Professional Documents
Culture Documents
Chapter 8: Scheduling: Learning Objectives
Chapter 8: Scheduling: Learning Objectives
Learning Objectives
Chapter Outline
8.0 The Introduction
Examine some scheduling techniques that have been found to be useful in
project management.
Risk analysis and management will be considered as an inherent feature of
all scheduling methods, and a simulation of a project schedule will be
demonstrated.
8.1 Background
66
i. It is a consistent framework for planning, scheduling, monitoring,
and controlling the project.
ii. It illustrates the interdependence of all tasks, work packages, and
work elements.
iii. It denotes the times when specific individuals and resources must
be available for work on a given task.
iv. It aids in ensuring that the proper communications take place
between departments and functions.
v. It determines an expected project completion date.
vi. It identifies so-called critical activities that, if delayed, will delay
the project completion time.
vii. It also identifies activities with slack that can be delayed for
specified periods without penalty, or from which resources may
be temporarily borrowed without harm.
viii. It determines the dates on which tasks may be started—or must
be started if the project is to stay on schedule.
ix. It illustrates which tasks must be coordinated to avoid resource
or timing conflicts.
x. It also illustrates which tasks may be run, or must be run, in
parallel to achieve the predetermined project completion date.
xi. It relieves some interpersonal conflict by clearly showing task
dependencies.
xii. It may, depending on the information used, allow an estimate of
the probability of project completion by various dates, or the date
corresponding to a particular a priori probability.
I. Terminology
A. Activity- A specific task or set of tasks that are required
by the project, use up resources, and take time to
complete.
B. Event- The result of completing one or more activities.
67
C. Network- The arrangement of all activities in a project
arrayed in their logical sequence and represented the arcs
and models.
D. Path- The series of connected activities between any two
events in a network.
E. Critical- Activities, events, or paths which, if delayed, will
delayed the completion of the project.
68
8.3 Risk Analysis Using Simulation with Crystal Ball
User-friendly software such as Microsoft Project, Crystal Ball, and Excel that
do similar jobs has made the use of tools.
Gathering the input data for the software is usually more difficult than
entering and processing it, but it is doable.
69
Chapter Summary
Schedule is the conversion of a project action plan into an operating
timetable. It serves as the basis for monitoring and controlling project
activity and taken together with the plan and budget, it is probably the major
tool for the management of projects.
The most common approach to project scheduling is the use of network
techniques such as Program Evaluation and Review Technique (PERT)
and Critical Path Method (CPM).
One of the oldest but still one of the most useful methods of presenting
project schedule information is the Gantt chart. It shows planned and actual
progress for a number of tasks displayed as bars against a horizontal time
scale.
Gantt chart was developed around 1917 by Henry L. Gantt, a pioneer in the
field of scientific management.
Networks are usually constructed from left to right, indicating activity
precedence and event times as the network is constructed. Through use of
the network, critical activities and events are identified, early and late activity
start times are found, available slacks for each activity are determined, and
probabilities of project completion by various times are calculated.
Precedence Diagramming consists of the following; Finish to Start, Start to
Start, Finish to Finish and Start to Finish. Precedence Diagramming is an
AON network method that easily allows for these leads and lags within the
network.
The model's output is used to build a statistical model of all the results. This
distribution indicates the decision's risk profile. The risk profile is addressed
together with the strategies and policies of the holding company, the
customer's preferences, and a few other considerations when making the
decision.
Risk Analysis using Simulation with Crystal ball means is that life with
projects is characterized by uncertainty like the time required, the cost and
availability, the success of the research, the wishes of the client, the
competitor’s actions as well as the vagaries of the weather.
Crystal Ball is an outstanding software program that enables simulation
relatively convenient tool for simulating a project. It is also possible to use
Excel to simulate tasks schedules with constructed services of their own.
They choose Crystal ball because it is a bit better user-friendly, but mostly
because it can display its outcome in a variety of ways about formats. By
reacting immediately to changes in the parameters of a simulation, Crystal
ball also enables the customers to connect with the software.
70
Assessment
A. Identify the following.
1. The two ways of illustrating a network: placing the activities on the arcs or on
the nodes.
2. It used deterministic activity time estimates and was designated to control both
the time and cost aspects of a project. In particular, time/cost trade-offs.
3. Originally, it was strictly oriented to the time element of projects and used
probabilistic activity time estimates to aid in determining the probability that a
project could be completed by some given date.
4. A manner of illustrating multiple, time-based activities on a horizontal time
scale.
5. A combination of interrelated activities and events depicted with arcs and
nodes.
71