00 10,000.00 1,000.00 11,000.00
Water meter 1.00 set 2,500.00 1,000.00 2,500.00 1,000.00 3,500.00
Clean out 4.00 pcs 250.00 150.00 1,000.00 600.00 1,600.00
Floor drain 6.00 pcs 350.00 150.00 2,100.00 900.00 3,000.00
Faucet 5.00 pcs 550.00 200.00 2,750.00 1,000.00 3,750.00
Fittings & consumables 1.00 Lot 10,000.00 10,000.00 10,000.00 10,000.00 20,000.00
SUB-TOTAL 78,670.00 42,400.00 121,070.00
IX FINISHING WORKS:
9.1 60 x 60cm Ceramic Tiles 360.00 m2 250.00 180.00 90,000.00 64,800.00 154,800.00
40 x 40cm Ceramic Tiles 240.00 m2 100.00 180.00 24,000.00 43,200.00 67,200.00
30 x 30cm Ceramic Tiles 120.00 m2 80.00 180.00 9,600.00 21,600.00 31,200.00
9.2 Gypsum Board Ceiling
9mm thk fiber cement board board on 81.00 m2 150.00 100.00 12,150.00 8,100.00 20,250.00
19mmx50mm Double Furring spaced @0.60 m o.c.
b.w. and carrying channel
12mm thk fiber cement board board on 10.00 m2 150.00 100.00 1,500.00 1,000.00 2,500.00
19mmx50mm Double Furring spaced @0.60 m o.c.
b.w. and carrying channel
9.3 Semi-gloss latex paint 500.00 m2 50.00 100.00 25,000.00 50,000.00 75,000.00
9.4 QDE paint on ceiling 100.00 m2 200.00 150.00 20,000.00 15,000.00 35,000.00
9.5 Consumables 1.00 Lot 10,000.00 10,000.00 10,000.00 10,000.00 20,000.00
SUB-TOTAL 192,250.00 213,700.00 405,950.00
X ROOF FRAME:
10.1 Base plate 16.00 pcs 200.00 75.00 3,200.00 1,200.00 4,400.00
10.2 1/4 x 2" x 2" Double Angle bar 2,000.00 kgs 70.00 18.00 140,000.00 36,000.00 176,000.00
10.3 1/4 x 1 1/2" x 1 1/2" Angle bar 900.00 kgs 96.00 18.00 86,400.00 16,200.00 102,600.00
10.4 2" x 4" C - Purlins 30.00 pcs 860.00 220.00 25,800.00 6,600.00 32,400.00
10.5 Consumables (welding rod etc.) 1.00 Lot 10,000.00 10,000.00 10,000.00 10,000.00 20,000.00
SUB-TOTAL 265,400.00 70,000.00 335,400.00
XI ROOF SHEETS:
11.1 Pre-painted G.I. long span roof 150.00 m2 350.00 120.00 52,500.00 18,000.00 70,500.00
11.2 G.I. gutter 10.00 l.m. 380.00 120.00 3,800.00 1,200.00 5,000.00
11.3 Spandrel Ceiling 20.00 m2 880.00 220.00 17,600.00 4,400.00 22,000.00
11.4 Ridge roll 47.10 l.m. 300.00 120.00 14,130.00 5,652.00 19,782.00
11.5 Insulation 90.00 m2 90.00 120.00 8,100.00 10,800.00 18,900.00
11.6 Flashings 20.00 l.m. 420.00 120.00 8,400.00 2,400.00 10,800.00
11.7 Consumables 1.00 Lot 2,000.00 1,000.00 2,000.00 1,000.00 3,000.00
SUB-TOTAL 106,530.00 43,452.00 149,982.00
XII CABINETS & CLOSETS 20.00 l.m. 3,500.00 2,500.00 70,000.00 50,000.00 120,000.00